                                             Officer:            Tracy Jones
                                             Direct Telephone:   (07) 5449 5228
                                             Response Address:   PO Box 141, Tewantin QLD 4565
                                             Email:              [email protected]
                                             Our Reference:      2007/256
                                             Your Reference:     6631
23 July 2009

Bunnings Properties Pty Ltd
CARE Conics Pty Ltd
PO Box 1559
FORTITUDE VALLEY QLD 4006




Dear Sir

                              Negotiated Decision Notice
                                  Integrated Planning Act 1997

I refer to your application and the representations you made in respect to the Decision Notice. On 16
July 2009 Council decided your representations.
Details of the negotiated decision are as follows:

1     APPLICATION DETAILS

 Application No:                 2007/256
 Street address:                 178 Eumundi Noosa Road, Noosaville
 Real property description:      Lot 80 SP 211687
 Planning Scheme:                The Noosa Plan

2     DECISION DETAILS
Council on 10 July 2008 decided to issue the following type of approval:-
    Preliminary Approval for Material Change of Use - Bunnings Warehouse
In relation to representations, Council on 16 July 2009 decided to grant a Development Permit and:
A.    Agree to delete Condition 24.
B.    Agree to change Conditions 1, 10, 11, 14, 22, 23, 37, 41, 45 & 50.
C.    Refuse to change/delete Conditions 8, 15, 16, 18, 19, 35, 51 & 62 for the following reasons:
      Condition 8
      The relevant Operational Works application forms and fee to allow for the assessment of the
      non-complying proposed signage have not been submitted with this application.

      Condition 15
      A lesser number of shower facilities will not adequately cater for expansion or overflow
      demands of cyclists. It is undesirable to have integrated facilities for both males and females,
      which would result from a lesser number of shower facilities being provided within the
      development.


                                                                                                1 of 20
Full text of the other 19 pages

Page 2

                                                                                        2007/256




     Condition 16
     The scale of the proposal plans does not allow for compliance with roof pitch and eaves
     requirements to be accurately determined.

     Condition 18 & 19
     The bond is required to secure performance of all conditions of the approval and the bond
     amount is reasonable given the amount of works required to be undertaken by this approval.

     Condition 35
     The condition is intended to ensure that any spaces that are intended to be used by staff are
     not utilised in error by a customer, with staff spaces in accordance with AS/NZS 2890.1:2004
     being a lesser width and therefore more difficult to access and unsuitable for customer use.

     Condition 51
     The condition ensures that the existing runoff volumes are maintained as much as is
     practicable, as the development must not increase or decrease runoff to the extent that it
     adversely affects the downstream ecosystem.

     Condition 62
     The development (staff and customers) will generate an increase in the need for public
     transport facilities in the area. The contribution amount is proportional to the cost of providing
     public transport facilities to service the increase in demand generated by the development.
D.   Amend Conditions 16, 21 & 62 and Advice Conditions 1 & 2.
E.   Include one additional Condition 75.
F.   Advise the applicant that Council does not agree to:-
      1.    Offset the cost of roadworks against the Coastal Major Road Network Infrastructure
            Charges Plan (CMRNICP) contributions as no works are planned for this roundabout or
            road diversion in the current CMRNICP nor in the Draft PIP and roadworks are
            necessitated by the increase in traffic generated by the Bunnings Warehouse;

      2.    Offset the cost of pathway works as the section of path along the Eumundi Noosa road
            frontage has been constructed by Council.

3    RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.

4    ASSESSMENT MANAGER CONDITIONS

Land Use
1.   Development undertaken in accordance with this approval must generally comply with the
     approved plans of development. The approved plans are numbered:
      Plan         /      Rev.    Plan / Document Name                       Date
      Document No.
      030                 P7      Site Plan – John R. Brogan &               27.05.09
                                  Associates
      100                 C       Ground Floor Plan – John R. Brogan &       01.09.08
                                  Associates
      101                 C       Mezzanine Floor Plan – John R.             01.09.08
                                  Brogan & Associates

                                                                                          2 of 20

Page 3

                                                                                         2007/256



     110                 C       Roof Plan – John R. Brogan &                 01.09.08
                                 Associates
     120                 C       Sections – John R. Brogan &                  01.09.08
                                 Associates
     121                 C       Sections – John R. Brogan &                  01.09.08
                                 Associates
     130                 D       Elevations – John R. Brogan &                14.10.08
                                 Associates
     131                 D       Coloured Elevations – John R. Brogan         14.10.08
                                 & Associates
     and as may be amended by these conditions.
2.   The development must be undertaken and operated in a manner that causes no detrimental
     effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
     lighting nuisance or other emissions.
3.   Existing trees on the site and within road reserves are to be retained, except where required to
     be removed due to building operations or the conduct of the approved use. These landscape
     plans required to be submitted are to denote areas of existing vegetation or existing trees
     proposed or required to be retained.
4.   The open space and setback areas are to be landscaped in accordance with Council’s Policy
     on Landscaping Guidelines and a properly prepared landscape plan. Such landscaping is to
     be completed prior to the premises being occupied and maintained at all times thereafter and
     shall include:-
     4.1.   Provision for planting of one native canopy tree every 6 car parking spaces within the
            car parking area.
     4.2.   Retention of existing native trees along the Eumundi Noosa Road frontage and those
            on the corner of Gateway Drive and Eumundi Noosa Road.
     4.3.   Planting to visually screen the outdoor nursery area and car parking spaces.
     4.4.   Screening of any electrical transformers or the like from the road frontages.
5.   All cut and fill works shall be finished in a manner that will ensure works visually integrate with
     the surroundings to the reasonable satisfaction of Council and include sloped batters to all
     road frontages, rather than retaining walls.
6.   Cleared vegetation is to be suitably processed by one of the following methods and removed
     from the site:-
     6.1.    Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
     loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a minimum of 10
     metres between edges of heaps.
     6.2.   Disposal for firewood.
     6.3.   Disposal for landscaping purposes.
     6.4.   Transport to alternative site for breaking down materials provided that all necessary
            permits have been obtained to allow the alternate site to be used for this purpose.
     6.5.   The disposal method for clearing works is to be submitted in conjunction with an
            application for a Development Permit for Operational Work. The Applicant is advised
            that other methods may be considered provided full details of the method are
            submitted.
     6.6.   The Applicant is advised that burning off is an unacceptable method of disposal.



