1. 202009 24 Lake MacDonald Program
28/09/2020 - 2406 Lake MacDonald Drive, Cooroy Shadforth
ID Task Task Name Duration Start Finish October 2020 November 2020 December 2020
Mode 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21
1 2406 - Lake MacDonald Drive, Cooroy 75 days Thu 24/09/20Sat 19/12/20
2 Contract Prelims 75 days Thu 24/09/20Sat 19/12/20
3 Execution of Contract 0 days Thu 24/09/20Thu 24/09/20 24/09
4 Submission of Insurances 0 days Thu 24/09/20Thu 24/09/20 24/09
5 Submission of WMP 5 days Thu 24/09/20Tue 29/09/20
6 Submission of EMP 5 days Thu 24/09/20Tue 29/09/20
7 Submission of ESC 5 days Thu 24/09/20Tue 29/09/20
8 Submission of TMP/TGS 5 days Thu 24/09/20Tue 29/09/20
9 Notification to Council of Prestart Documents 5 days Wed Mon
30/09/20 5/10/20
10 OPW Contract Prestart with Council 0 days Mon 5/10/20Mon 5/10/20 5/10
11 Submission of Pre Construction Condition 0 days Mon Mon 5/10
Photographs 5/10/20 5/10/20
12 OPW Clause 16. The developer must notify 0 days Mon Mon 5/10
Council’s Traffic Engineer for any works involving 5/10/20 5/10/20
the removal or modification of existing council
traffic signs and/or parking bays prior to such
works commencing
13 Demobilisation 5 days Tue 15/12/20Sat 19/12/20
14 Demobilise ESC controls 2 days Tue 15/12/20Wed 16/12/20
15 Demobilise site sheds 1 day Thu 17/12/20Thu 17/12/20
16 Demobilise equipment 2 days Fri 18/12/20 Sat 19/12/20
17 Construction Duration Tender 60 days / 10 Weeks 60 days Mon Mon
5/10/20 14/12/20
18 Date of possession 0 days Mon 5/10/20Mon 5/10/20 5/10
19 Practical Completion / On maintenance 0 days Mon 14/12/20Mon 14/12/20 14/12
21 Construction 60 days Tue 6/10/20 Mon 14/12/20
22 Site Establishment 11 days Tue 6/10/20 Sat 17/10/20
23 Letter Box Drop - Community Notification 5 days Tue 6/10/20 Sat 10/10/20 Comms
24 Establish Survey 3 days Tue 6/10/20 Thu 8/10/20 Survey
25 Mobilisation of site sheds and compound 5 days Tue 6/10/20 Sat 10/10/20
28 Survey Pre-Stripped surface 2 days Fri 9/10/20 Sat 10/10/20 Survey
27 Mobilisation of Traffic control devices 0 days Sat 10/10/20 Sat 10/10/20 10/10
29 CBR Testing of subgrades in cut 0 days Sat 10/10/20 Sat 10/10/20 10/10
26 Mobilisation of ESC Controls 6 days Mon 12/10/20Sat 17/10/20 Erosion Sediment Crew
30 Processing of CBRS 5 days Mon 12/10/20Fri 16/10/20 Geotech
31 Pavement Design Approval 0 days Fri 16/10/20 Fri 16/10/20 16/10
69 Road 1 & Lake Macdonald Drive Shoulders 49 days Mon Mon
19/10/20 14/12/20
70 Road 1 44 days Mon 19/10/20
Tue 8/12/20
71 Clearing and Grubbing 4 days Mon 19/10/20Thu 22/10/20 Mulching Services
72 Supply and install SW - 0/X2 - 1/X2 - 2/X2 0.5 days Fri 23/10/20 Fri 23/10/20 SW Crew
73 Supply and install SW - 0/X3 - 1/X3 0.5 days Fri 23/10/20 Fri 23/10/20 SW Crew
74 Strip Topsoil to Windrow 3 days Sat 24/10/20 Tue 27/10/20 Excavator
75 GST to Foundation 4 days Wed 28/10/20Sat 31/10/20 Grader Earthworks
76 Localised Cut to fill 10 days Mon 2/11/20Thu 12/11/20 Excavator,Moxy Crew
78 CBR Testing of subgrades 0 days Thu 12/11/20Thu 12/11/20 12/11
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: 1. 202009 24 Lake Mac
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Mon 28/09/20
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Construction Program. Submitted in accordance with GCOC Page 1 1. 202009 24 Lake MacDonald Program
