28/09/2020 - 2406 Lake MacDonald Drive, Cooroy                                                                                                                                                                                                                                                                              Shadforth
ID          Task     Task Name                                                  Duration     Start       Finish                                          October 2020                                                           November 2020                                            December 2020
            Mode                                                                                                           16     19   22    25     28    1       4      7       10     13    16     19    22     25      28   31    3      6   9   12         15   18   21   24   27   30    3      6        9   12   15     18   21
     1               2406 - Lake MacDonald Drive, Cooroy                        75 days      Thu 24/09/20Sat 19/12/20
     2                  Contract Prelims                                        75 days      Thu 24/09/20Sat 19/12/20
     3                    Execution of Contract                                 0 days       Thu 24/09/20Thu 24/09/20                       24/09
     4                    Submission of Insurances                              0 days       Thu 24/09/20Thu 24/09/20                       24/09
     5                    Submission of WMP                                     5 days       Thu 24/09/20Tue 29/09/20
     6                    Submission of EMP                                     5 days       Thu 24/09/20Tue 29/09/20
     7                    Submission of ESC                                     5 days       Thu 24/09/20Tue 29/09/20
     8                    Submission of TMP/TGS                                 5 days       Thu 24/09/20Tue 29/09/20
     9                    Notification to Council of Prestart Documents         5 days       Wed         Mon
                                                                                             30/09/20    5/10/20
     10                   OPW Contract Prestart with Council                    0 days       Mon 5/10/20Mon 5/10/20                                                     5/10
     11                   Submission of Pre Construction Condition              0 days       Mon         Mon                                                            5/10
                          Photographs                                                        5/10/20     5/10/20
     12                   OPW Clause 16. The developer must notify           0 days          Mon         Mon                                                            5/10
                          Council’s Traffic Engineer for any works involving                 5/10/20     5/10/20
                          the removal or modification of existing council
                          traffic signs and/or parking bays prior to such
                          works commencing
     13                   Demobilisation                                        5 days       Tue 15/12/20Sat 19/12/20
     14                      Demobilise ESC controls                            2 days       Tue 15/12/20Wed 16/12/20
     15                      Demobilise site sheds                              1 day        Thu 17/12/20Thu 17/12/20
     16                      Demobilise equipment                               2 days       Fri 18/12/20 Sat 19/12/20
     17                 Construction Duration Tender 60 days / 10 Weeks 60 days              Mon         Mon
                                                                                             5/10/20     14/12/20
     18                   Date of possession                                    0 days       Mon 5/10/20Mon 5/10/20                                                     5/10
     19                   Practical Completion / On maintenance                 0 days       Mon 14/12/20Mon 14/12/20                                                                                                                                                                                                  14/12
     21                   Construction                                          60 days      Tue 6/10/20 Mon 14/12/20
     22                      Site Establishment                                 11 days      Tue 6/10/20 Sat 17/10/20
     23                          Letter Box Drop - Community Notification       5 days       Tue 6/10/20 Sat 10/10/20                                                             Comms
     24                          Establish Survey                               3 days       Tue 6/10/20 Thu 8/10/20                                                           Survey
     25                          Mobilisation of site sheds and compound        5 days       Tue 6/10/20 Sat 10/10/20

     28                          Survey Pre-Stripped surface                    2 days       Fri 9/10/20 Sat 10/10/20                                                             Survey
     27                          Mobilisation of Traffic control devices        0 days       Sat 10/10/20 Sat 10/10/20                                                                10/10
     29                          CBR Testing of subgrades in cut                0 days       Sat 10/10/20 Sat 10/10/20                                                                10/10
     26                          Mobilisation of ESC Controls                   6 days       Mon 12/10/20Sat 17/10/20                                                                              Erosion Sediment Crew
     30                          Processing of CBRS                             5 days       Mon 12/10/20Fri 16/10/20                                                                          Geotech
     31                          Pavement Design Approval                       0 days       Fri 16/10/20 Fri 16/10/20                                                                             16/10
     69                      Road 1 & Lake Macdonald Drive Shoulders            49 days      Mon         Mon
                                                                                             19/10/20    14/12/20
     70                          Road 1                                         44 days      Mon 19/10/20
                                                                                                        Tue 8/12/20
     71                            Clearing and Grubbing                        4 days       Mon 19/10/20Thu 22/10/20                                                                                       Mulching Services
     72                            Supply and install SW - 0/X2 - 1/X2 - 2/X2 0.5 days       Fri 23/10/20 Fri 23/10/20                                                                                          SW Crew


     73                            Supply and install SW - 0/X3 - 1/X3          0.5 days     Fri 23/10/20 Fri 23/10/20                                                                                          SW Crew
     74                            Strip Topsoil to Windrow                     3 days       Sat 24/10/20 Tue 27/10/20                                                                                                    Excavator
     75                            GST to Foundation                            4 days       Wed 28/10/20Sat 31/10/20                                                                                                           Grader Earthworks
     76                            Localised Cut to fill                        10 days      Mon 2/11/20Thu 12/11/20                                                                                                                                  Excavator,Moxy Crew
     78                            CBR Testing of subgrades                     0 days       Thu 12/11/20Thu 12/11/20                                                                                                                                    12/11