                                                                                          3 of 20

Page 4

                                                                                        2007/256



7.    The area identified as ‘water sensitive landscape feature’ on Drawing No. 030 Amendment No.
      G prepared by John R Brogan & Associates and dated 3 April 2008 shall be dedicated as
      parkland, at no cost to Council.
8.    Any advertising sign or device is to comply with Council's policies on advertising.
9.    All goods are to be displayed on site within the property boundaries and/or on the premises
      approved for the use.
10.   All storage areas shall be screened from the street and adjoining properties by landscaping, or
      suitable screening devices where landscaping screening cannot be achieved.
11.   All materials stored outside of the building, excluding the nursery and receiving canopy areas,
      shall not exceed half the height of the on-site building.
12.   All mechanical plant and equipment shall be designed and located to visually integrate with
      the building design to the reasonable satisfaction of Council.
13.   All hot water systems installed shall be either solar systems; electric heat pump systems; or
      gas systems (LPG or natural).
14.   Secure bicycle racks shall be provided on site to accommodate a minimum of 20 bicycles
      comprising 4 stainless steel hoops or U rails for customers and 10 U rails or wall parking
      hooks within a secured area for employees. The proposed bicycle racks shall be identified on
      the landscaping plans and shall be located to the reasonable satisfaction of Council.
15.   End of trip facilities shall be provided within the approved building at a minimum of 30 lockers;
      and 4 showers, with change rooms.
16.   The building shall comprise a roof pitch of a minimum of 5 degrees and provision made for
      eaves a minimum of 600mm wide to at least that part of the building fronting Gateway Drive
      and Eumundi Noosa Road.
17.   The proposed development shall have all kitchen, laundry and bathroom fittings that comply
      with the AAA Water Conservation Rating System as defined by the AS/NZS 6400 (Water
      Efficient Products - Rating and Labelling 2003) and AS/NZS 3500 (National Plumbing and
      Drainage Standard Part 1.2), with toilets to comply with the AAAA Water Conservation Rating
      System. All tap ware and shower roses shall not exceed a maximum flow of 9 litres per min.
      Dishwashers and washing machines are excluded from this requirement.
18.   Security in the form of a cash bond or trading bank guarantee to the sum of $250,000 must be
      submitted, to secure performance of all conditions of this approval, prior to the issue of a
      Development Permit for operational works. The cash bond or trading bank guarantee will be
      returned on performance of the conditions of approval less any costs incurred by Council in
      respect of enforcing performance of this permit.
19.   The requirements of this development approval are to be effected, prior to the use of the
      premises. Council reserves the right to call upon the bond or guaranteed sum referred to in
      this approval to effect compliance with conditions.
20.   The developer must obtain all of the other Development Permits referred to in the Decision
      Notice, prior to obtaining a Development Permit for Building Works.
21.   The Development Permit for a material change of use of premises lapses if the use has not
      happened by 16 July 2013, unless an application to extend the currency is approved by
      Council.




                                                                                            4 of 20

Page 5

                                                                                       2007/256



Land Development

Roadworks/Intersection Construction
22.   The applicant shall upgrade the Rene Street – Eumundi Noosa Road roundabout and provide
      a new road reserve generally in accordance with plans CB-0849-F01 Rev I dated 27 May
      2009, CB-0849-F03 Rev C dated 27 May 2009, CB-0849-F04 Rev C dated 27 May 2009, CB-
      0849-F05 Rev B dated 27 May 2009, CB-0849-F06 Rev A dated 27 May 2009, CB-0849-
      TRN01 Rev C dated 27 May 2009 and CB-0849_TRN02 Rev C dated 27 May 2009. The
      works shall be designed and constructed to Council standards for Arterial Roads.
23.   The applicant shall modify Gateway Drive and provide a new road reserve generally in
      accordance with plans CB-0849-F01 Rev I dated 27 May 2009, CB-0849-F02 Rev D dated 2
      June 2009, CB-0849-F05 Rev B dated 27 May 2009, CB-0849-F06 Rev A dated 27 May 2009,
      CB-0849-TRN01 Rev C dated 27 May 2009 and CB-0849_TRN02 Rev C dated 27 May 2009.
      The works shall be designed and constructed to Council standards for Arterial Roads. All
      associated retaining walls, safety rails and fencing shall be located wholly within the proposed
      new lot boundaries.
24.   Deleted.
25.   The frontages of the development site affected by road improvements shall be upgraded by
      providing kerb & channel, bitumen road widening and landscaping improvements to the
      footpath. All associated and ancillary work including pavement correction to the existing
      pavement, drainage works, modification of the footpath, and adjustments to the existing
      infrastructure shall be undertaken to complete the roadworks widening.
Vehicle Access
26.   Vehicular accesses to the development shall be located generally as indicated on BMD
      Consulting Drawing No. CB-0849-F01 Rev B dated 10 April 2008, except if relocation is
      required as a result of the amended external roadworks plan.
27.   All driveways shall be designed and constructed to Council’s design standards and to grades
      that prevent vehicles from scraping and/or bottoming whilst also allowing pedestrians
      movements along the footpath without any step or level difference. Should any driveways be
      constructed to grades that do not comply with AS2890.1-2004 and AS2890.2-2002, Council
      will require that the driveway be removed and reconstructed to levels that do comply.
      Please note, a step between the driveway and the footpath shall be avoided, as it is preferred
      to have the footpath continue at a constant grade to minimise the potential for pedestrians to
      trip or fall.
28.   To ensure pedestrian safety between vehicles exiting the site and pedestrians on the footpath,
      the driveway and any associated fencing or vegetation near the driveway shall comply with the
      minimum sight line requirements as defined in AS2890.1, section 3.2.4. The applicant shall
      demonstrate compliance by illustrating these sight lines on the plans submitted for both
      Operational Works approval and Building Works approval.
29.   All vehicles shall enter and leave the site in a forward direction.
Loading Areas
30.   Loading zones, delivery areas shall be generally as shown on John Brogan & Associates
      Drawing No. 030 – G and sized to accommodate the appropriate vehicle expected to utilise
      the space.
Car Parking

