2020-07-07 P&E Agenda - Item 3 - Attachment 1 - TNC Project Management Plan
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn To improve the environmental health of the Noosa River Estuary through active restoration
Project Goal and conservation activities that engage the Noosa Community in meaningful conservation
and support economic and community wellbeing.
Expected
Party
completion date
responsible
Objectives Deliverables (from 1 July 2019 Measurable outcomes
for
unless otherwise
Deliverable
stated)
and (if acceptable) approved
by Noosa Council.
6 monthly status and
(A1.6) 6 monthly status and
progress reports, and
progress reports which
financial statement, are
address, at a minimum:
produced, endorsed by the
Progress against
Technical Advisory Group,
deliverables and monitoring
and provided to NSC, within
and evaluation report. 6 monthly TNC
30 days of end of each six (6)
6 monthly financial
month period. Reports and
statements including
financial statements due at
a statement of Project
the end of the financial year
income/funding and
may be included with annual
expenditure
reports and the final report.
(A2.1) Shellfish restoration
suitability model Restoration suitability model
incorporating physical which incorporates industry,
12 months
parameters of oysters and Kabi Kabi knowledge and TNC
public and industry usage, public interests.
A-2: Site
access etc. to identify
selection
priority sites for restoration.
(A2.2) Obtain necessary
Identify suitable
State government
restoration sites Outcomes:
permits/authorities
for Phase II and (a) Obtain all required State
including particular
Phase III and government
resource allocation
appropriate permits/authorities for
authority, for shellfish 13(a) - TNC
shellfish oyster ecosystem
ecosystem restoration
substrate design 18 months restoration.
Obtain necessary local
and (b) Obtain all required Local
government 13(b) –
configurations government
permits/approvals including NSC
that minimize permits/approvals for
in particular fisheries
estuary-user oyster ecosystem
development approval for
conflict whilst restoration are obtained.
oyster ecosystem
optimizing
restoration
rehabilitation
(A2.3) Community, industry
Records of public and
and stakeholder
stakeholder consultation,
consultation sufficient to
18 months including one-on-one TNC
gain majority support for
meetings, open forums,
oyster ecosystem
media, etc.
restoration locations.
13
BRING BACK THE FISH: PROJECT MANAGEMENT PLAN
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.