                                  Task                                     Summary                                Inactive Milestone                         Duration-only                                  Start-only                              External Milestone                      Critical Split
Project: 1. 202009 24 Lake Mac
                                  Split                                    Project Summary                        Inactive Summary                           Manual Summary Rollup                          Finish-only                             Deadline                                Progress
Date: Mon 28/09/20
                                  Milestone                                Inactive Task                          Manual Task                                Manual Summary                                 External Tasks                          Critical                                Manual Progress

Construction Program. Submitted in accordance with GCOC                                                                                                    Page 1                                                                                                                          1. 202009 24 Lake MacDonald Program
Log in to download the original file

1. 202009 24 Lake MacDonald Program.pdf · 758 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 2 pages

Page 2

28/09/2020 - 2406 Lake MacDonald Drive, Cooroy                                                                                                                                                                                                                                                                                  Shadforth
ID          Task     Task Name                                                  Duration     Start       Finish                                       October 2020                                                      November 2020                                                      December 2020
            Mode                                                                                                           16     19   22   25   28    1       4     7     10     13   16   19   22    25       28     31    3      6      9     12         15   18      21   24     27   30    3      6         9   12    15     18   21
     77                            Subgrade Prep ~3100m2                        2 days       Fri 13/11/20 Sat 14/11/20                                                                                                                                  Grader Earthworks
     79                            Submission of Pavement CBR Results for 5 days             Fri 13/11/20 Wed                                                                                                                                                      Geotech
                                   approval                                                               18/11/20
     80                            HOLD POINT SUBGRADE INSPECTION               0 days       Wed 18/11/20Wed 18/11/20                                                                                                                                                 18/11
     81                            Supply and install SW - 0/B- 1/B- 2/B-3/B 1 day           Thu         Thu                                                                                                                                                          SW Crew
                                                                                             19/11/20    19/11/20
     84                            Supply and install Subsoil Drainage ~190M4 days           Thu 19/11/20Mon 23/11/20                                                                                                                                                         Trencher
     82                            Supply and install SW - 0/C- 1/C- 2/C        0.5 days     Fri 20/11/20 Fri 20/11/20                                                                                                                                                 SW Crew


     83                            FRP Pits                                     3 days       Fri 20/11/20 Tue 24/11/20                                                                                                                                                        Concretors
     85                            Supply and place 200mm Subbase               2 days       Tue         Wed                                                                                                                                                                       Grader Pavement
                                   ~3048M2 X 0.2M = 610M3                                    24/11/20    25/11/20
     86                            Supply and place Type M1 Kerb and            5 days       Thu         Tue 1/12/20                                                                                                                                                                         Kerb SC
                                   Channel 915m                                              26/11/20
     88                            Supply and install KEU and headwall          2 days       Mon 30/11/20Tue 1/12/20                                                                                                                                                                         Concretors
     87                            Spread Site won topsoil to 100mm depth 3 days             Wed         Fri 4/12/20                                                                                                                                                                                 Posi Track
                                                                                             2/12/20
     89                            Supply and place 120mm base (2807M2 2 days                Wed         Thu 3/12/20                                                                                                                                                                              Grader Pavement
                                   X 0.120M= 337M3)                                          2/12/20
     90                            Primer Seal                                  3 days       Fri 4/12/20 Mon 7/12/20                                                                                                                                                                                           SEAL Crew
     91                            Supply and place AC surfacing                1 day        Tue 8/12/20 Tue 8/12/20                                                                                                                                                                                            AC Crew
     92                          Lake MacDonald Drive Shoulders                 37 days      Tue 27/10/20Tue 8/12/20
     93                            Clearing and Grubbing                        2 days       Tue 27/10/20Wed 28/10/20                                                                                              Mulching Services
     94                            Strip Topsoil to Windrow                     2 days       Thu 29/10/20Fri 30/10/20                                                                                                 Excavator
     95                            Saw Cut to Existing pavement                 1 day        Sat 31/10/20 Sat 31/10/20                                                                                                  Saw Cutter
     96                            Excavate and dispose of shoulder             3 days       Mon 2/11/20Wed 4/11/20                                                                                                             Excavator
     97                            GST to Foundation                            1 day        Thu 5/11/20 Thu 5/11/20                                                                                                              Posi Track
     98                            Subgrade Prep                                1 day        Fri 6/11/20 Fri 6/11/20                                                                                                                 Posi Track
     99                            HOLD POINT SUBGRADE INSPECTION               0 days       Fri 6/11/20 Fri 6/11/20                                                                                                                    6/11
 100                               Supply and place 260mm Subbase               3 days       Sat 7/11/20 Tue                                                                                                                                   Posi Track
                                   372M2 X 0.260M = 97M3                                                 10/11/20
 101                               Supply and place 140mm base (372M2 X 3 days               Wed         Fri 13/11/20                                                                                                                                 Posi Track
                                   0.140M= 53M3)                                             11/11/20
 102                               Spread Site won topsoil to 100mm depth 1 day              Sat 14/11/20 Sat 14/11/20                                                                                                                                      Posi Track