Off Street
31.   Carparking shall be provided within the site generally as shown John Brogan & Associates
      Drawing No. 030 – G, except as modified herein.
                                                                                         5 of 20

Page 6

                                                                                         2007/256



32.   A minimum of 220 uncovered carpark spaces and 8 motorcycle spaces shall be provided on
      site, including clearly defined disabled carpark spaces pursuant to the Building Code of
      Australia (in accordance with AS2890.6).
33.   The carparking area shall be designed to comply with the provisions of AS 2890.1-2004 for
      User Class 3A and Class 1 for Staff spaces with allowance for vehicles to enter and leave the
      site in a forward gear and with a minimum head clearance (headroom) at any point of 2.2m.
      Disabled spaces will be designed in accordance with AS2890.6.
34.   All carparking shall be kept, maintained and line-marked in a condition fit for use.
35.   All staff carpark spaces shall be clearly defined by line marking each space with the words
      “Staff Parking Only” and by sign posting each space with a similar wording.
Frontage Works
36.   Footpath improvements such as topsoiling, grassing, and tree planting are required to the
      street frontages of the site in accordance with Planning Scheme Policy PSP03 Landscaping
      Plants & Guidelines. Grass shall be couch, free of weeds. Shade trees shall be provided
      along the pathways that are constructed.
37.   Any sections of the existing 3.0m wide concrete path along the Eumundi Noosa Road frontage
      of the site that are damaged or made redundant due to the construction of the necessary
      roadworks shall be replaced by the applicant and a new 2.0m wide concrete path shall be
      constructed along the new road and Gateway Drive frontage of the site. The path works shall
      be at no cost to Council, in accordance with Council’s design standards and to an alignment
      that protects any significant vegetation or any underground service.
38.   Pram ramps shall be installed wherever needed to direct pedestrians across the road and at
      the roundabout, but the gaps in the islands shall be at road surface level and without ramps.
39.   All paths, pram ramps, driveways and parking areas shall be designed and constructed to
      ensure pedestrian safety using non-slip materials, to produce an evenly graded surface finish.
40.   All redundant vehicular crossings to the site shall be removed and replaced by kerb & channel,
      footpath paving and landscaping such as trees and grasses in accordance with Council’s
      Standard specifications prior to commencement of the use permitted by this permit.
41.   The developer shall provide a safe connection for pedestrians and cyclists from Eumundi
      Noosa Road and Gateway Drive into the development site as shown on the approved plans of
      development.
Power
42.   The applicant shall be responsible for the relocation of all power services required to be
      moved as a result of the works associated with this development.
Environmental Management Plan
43.   An Environmental Management Plan shall be submitted to Council in conjunction with any
      Operational Works application addressing:
      43.1. Construction Management including:
              43.1.1.   Erosion and Sediment Controls;
              43.1.2.   Traffic Management;
              43.1.3.   Dust and Noise nuisance;
              43.1.4.   Haulage Routes.
      43.2. Acid Sulfate Management; and
      43.3. Operational Surface Water Management.

                                                                                             6 of 20

Page 7

                                                                                        2007/256



Roof Water & Stormwater Drainage
44.   Roof runoff from any new building shall be directed to a rainwater storage system or tank that
      is installed to ensure water from the tank is used for external uses (such as watering gardens,
      irrigation, ornamental ponds, water features, outdoor cleaning, etc) and for use in flushing of
      toilets internal to the building.   All rainwater tanks are to be designed and installed in
      accordance with the Queensland Development Code (QDC), Part 25 – Rainwater Tanks, and
      shall be part of the plumbing application in conjunction with the building approval. The
      location and capacity of the tanks shall be in accordance with the approved Surface Water
      Management Plan (SWMP) and be clearly shown on the plans submitted for Operational
      Works approval and any overflow shall be directed as required by the SWMP.
45.   All stormwater drainage (including roof water overflow from the rainwater storage system)
      shall be collected and discharged so there is no net increase in stormwater runoff from the site
      for up to and including a Q100 rain event.
46.   Stormwater drainage permitted to drain from the site shall be discharged to Council’s existing
      drainage structures in Gateway Drive. If required, the applicant shall upgrade the existing
      drainage system. Plans of the drainage design shall be prepared by a Registered
      Professional Civil Engineer and submitted to Council prior to obtaining a Development Permit
      for Operational Works. A Development Permit for Building Works shall not be granted until a
      Development Permit for Operational Works has been issued in regard to the drainage
      scheme.
47.   As the site is proposed to be filled, appropriate stormwater drainage pipes shall be installed or
      overland flowpaths created within the site to collect and discharge stormwater runoff from all
      adjoining properties to prevent additional ponding/flooding on these properties.
48.   All site stormwater drainage shall be by means of a gravity system.
49.   All stormwater drainage lines including inter-allotment drainage shall be inspected by closed
      circuit television (CCTV) prior to commencement of the approved Use.
      CCTV inspection will be carried out by Council's CCTV contractor and arranged by Council
      following satisfactory completion of construction works. The developer will be responsible for
      the full cost of CCTV inspection, including any additional inspection necessary following defect
      identification and rectification. This charge is payable prior to the issue of Operational Works
      approval and will be determined on the unit rate basis current at the time of approval.

Surface Water Management
50.   To ensure that polluted run-off does not enter Council’s stormwater drainage system or the
      downstream ecosystem, stormwater run-off from the carparking areas and the driveways shall
      be treated and maintained in accordance with an approved Surface Water Management Plan.
      The Cardno Surface Water Management Plan dated 8 February 2008 shall be amended to
      reflect the conditions of this approval and the modified layout approved herein.
      The design, construction and maintenance of treatment measures shall be in accordance with
      the Healthy Waterways Water Sensitive Urban Design Technical Design Guidelines for South
      East Queensland (2006 or more recent edition).
      The amended Surface Water Management Plan shall include a requirement for monitoring to
      be undertaken for a period of three years after the commencement of the use. Monitoring
      results shall be submitted to Council on a quarterly basis for their records in digital form.

