     Condition 16
     The scale of the proposal plans does not allow for compliance with roof pitch and eaves
     requirements to be accurately determined.

     Condition 18 & 19
     The bond is required to secure performance of all conditions of the approval and the bond
     amount is reasonable given the amount of works required to be undertaken by this approval.

     Condition 35
     The condition is intended to ensure that any spaces that are intended to be used by staff are
     not utilised in error by a customer, with staff spaces in accordance with AS/NZS 2890.1:2004
     being a lesser width and therefore more difficult to access and unsuitable for customer use.

     Condition 51
     The condition ensures that the existing runoff volumes are maintained as much as is
     practicable, as the development must not increase or decrease runoff to the extent that it
     adversely affects the downstream ecosystem.

     Condition 62
     The development (staff and customers) will generate an increase in the need for public
     transport facilities in the area. The contribution amount is proportional to the cost of providing
     public transport facilities to service the increase in demand generated by the development.
D.   Amend Conditions 16, 21 & 62 and Advice Conditions 1 & 2.
E.   Include one additional Condition 75.
F.   Advise the applicant that Council does not agree to:-
      1.    Offset the cost of roadworks against the Coastal Major Road Network Infrastructure
            Charges Plan (CMRNICP) contributions as no works are planned for this roundabout or
            road diversion in the current CMRNICP nor in the Draft PIP and roadworks are
            necessitated by the increase in traffic generated by the Bunnings Warehouse;

      2.    Offset the cost of pathway works as the section of path along the Eumundi Noosa road
            frontage has been constructed by Council.

3    RELEVANT PERIOD OF APPROVAL
The relevant period for this Development Approval is identified in the Assessment Manager
conditions.

4    ASSESSMENT MANAGER CONDITIONS

Land Use
1.   Development undertaken in accordance with this approval must generally comply with the
     approved plans of development. The approved plans are numbered:
      Plan         /      Rev.    Plan / Document Name                       Date
      Document No.
      030                 P7      Site Plan – John R. Brogan &               27.05.09
                                  Associates
      100                 C       Ground Floor Plan – John R. Brogan &       01.09.08
                                  Associates
      101                 C       Mezzanine Floor Plan – John R.             01.09.08
                                  Brogan & Associates

                                                                                          2 of 20

Used in these records

About this file

File size
101 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Negotiated Decision Notice - 010.2007.00000256.001 [As Published].pdf · 101 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.