2020-07-07 P&E Agenda - Item 3 - Attachment 1 - TNC Project Management Plan
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawn To improve the environmental health of the Noosa River Estuary through active restoration
Project Goal and conservation activities that engage the Noosa Community in meaningful conservation
and support economic and community wellbeing.
Expected
Party
completion date
responsible
Objectives Deliverables (from 1 July 2019 Measurable outcomes
for
unless otherwise
Deliverable
stated)
(A5.6) Promote Noosa
Council’s Noosa River Plan
Presentation to at least one
and shellfish restoration 36 months
national and one TNC & NSC
project in at least one
international conference.
national and one
international conference.
(A5.7) Promote Noosa
Council’s Noosa River Plan
and shellfish restoration
project to corporate, A number of new corporate/
philanthropic and Ongoing for government/ philanthropic
state/federal government duration of alliances and new in-kind TNC & NSC
audiences to establish project support/financial funding
further support for contributions.
conservation activities that
support the Noosa River
Plan.
2.4 Project stakeholders, roles and responsibilities and team structure
Project stakeholders
The innovative and applied nature of the TNC-NSC partnership and genesis of the Bring Back the Fish project has
resulted in significant government, community, private sector and academic interest. The below list of project
stakeholders is not exhaustive and will be updated regularly throughout the project:
Government and Community
• Noosa Shire Council – Project Supporter, Technical Advisor
• Tourism Noosa - Technical Advisor, Community Partner
• Queensland Government Department of Agriculture & Fisheries – Regulator, Technical Advisor
• Maritime Safety Queensland – Regulator, Technical Advisor
• Queensland Government Department of Environment & Science – Regulator, Technical Advisor
• Queensland Government Department of Natural Resources, Mines and Energy – Regulator, Technical Advisor
Community
• Kabi Kabi – Traditional Owner, Technical and Cultural Advisor
• The Thomas Foundation – Project Supporter
• Australian Marine Conservation Society – Project Supporter
• Noosa Parks Association – Community Partner
16
BRING BACK THE FISH: PROJECT MANAGEMENT PLAN
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLarge file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.