      Monitoring results presented to Council shall include:

           qualitative statements detailing the presence/absence of scour, sediment and litter
             build-up within bioretention basins and inlet and surcharge pits; and
           results of water quality monitoring undertaken during rain events up to a Q3 month
             event that create a suitable amount of runoff to allow for the collection of water
                                                                                          7 of 20

Page 8

                                                                                         2007/256



             samples. Water samples shall be collected and/or sampled for pH and nitrogen,
             phosphorus and suspended solids concentrations in accordance with the Queensland
             Water Quality Sampling Manual (3rd edition • December 1999 or more recent edition).
             Water samples shall be analysed at a NATA accredited laboratory for nitrogen,
             phosphorus and suspended solids.

      Rectification measures for non-compliance with water quality objectives shall be included in the
      Environmental Management Plan.
51.   The amended Surface Water Management Plan shall demonstrate that the ecosystem located
      downstream will not be adversely affected by water harvesting and detention proposed.
Sewer Mains
52.   The site shall be connected to Council’s existing sewerage reticulation systems and be
      constructed in accordance with Council’s standards and requirements at no cost to Council.
      This may require the construction of sewer mains external to the site to connect to an
      approved connection point.
53.   Any existing sewer mains that traverse the site and are no longer required shall be removed
      and capped in accordance with Council’s requirements.
Town Water Supply
54.   The site shall be connected to Council’s existing town water supply and be constructed in
      accordance with Council’s standards and requirements at no cost to Council.
55.   The water connection to the water reticulation system shall extend to the property boundary
      and be metered. All fees for the supply of water meters shall be paid to the Council.
56.   The water meter must be located outside the property boundary and in an easily assessable
      location to facilitate unhindered reading by Council and/or Council’s contracted water meter
      readers, and not behind fences or locked gates. In this regard approval of the water meter
      configuration and location must be obtained from Council’s Water & Sewerage Capital Works
      Manager prior to lodgement and approval of hydraulic drawings.
Earthworks
57.   Filling works required on site shall be carried out in accordance with Section 3.8 of Council’s
      Engineering Design Standards Manual and so as not to cause the additional ponding of water
      on any adjoining lands or the blockage of, or interference with, any natural watercourses.
      Detailed site surveys indicating natural surface levels and contours of the adjoining properties
      must be provided with the application for a Development Permit for Operational Works for
      Filling and Drainage.
      This may require the design and construction of drainage pipes and/or an overland flow-path
      within the development site that caters for drainage from the adjoining sites for a design storm
      with an Average Recurrence Interval of 1 in 100 years. A private easement for the Drainage of
      Water encompassing the drainage pipes or overland flow-path will also be required. In this
      regard a Development Permit for Operational Works shall be obtained.

      Should evidence be provided to Council indicating that no additional ponding of stormwater
      will occur on the adjoining properties the requirement for the drainage pipes, overland flow-
      path and easement shall not apply.
58.   Earthworks carried out on site shall not affect the structural integrity of any of the existing
      fences or structures that border the development site. Fences that are affected shall be
      replaced prior to the Building Certifier issuing the Certificate of Classification. In this regard
      any fences to be replaced shall be clearly shown on the plans submitted for Operational
      Works approval.


                                                                                          8 of 20

Page 9

                                                                                         2007/256



Acid Sulfate Soils
59.   As the site is located below the 20m AHD and above the 5m AHD, any excavation works
                           3
      consisting of 100m or greater which extends below 5m AHD will need to be carried out in
      accordance with State Planning Policy 2/02 Planning and Managing Development Involving
      Acid Sulfate Soils. In this regard appropriate testing and supporting documentation prepared
      by a suitably qualified specialist shall be submitted to Council for approval prior to obtaining a
      Development Permit for Operational Works.
Site Stability
60.   A Geotechnical Engineer or similar qualified expert shall assess the soil condition on site,
      determine the soil classification, establish whether any measures are required to protect the
      stability of adjoining buildings and/or structures and/or land, and make recommendations on
      the type of foundation system(s) best suited for the proposed development. The
      recommendations of this report shall be incorporated into the design and construction of the
      proposed development.
Erosion and Sediment Control
61.   Any person acting on this permit shall prevent erosion and sediment export from leaving the
      site. Site control measures such as silt fencing, controlled gravel access to the site and
      controlled disposal of waste, will be necessary.
      In this regard plans detailing the methods of controlling erosion and sediment are required to
      be submitted to the Council for approval prior to obtaining a Development Permit for
      Operational Works.

Contributions Towards Council Infrastructure
62.   Monetary contributions shall be paid to Sunshine Coast Regional Council towards the cost of
      providing and/or upgrading various infrastructure at the rates applicable at the time of
      payment. An estimate only of the contribution amounts under the current Council policies and
      requirements is outlined in the table below:


         Contribution Required For:                                                        Amount:
         PSP12 – Public Open Space Contributions (Park)
                                                                                           $0
         (Land dedicated in lieu per condition 7)

         PSP16 – Sewerage Headworks Contributions                                          $36,143

         PSP17 – Water Supply Headworks Contributions                                      $10,689
         PSP20 – Pathway Trunk Network Contributions                                       $14,441
         Contribution towards cost of providing and/or upgrading the two bus shelters
                                                                                           $10,000
         on Eumundi Noosa Road that will service the development.
         TOTAL Contribution Amount =                                                       $71,273

         Please note, that these amounts are all subject to variations in the Consumer Price Index,
         All Groups Brisbane from March 2009 until the date of payment.


       All contributions must be paid prior to the commencement of the use.




                                                                                          9 of 20

Page 10

                                                                                       2007/256



General
63.   Cleared vegetation is to be suitably processed by one of the following methods and removed
      from the site:-
      63.1. Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
             loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a
             minimum of 10 metres between edges of heaps.
      63.2. Disposal for firewood.
      63.3. Disposal for landscaping purposes.
      63.4. Transport to alternative site for breaking down materials provided that all necessary
             permits have been obtained to allow the alternate site to be used for this purpose.
      The disposal method for clearing works is to be submitted in conjunction with an application
      for a Development Permit for Operational Work. The Applicant is advised that other methods
      may be considered provided full details of the method are submitted.