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 2 pages
Page 2
28/09/2020 - 2406 Lake MacDonald Drive, Cooroy Shadforth
ID Task Task Name Duration Start Finish October 2020 November 2020 December 2020
Mode 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21
77 Subgrade Prep ~3100m2 2 days Fri 13/11/20 Sat 14/11/20 Grader Earthworks
79 Submission of Pavement CBR Results for 5 days Fri 13/11/20 Wed Geotech
approval 18/11/20
80 HOLD POINT SUBGRADE INSPECTION 0 days Wed 18/11/20Wed 18/11/20 18/11
81 Supply and install SW - 0/B- 1/B- 2/B-3/B 1 day Thu Thu SW Crew
19/11/20 19/11/20
84 Supply and install Subsoil Drainage ~190M4 days Thu 19/11/20Mon 23/11/20 Trencher
82 Supply and install SW - 0/C- 1/C- 2/C 0.5 days Fri 20/11/20 Fri 20/11/20 SW Crew
83 FRP Pits 3 days Fri 20/11/20 Tue 24/11/20 Concretors
85 Supply and place 200mm Subbase 2 days Tue Wed Grader Pavement
~3048M2 X 0.2M = 610M3 24/11/20 25/11/20
86 Supply and place Type M1 Kerb and 5 days Thu Tue 1/12/20 Kerb SC
Channel 915m 26/11/20
88 Supply and install KEU and headwall 2 days Mon 30/11/20Tue 1/12/20 Concretors
87 Spread Site won topsoil to 100mm depth 3 days Wed Fri 4/12/20 Posi Track
2/12/20
89 Supply and place 120mm base (2807M2 2 days Wed Thu 3/12/20 Grader Pavement
X 0.120M= 337M3) 2/12/20
90 Primer Seal 3 days Fri 4/12/20 Mon 7/12/20 SEAL Crew
91 Supply and place AC surfacing 1 day Tue 8/12/20 Tue 8/12/20 AC Crew
92 Lake MacDonald Drive Shoulders 37 days Tue 27/10/20Tue 8/12/20
93 Clearing and Grubbing 2 days Tue 27/10/20Wed 28/10/20 Mulching Services
94 Strip Topsoil to Windrow 2 days Thu 29/10/20Fri 30/10/20 Excavator
95 Saw Cut to Existing pavement 1 day Sat 31/10/20 Sat 31/10/20 Saw Cutter
96 Excavate and dispose of shoulder 3 days Mon 2/11/20Wed 4/11/20 Excavator
97 GST to Foundation 1 day Thu 5/11/20 Thu 5/11/20 Posi Track
98 Subgrade Prep 1 day Fri 6/11/20 Fri 6/11/20 Posi Track
99 HOLD POINT SUBGRADE INSPECTION 0 days Fri 6/11/20 Fri 6/11/20 6/11
100 Supply and place 260mm Subbase 3 days Sat 7/11/20 Tue Posi Track
372M2 X 0.260M = 97M3 10/11/20
101 Supply and place 140mm base (372M2 X 3 days Wed Fri 13/11/20 Posi Track
0.140M= 53M3) 11/11/20
102 Spread Site won topsoil to 100mm depth 1 day Sat 14/11/20 Sat 14/11/20 Posi Track
103 Primer Seal 3 days Fri 4/12/20 Mon 7/12/20 AC Crew,SEAL Crew
104 Supply and place AC surfacing 1 day Tue 8/12/20 Tue 8/12/20 AC Crew
105 Finishing Works 5 days Wed 9/12/20Mon 14/12/20
106 Line marking and signage 1 day Wed 9/12/20Wed 9/12/20
107 Hydromulch 2 days Thu 10/12/20Fri 11/12/20
108 Turf 2 days Sat 12/12/20 Mon 14/12/20
32 DW08 - Middle Lots 4,8 17 days Fri 23/10/20 Wed 11/11/20
33 Clearing and Grubbing 2 days Fri 23/10/20 Sat 24/10/20 Mulching Services
34 Strip Topsoil to Windrow 2 days Mon 26/10/20Tue 27/10/20 Topsoil crew
35 GST to Foundation 2 days Wed 28/10/20Thu 29/10/20 Grader Earthworks
36 Localised Cut to fill 2 days Fri 30/10/20 Sat 31/10/20 Excavator,Moxy Crew
37 Extend Dam 2 days Mon 2/11/20Tue 3/11/20 Excavator,Moxy Crew
38 Trim Subgrades on Lot 4,8 (375m x 5.6m = 2 days Mon Tue 3/11/20 Grader Earthworks
2100m2) 2/11/20
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: 1. 202009 24 Lake Mac