      The Applicant is also advised that burning off is an unacceptable method of disposal.
64.   A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
      specifications for all engineering works that will become Council infrastructure, which shall be
      submitted in conjunction with an application for a Development Permit for Operational Works.
      To avoid conflict with underground pipes or services, all existing and proposed services
      required by the development shall be shown on the plans.
65.   The Construction Management Plan shall incorporate practices to minimise the risk of damage
      occurring to Council services.
66.   Any damage caused to any public utility during the course of construction shall be repaired to
      Council’s standards and at no cost to Council.
67.   Any alteration of any public utility or other facilities necessitated by the development of the
      land or associated construction works external to the site shall be at no cost to Council.
68.   The transportation of all materials to and from the site shall be undertaken in a manner such
      that no particle matter escapes onto a public road. All vehicles carrying materials either to or
      from the site shall be covered to prevent materials including dust being windblown from the
      vehicle.
Environmental Health
69.   The developer must provide waste storage and disposal facilities in accordance with Planning
      Scheme Policy No. 9 “Waste Management Multi-Dwellings and Commercial and Industrial
      Premises”, including an external imperviously paved area correctly sized for all refuse and
      recycling containers and suitably screened from public places and neighbouring properties. A
      bin wash area is required with a cold-water tap, hose and drain outlet connected to sewer, via
      a bucket trap. The drain outlet is to be designed to prevent storm water entry to the sewerage
      system and this can be achieved with a nib wall 50mm high and up to 700mm x 700mm wide
      (max 0.5m²), or alternatively the waste area can be roofed, or any other design approved by
      Council.
70.   The development must allow refuse-loading areas to be located off street. All vehicles
      associated with the collection of waste/recyclables, shall enter and leave the site in a forward
      direction.
71.   A Waste Management Plan (Operational) in accordance with Planning Scheme Policy No. 9
      “Waste Management Multi-Dwellings and Commercial and Industrial Premises”, must be
      submitted for the day-to-day operation of the development and approved by Council’s Health
      Section prior to issue of development permit for operational works.

                                                                                        10 of 20

Page 11

                                                                                        2007/256



      It is critical that waste areas are properly planned. A copy of Planning Scheme Policy No. 9
      explaining exactly how to predict waste quantities and design waste areas is available from
      Council and the web. The Plan shall include the following information: -
          The types of waste that will be generated from the activities approved within the
            development.
          Estimated volumes or tonnage of both recyclables and waste generated.
          Methods to be used for dealing with garden waste.
          Initiatives to minimize waste either by waste prevention, reduction, re-use or recycling.
          Description of procedures for getting all waste to the bins; the storage of bins and the
            collection of bins by the contractor.
          A description of the design details of waste storage and recycling areas including size,
            location, elevation and floor plan, methods of bin washing and system to prevent storm
            water getting into sewer via the bin wash.
          A description of types and volume of waste storage containers to be used.
          The waste and recycling storage area shall include the provision of containers for all
            waste and recycling materials including putresable matter, non-recycling waste, paper/
            cardboard, glass, aluminum/steel cans, waste oil, styrofoam boxes, etc, and bin
            washing facilities connected to sewer.
          A detailed description of vehicular access to collect waste. Where collection is off
            street, access must allow vehicles to enter and leave the site in a forward direction.
72.   A Waste Management Plan (construction and demolition) shall be submitted prior to
      demolition, removal or relocation of any building other than a shed.
      A Waste Management Plan (construction and demolition) is also required for construction of
      15 or more dwelling units or for any business use of greater than 500m².

      Waste Management Plans (construction and demolition) are required to be submitted in
      accordance with Planning Scheme Policy 11, Waste Management Plans see table below.

      Waste storage areas are to provide for adequate separation of all reusable, recyclable and
      waste materials. These shall be located so that they are convenient and safe to use. (Refer to
      Noosa Council Waste Management Code)
      The Plan shall contain the following information:
          The site area for the storage and separation of waste is to be shown on the plan
            drawings accompanying the application.
          A waste management table as indicated below is to be completed showing how waste
            material is to be segregated - recycled – reused or disposed.




                                                                                         11 of 20

Page 12

                                                                                      2007/256



           MATERIALS ON-SITE               DESTINATION
                                           Re-use and Recycling                    Disposal
           Expected    waste   Estimated   On-site            Off-site             *specify
           materials           volume      *specify proposed *specify              contractor    and
                               (m³)        re-use or on-site contractor      and   landfill site or
                                           recycling          recycling outlet     other     disposal
                                           methods                                 site
           Excavation
           material
           Green waste
           Bricks
           Concrete
           Timber-please
           specify
           Plasterboard
           Metals - please
           specify
           Asbestos
           Other - please
           specify

      Note * If a demolition contractor is undertaking works, then the Waste Management table is to
      be completed by the demolition contractor.

      The purpose of the Waste Management Plan is to facilitate the segregation of waste for the
      effective reuse and recycling of such materials. Additionally Council rewards those who
      segregate waste by significantly reducing disposal fees at the landfill some items are free.
      Higher gate fees are charged for loads of mixed waste.
73.   Noise emission from mechanical equipment (air conditioners, refrigeration equipment or pool
      pumps etc) shall comply with the following requirements:
      The equipment shall be installed and located in a manner that prevents excessive noise in
      accordance with Council’s Local Law No. 12 - Control of Nuisances. Infringement Notices (on-
      the-spot fines) may apply for offences.

      A person must not use equipment on any day if it makes or causes noise to be made –

      From 10pm to 7am: More than the lower of either –
             40 dB(A)
             3 dB(A) above the background noise level
             No audible noise for pool pumps apply during these hours.
      From 7am to 7pm: More than the lower of either –
             50 dB(A)
             5 dB(A) above the background noise level
      From 7pm to 10pm: More than 3 dB(A) above the background noise level.
74.   Submission of written certification from a suitably qualified person confirming that the noise
      levels from all mechanical equipment comply with the cause above when measured at either
      the residential boundary or outside the most exposed part of an affected building, whichever is
      the closest to the equipment.


                                                                                       12 of 20

Page 13

                                                                                       2007/256



       The assessment and certification is required immediately after installation of the equipment
       and prior to any occupation of the building, and in a format approved by Council. This
       assessment must take into account noise from any other fixed equipment on the property e.g.
       swimming pool pump, heating/cooling equipment, etc that may increase the overall noise level
       emitted.

       Advice: It is highly recommended that the person you engage to certify the installation is
       involved at the plan development stage so they can recommend where this equipment is best
       located. They can also advise about noise enclosures and can make other suggestions to
       avoid noise problems. It is a lot more costly to try and deal with noise problems after
       everything is built.
75.    A minimum 1 metre wide landscape area shall be provided adjacent to the outdoor nursery
       and the site’s boundary to Gateway Drive
5      REFERRAL AGENCY CONDITIONS

The referral agencies applicable to this application are:

 Referral Trigger              Referral Status   Referral Agency      Referral Address

 Nil

6      APPROVED PLANS/DOCUMENTS
The approved plans and / or documents for this development approval are listed in the following
table:
 Plan / Document No.       Rev.     Plan / Document Name                    Date
 030                       P7       Site Plan – John R. Brogan &            27.05.09
                                    Associates
 100                       C        Ground Floor Plan – John R. Brogan &    01.09.08
                                    Associates
 101                       C        Mezzanine Floor Plan – John R.          01.09.08
                                    Brogan & Associates
 110                       C        Roof Plan – John R. Brogan &            01.09.08
                                    Associates
 120                       C        Sections – John R. Brogan &             01.09.08
                                    Associates
 121                       C        Sections – John R. Brogan &             01.09.08
                                    Associates
 130                       D        Elevations – John R. Brogan &           14.10.08
                                    Associates
 131                       D        Coloured Elevations – John R. Brogan    14.10.08
                                    & Associates


7      ADVISORY NOTES

The following Advisory Notes are for information purposes only and do not form conditions of
approval:
Advice Conditions
1.     The applicant is advised that development contributions and infrastructure charges applicable
       to this development approval have been based on the following Uses Class/ Uses and
       applicable quantities:-


                                                                                       13 of 20

Page 14

                                                                                      2007/256




       Existing Development                                Approved Development
                                                           Approved Use Class /       Approved
       Existing Use Class / Use     Existing Quantity
                                                           Use                        Quantity
       Industrial Business Type
                                          2
       2 - Production, alteration, 1,450 m use area
       repackaging and repairing
                                                                                                  2
       +                           +                       Retail Business Type 6     5,740 m use
                                          2
       Retail Business Type 3      2,240 m use area        - Hardware Store           area
       - Landscape and rural                               +                          +
                                                                                             2
       + Additional remaining credit for water             Retail Business Type 7     1,815 m use
       headworks given from balance of 2007/1626 Re:       - Garden Centre            area
       previous water & sewerage headworks
       contributions acquired from call in of bond
       applicable to Rezoning Deed, R 228
2.   The applicant is informed that approval of this development application will trigger an
     Infrastructure Charge in accordance with the Coastal Major Road Network Infrastructure
     Charges Plan for the estimated amount of $716,439 and is subject to variations in the
     Consumer Price Index, All Groups Brisbane from MARCH 2009 until the date of payment. An
     Infrastructure Charge Notice will be issued in accordance with Chapter 5 of the Integrated
     Planning Act 1997.
3.   The applicant is informed that payment via credit card transaction will not be an acceptable
     method of payment for development contributions conditioned in this permit or for
     infrastructure charge notices issued separately.
4.   Digital detailed designs including drawings, calculations and specifications shall be submitted
     with any application for a Development Permit for Operational Works in respect of roadworks
     and stormwater drainage works. In this regard a DXF/DWG file on GDA94 zone 56 grid of the
     proposed cadastre layout is to be submitted in conjunction with any application for Operational
     Works. The design shall be in accordance with Council’s Planning Scheme Policy PSP05 –
     Engineering Design Standards – Roads, Drainage and Earthworks.
5.   To facilitate production of As Constructed drawings it is suggested that all design drawings are
     submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
     use of ADAC are available at www.adac.com.au).
6.   The applicant is advised that a Compliance Permit for all plumbing and drainage works within
     the boundaries of the development site shall be obtained from Council’s Plumbing Services
     Section prior to obtaining a Development Permit for Building Works.
7.   The applicant is advised that this development may require the provision of fire hydrants and a
     booster pump in accordance with the Building Code of Australia, and consultation may also be
     needed with Queensland Fire Services to ensure suitable fire fighting infrastructure is
     provided. To this end any necessary fire hydrants shall be clearly shown on the plans
     submitted for both Operational Works and Building Works approval and if a booster pump is
     deemed necessary, the plans shall indicate where the fire truck is to be accommodated in
     order to provide boosting to the water supply.
8.   Approval for the Underground Petroleum Storage System should be obtained under the
     Dangerous Goods Safety Management Act 2001 and the Environmental Protection Act 1994.
     The application for such approval should be lodged with Council’s Environmental Health
     Section and includes an assessment by a competent person of the site’s class pursuant to
     Council’s “Operators Compliance Guide for Petroleum Product Storage”.