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Mon 28/09/20
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Construction Program. Submitted in accordance with GCOC Page 2 1. 202009 24 Lake MacDonald Program
Page 3
28/09/2020 - 2406 Lake MacDonald Drive, Cooroy Shadforth
ID Task Task Name Duration Start Finish October 2020 November 2020 December 2020
Mode 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21
39 HOLD POINT SUBGRADE INSPECTION 0 days Tue 3/11/20 Tue 3/11/20 3/11
40 Construct Site Entrance 1 day Wed 4/11/20Wed 4/11/20 Grader Pavement
41 Lot 4,8Supply and place 2.4 subbase 2 days Thu 5/11/20 Fri 6/11/20 Grader Pavement
@100mm (375M X 5.6M ~210M3)
42 Lot 4,8 Supply and place 2.2 base 2 days Sat 7/11/20 Mon Grader Pavement
@100mm(375M X 4.8M ~180M3) 9/11/20
43 Lot 4,8 Spread Site won topsoil to 100mm 2 days Tue Wed Grader Pavement
depth 10/11/20 11/11/20
44 Road 2 Wilgee Court - Lot 5,6 7 39 days Sat 24/10/20Tue 8/12/20
45 Resident Consultation with Driveway 0 days Sat 24/10/20 Sat 24/10/20 24/10
Access
46 Clearing and Grubbing 1 day Mon 26/10/20Mon 26/10/20 Mulching Services
47 Strip Topsoil to Windrow 2 days Tue 27/10/20Wed 28/10/20 Topsoil crew
48 Localised Cut to fill 2 days Thu 29/10/20Fri 30/10/20 Excavator,Moxy Crew
49 Trim Subgrades on Lot 5,6,7 (348m x 5.6m = 2 days Sat 31/10/20 Mon Grader Earthworks
1948m2) 2/11/20
50 HOLD POINT SUBGRADE INSPECTION 0 days Mon 2/11/20Mon 2/11/20 2/11
51 Lot 5,6,7 Supply and place 2.4 subbase 1 day Tue 3/11/20 Tue 3/11/20 Grader Pavement
@100mm (348M X 5.6M ~194M3)
52 Lot 5,6,7 Supply and place 2.2 base 2 days Wed Thu 5/11/20 Grader Pavement
@100mm(348M X 4.8M ~167M3) 4/11/20
53 Lot 5,6,7 Spread Site won topsoil to 100mm 2 days Fri 6/11/20 Sat 7/11/20 Grader Pavement
depth
54 Road 2 Wilgee Court - Driveway 28 days Fri 6/11/20 Tue 8/12/20
55 Demolition and disposal of Existing 2 days Fri 6/11/20 Sat 7/11/20 Excavator
Driveway
56 Excavate to Subgrade 1 day Mon 9/11/20Mon 9/11/20 Excavator
57 Trim Subgrade 1 day Tue 10/11/20Tue 10/11/20 Grader Earthworks
58 HOLD POINT SUBGRADE INSPECTION 0 days Tue 10/11/20Tue 10/11/20 10/11
59 Supply and install SW - 0/A- 1/A- 2/A 1 day Wed 11/11/20Wed 11/11/20 SW Crew
60 FRP Pits 3 days Thu 12/11/20Sat 14/11/20 Concretors
61 Supply and install Subsoil Drainage ~190M2 days Mon 16/11/20Tue 17/11/20 Trencher
62 Supply and place 180mm Subbase 1 day Wed Wed Grader Pavement
627M2 X 0.180M = 112M3 18/11/20 18/11/20
63 Supply and place Type M1 Kerb and 3 days Thu Sat 21/11/20 Kerb SC
Channel 19/11/20
64 Supply and install KEU and headwall 0.5 days Fri 20/11/20 Fri 20/11/20 Concretors
65 Supply and place 100mm base (534M2 X 1 day Mon Mon Grader Pavement
0.1M= 53.4M3) 23/11/20 23/11/20
68 Spread Site won topsoil to 100mm depth 1 day Tue Tue Posi Track
24/11/20 24/11/20
66 Primer Seal 3 days Fri 4/12/20 Mon 7/12/20 SEAL Crew
67 Supply and place AC surfacing 1 day Tue 8/12/20 Tue 8/12/20 AC Crew
20 Submission of QA/ Survey 5 days Wed 9/12/20Mon 14/12/20
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: 1. 202009 24 Lake Mac
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Mon 28/09/20
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Construction Program. Submitted in accordance with GCOC Page 3 1. 202009 24 Lake MacDonald Program