                                                                                       14 of 20

Page 15

                                                                                           2007/256



9.    An annual licence is required from Council’s Environmental Health Section with respect to the
      storage of flammable/combustible liquids in excess of the minimum amounts permitted under
      the Dangerous Goods Safety Management Act 2001. Application for a DGSM licence should
      be made at the time of submission of a development application for building works and you
      must include all relevant plans and specifications.
10.   The development should be undertaken and operated in a manner that causes no detrimental
      effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
      lighting, air-borne hazards, atmospheric pollutants (including dust or odours) nuisance or any
      other emissions in accordance with the nuisance provisions of the Environmental Protection
      Regulation 1998 or Council’s Local Law No. 12 – Control of Nuisances.
11.   All refrigeration plant including motors, should be situated within the building or suitably
      provided with noise reduction measures and located as to prevent a noise nuisance in
      accordance with the nuisance provisions of the Environmental Protection Regulation 1998.
      On the spot fines apply for such offences.
12.   Noise from building works associated with commercial and or industrial development should
      comply with the following –
      12.1.   Limited to between 7:00am to 6:30pm Monday to Saturday.
      12.2.   All reasonable measures are taken to minimise noise emissions.
      12.3.   Not permitted on Sunday or public holidays.
13.   In accordance with the Environmental Protection (Water) Policy 1997, all sand, silt, mud, paint,
      cement, concrete, builder’s waste or rubbish should not be permitted to enter or be placed
      where it could reasonably be expected to move into a roadside gutter, storm water drain or a
      watercourse. On the spot fines apply for such offences.
14.   The plans for the proposed building work have not been assessed for compliance with the
      requirements of the Building Code of Australia as they relate to people with disabilities. Your
      attention is drawn to the matter that either or both the Disability Discrimination Act 1992
      (commonwealth) and the Anti-Discrimination Act 1991(Queensland) may impact on the
      proposed building work.
      Noosa Council recommends that the following matters be considered to address equitable
      access and facilities in the building:-
      14.1.   The building and environs should be designed to meet the requirements of the Human
              Rights and Equal Opportunity Commission “Advisory Notes on Access to Premises”
              and AS1428.2;
      14.2.   Applicants should be aware that a “Disability Standard on Access to Premises is being
              developed and most likely will result in changes to the Building Code of Australia;
      14.3.   Any services and facilities in the building complex must allow independent, dignified
              and equitable use of the services and facilities for all people.
15.   This proposal has not been assessed in relation to the spread of fire between properties /
      buildings. It is the building certifiers responsibility to assess the requirements for fire services,
      fire separation and appropriate methods of construction as part of the building works approval
      process. Referral to the Queensland Fire and Rescue Service (QFRS) may be required as
      part of the Building Approval process.
16.   Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if
      the cost of operational works exceeds $80,000, then a portable long service leave levy is
      required to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight
      the approved form issued by the Building and Construction Industry (Portable Long Service
      Leave) Authority that confirms that the requirements of the Act have been satisfied. A statutory
      declaration outlining the cost of the operational works must be submitted to Council with the
      lodgement of any application for operational works over the site.
                                                                                            15 of 20

Page 16

                                                                                            2007/256



Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.

8     PROPERTY NOTES
Not applicable

9     PRELIMINARY APPROVAL OVERRIDING SCHEME

Not applicable

10    FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required            Subject of the required Development Permit
 Development Permit for Building Works          All Building Works

 Development      Permit   for   Operational    Landscaping, Carparking and Access, Site Civil
 Works                                          Works      (including       Earthworks),   Roadworks,
                                                Stormwater Drainage, Frontage Works, Sewer
                                                Reticulation (including New Mains, Relocations,
                                                Diversions, Pump Stations and Rising Mains), Water
                                                Reticulation, Site Filling, Erosion & Sediment Control

11    SELF ASSESSABLE CODES

The developer must comply with the following codes for self-assessable development related to the
development approved under this Decision Notice:
Advertising Devices Code
12    SUBMISSIONS
There were two (2) properly made submissions about the application. In accordance with Integrated
Planning Act 1997, the name and address of the principal submitter for each properly made
submission is provided and attached.

13    REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME

1.    There is a continuing significant planning need for a mega hardware store in the Noosa area,
      which will improve the range of hardware and related services available to residents, trades
      persons and businesses;

2.    The proposed Bunnings Warehouse will not adversely impact upon the economic viability of
      the Shire Business Centre;


                                                                                            16 of 20

Page 17

                                                                                      2007/256



3.    The proposed use has a significant hardware component, which is identified as a consistent
      use in the industrial zone under The Noosa Plan; and

4.     The proposed retail component of a Bunnings Warehouse is associated with the hardware use
       and this is consistent with many other hardware stores in which these types of business have
       expanded beyond the traditional retailing of hardware and trade supplies.

14     RIGHTS OF APPEAL
You have continuing appeal rights in respect of Council’s decision on your application. Refer Section
4.1.27. of the Integrated Planning Act 1997.
Please note that the Development approval does not take effect and cannot be acted upon, until the
end of the submitter’s appeal period.

15     OTHER DETAILS

Please note that an Infrastructure Charge in accordance with the Coastal Major Road Network
Infrastructure Charges Plan has been triggered by the approval of this development application. An
Infrastructure Charge Notice is attached in compliance with Chapter 5 of the Integrated Planning Act
1997
Should you wish to obtain more information about Council’s decision, electronic copies of Council’s
decision are available on line at www.sunshinecoast.qld.gov.au, or at Council Offices.

Yours faithfully,



Kerri Coyle
Coordinator Planning Applications (North)



Decision Notice History
10 July 2008 -                 Original Decision Notice.
16 July 2009 -                 Negotiated Decision Notice
                               with changes to Conditions
                               1, 10, 11, 14, 22, 23, 37,
                               41, 45 & 50.
                               Deletion of Condition 24.
                               Amendment to Conditions
                               16, 21 & 62 and Advice
                               Conditions 1 & 2 and an
                               additional Condition 75.




                                                                                       17 of 20

Page 18

                                                                                 2007/256




                                      List of Submitters
                                     INTEGRATED PLANNING ACT 1997 & 1998 REGULATION



Lee Meiklejohn
PO Box 1064
MOOLOOLABA QLD 4557




Melco Mitre 10 Home & Timber
CARE Harrison Grierson Consultants Pty Ltd
GPO Box 1064
BRISBANE QLD 4001




                                                                                 18 of 20

Page 19

                                                                                                           2007/256




                                                     Appeal Rights
                                                     INTEGRATED PLANNING ACT 1997 & 1998 REGULATION




The following is an extract from the Integrated                         (6) If an application involves assessment against a
Planning Act (Chapter 4).                                           concurrence agency code, appeal rights for submitters
                                                                    for the application are not available against the part of
Division 8 - Appeals to                court   relating    to       the approval that represents the concurrence agency’s
development applications                                            response for the code.
Appeals by applicants                                               Appeals by advice agency submitters
4.1.27.(1) An applicant for a development application may           4.1.29.(1) An advice agency may, within the limits of its
appeal to the court against any of the following-                   jurisdiction, appeal to the court about the giving of a
(a) the refusal, or the refusal in part, of a development           development approval for a development application if-
    application;                                                    (a) the development      application     involves   impact
(b) a matter stated in a development approval, including any           assessment; and
    condition applying to the development,           and   the
                                                                    (b) the advice agency told the applicant and the
    identification of a code under section 3.1.6;1
                                                                       assessment manager to treat its response to the
(c) the decision to give a preliminary approval when a                 application as a submission for an appeal.
    development permit was applied for;
                                                                       (2) The appeal must be started within 20 business
(d) the length of a relevant period;                                days after the day the decision notice or negotiated
(e) a deemed refusal.                                               decision notice is given to the advice agency as a
    (2) An appeal under subsection (1)(a) to (d) must be            submitter.
started within 20 business days (the “applicant’s appeal            Appeals for matters arising after approval given
period”) after the day the decision notice or negotiated            (co-respondents)
decision notice is given to the applicant.
                                                                    4.1.30.(1) For a development approval given for a
    (3) An appeal under subsection (1)(e) may be started at         development application, a person to whom any of the
any time after the last day a decision on the matter should         following notices have been given may appeal to the
have been made.
                                                                    court against the decision in the notice-
Appeals by submitters
                                                                    (a) a notice giving a decision on a request for extension
4.1.28.(1) A submitter for a development application may               of the relevant period for an approval;
appeal to the court about-
                                                                    (b) a notice giving a decision on a request to make a
(a) the giving of a development approval, including any                minor change to an approval.
    conditions (or lack of conditions) or other provisions
                                                                        (2) The appeal must be started within 20 business
    of the approval; or
                                                                    days after the day the notice of the decision is given to
(b) the length of a relevant period for the approval.               the person.
    (2) The appeal must be started within 20 business                   (3) Subsection (1)(a) does not apply if the approval
days (the “submitters appeal period”) after the day the             resulted from a development application (superseded
decision notice or negotiated decision notice is given to           planning scheme) that was assessed as if it were an
the submitter.                                                      application under a superseded planning scheme.
   (3) If a person withdraws a submission before the                   (4) Also, a person who has made a request
application is decided, the person may not appeal the               mentioned in subsection (1) may appeal to the court
decision.                                                           against a deemed refusal of the request.
   (4) If an application involves both impact assessment               (5) An appeal under subsection (4) may be started at
and code assessment, appeal rights for submitters are               any time after the last day the decision on the matter
available only for the part of the application involving            should have been made.
impact assessment.
                                                                    Division 9 - Appeals to court about other matters
    (5) If an application is processed under section                Appeals for matters arising after approval given
6.1.28(2), appeal rights for submitters for the application
                                                                    (no co-respondents)
are available only for the aspects of the development that
would have required public notification under the                   4.1.31.(1) A person to whom any of the following notices
repealed Act.                                                       have been given may appeal to the court against the
                                                                    decision in the notice-
                                                                    (a) a notice giving a decision on a request to change or
                                                                       cancel a condition of a development approval.
1
   Section 3.1.6 (Preliminary approval may override local
planning instrument)
                                                                                                           19 of 20

Page 20

                                                                                                    2007/256

(b) a notice under section 6.1.442 giving a decision to        (c) the decision to give a preliminary approval when a
    change or cancel a condition of a development                    development permit was applied for;
    approval.                                                  (d) the length of a period mentioned in section 3.5.21
    (2) The appeal must be started within 20 business                relevant period;
       days after the day the notice of the decision is        (e) a deemed refusal.
       given to the person.
                                                                   (2) An appeal under subsection (1)(a) to (d) must be
    (3) Also, a person who has made a request                  started within 20 business days (the “applicant’s appeal
       mentioned in subsection (1)(a) may appeal to the        period”) after the day the decision notice or negotiated
       court against a deemed refusal of the request.          decision notice is given to the applicant.
    (4) An appeal under subsection (3) may be started at           (3) An appeal under subsection (1)(e) may be started
       any time after the last day the decision on the         at any time after the last day a decision on the matter
       matter should have been made.                           should have been made.
Appeals against decisions to change approval conditions        The Registrar for the Building and Development
under the repealed Act                                         Tribunal may be contacted at the website
4.1.33A.(1) A person who is dissatisfied with a decision       http://www.localgovernment.qld.gov.au/
made on an application to change the conditions
attached to an approval given under section 2.19(3)or          For Infrastructure Charges Only
section 4.4 of the repealed Act may appeal to the court        4.1.36 Appeals about particular infrastructure
against-                                                       charges
(a) the decision; or                                           (1) This section applies to a person who has been
(b) a deemed refusal of the application.                       given, and is dissatisfied with, an infrastructure charges
                                                               notice or a regulated State infrastructure charges notice.
    (2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of        (2) The person may appeal to the court against the
the decision is to be given to the person.                     notice.
    (3) An appeal under subsection (1)(b) may be started       (3) The appeal must be started within 20 business days
at any time after the last day a decision on the matter        after-
should have been made.                                         (a) if the notice is given because of a development
Appeals against local laws                                          approval or master plan approval-the day the
                                                                    applicant is given notice of the decision about the
4.1.33B.(1) An applicant who is dissatisfied with a                 approval; or
decision of a local government or the conditions applied
under a local law about the use of premises or the             (b)    otherwise-the day the notice is given to the person.
erection of a building or other structure permitted by the     (4)    An appeal under this section may only be about-
planning scheme may appeal to the court against the            (a) whether a charge in the notice is so unreasonable
decision or the conditions applied.                                that no reasonable relevant local government, State
   (2) The appeal must be started within 20 business               infrastructure provider or coordinating agency could
days after the day notice of the decision is given to the          have imposed it; or
applicant.                                                     (b) an error in the calculation of the charge.
For Building Works Only                                        (5) To remove any doubt, it is declared that an appeal
Rights of appeal conferred by Section 4.2.9 of the             under this section can not be about the methodology
Integrated Planning Act 1997 as follows:                       used to establish the charge in the relevant infrastructure
                                                               charges schedule or regulated State infrastructure
Division 3 – Appeals          to   tribunals   relating   to
                                                               charges schedule.
development applications
Appeals by applicants
4.2.9(1) An applicant for a development application may
appeal to the Building and Development Tribunal against
any of the following-
(a) the refusal, or the refusal in part, of a development
    application;

(b) a matter stated in a development approval, including
    any condition applying to the development, and the
    identification of a code under section 3.1.6;3

2
  Section 6.1.44 (Conditions may be changed or cancelled
by assessment manager or concurrence agency in certain
circumstances)
3
   Section 3.1.6 (Preliminary approval may override local
planning instrument)
                                                                                                    20 of 20

Used in these records

About this file

File size
101 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice - 010.2007.00000256.001 [As Published].pdf · 101 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.