 103                               Primer Seal                                  3 days       Fri 4/12/20 Mon 7/12/20                                                                                                                                                                                           AC Crew,SEAL Crew
 104                               Supply and place AC surfacing                1 day        Tue 8/12/20 Tue 8/12/20                                                                                                                                                                                            AC Crew
 105                             Finishing Works                                5 days       Wed 9/12/20Mon 14/12/20
 106                               Line marking and signage                     1 day        Wed 9/12/20Wed 9/12/20
 107                               Hydromulch                                   2 days       Thu 10/12/20Fri 11/12/20
 108                               Turf                                         2 days       Sat 12/12/20 Mon 14/12/20
     32                      DW08 - Middle Lots 4,8                             17 days      Fri 23/10/20 Wed 11/11/20
     33                          Clearing and Grubbing                          2 days       Fri 23/10/20 Sat 24/10/20                                                                                 Mulching Services
     34                          Strip Topsoil to Windrow                       2 days       Mon 26/10/20Tue 27/10/20                                                                                           Topsoil crew
     35                          GST to Foundation                              2 days       Wed 28/10/20Thu 29/10/20                                                                                                Grader Earthworks
     36                          Localised Cut to fill                          2 days       Fri 30/10/20 Sat 31/10/20                                                                                                  Excavator,Moxy Crew
     37                          Extend Dam                                     2 days       Mon 2/11/20Tue 3/11/20                                                                                                            Excavator,Moxy Crew
     38                          Trim Subgrades on Lot 4,8 (375m x 5.6m = 2 days             Mon         Tue 3/11/20                                                                                                           Grader Earthworks
                                 2100m2)                                                     2/11/20

                                  Task                                     Summary                                Inactive Milestone                      Duration-only                           Start-only                                     External Milestone                           Critical Split
Project: 1. 202009 24 Lake Mac
                                  Split                                    Project Summary                        Inactive Summary                        Manual Summary Rollup                   Finish-only                                    Deadline                                     Progress
Date: Mon 28/09/20
                                  Milestone                                Inactive Task                          Manual Task                             Manual Summary                          External Tasks                                 Critical                                     Manual Progress

Construction Program. Submitted in accordance with GCOC                                                                                                 Page 2                                                                                                                               1. 202009 24 Lake MacDonald Program

Page 3

28/09/2020 - 2406 Lake MacDonald Drive, Cooroy                                                                                                                                                                                                                                                                                Shadforth
ID          Task     Task Name                                                  Duration     Start       Finish                                       October 2020                                                      November 2020                                                    December 2020
            Mode                                                                                                           16     19   22   25   28    1       4     7     10     13   16   19   22    25        28    31    3      6     9     12         15   18      21   24    27   30    3      6         9   12    15     18   21
     39                          HOLD POINT SUBGRADE INSPECTION                 0 days       Tue 3/11/20 Tue 3/11/20                                                                                                           3/11
     40                          Construct Site Entrance                        1 day        Wed 4/11/20Wed 4/11/20                                                                                                               Grader Pavement
     41                          Lot 4,8Supply and place 2.4 subbase            2 days       Thu 5/11/20 Fri 6/11/20                                                                                                                  Grader Pavement
                                 @100mm (375M X 5.6M ~210M3)
     42                          Lot 4,8 Supply and place 2.2 base              2 days       Sat 7/11/20 Mon                                                                                                                               Grader Pavement
                                 @100mm(375M X 4.8M ~180M3)                                              9/11/20
     43                          Lot 4,8 Spread Site won topsoil to 100mm       2 days       Tue         Wed                                                                                                                                   Grader Pavement
                                 depth                                                       10/11/20    11/11/20
     44                      Road 2 Wilgee Court - Lot 5,6 7                    39 days      Sat 24/10/20Tue 8/12/20
     45                          Resident Consultation with Driveway            0 days       Sat 24/10/20 Sat 24/10/20                                                                                24/10
                                 Access
     46                          Clearing and Grubbing                          1 day        Mon 26/10/20Mon 26/10/20                                                                                          Mulching Services
     47                          Strip Topsoil to Windrow                       2 days       Tue 27/10/20Wed 28/10/20                                                                                              Topsoil crew
     48                          Localised Cut to fill                          2 days       Thu 29/10/20Fri 30/10/20                                                                                                 Excavator,Moxy Crew
     49                          Trim Subgrades on Lot 5,6,7 (348m x 5.6m = 2 days           Sat 31/10/20 Mon                                                                                                               Grader Earthworks
                                 1948m2)                                                                  2/11/20
     50                          HOLD POINT SUBGRADE INSPECTION                 0 days       Mon 2/11/20Mon 2/11/20                                                                                                          2/11
     51                          Lot 5,6,7 Supply and place 2.4 subbase         1 day        Tue 3/11/20 Tue 3/11/20                                                                                                          Grader Pavement
                                 @100mm (348M X 5.6M ~194M3)
     52                          Lot 5,6,7 Supply and place 2.2 base            2 days       Wed         Thu 5/11/20                                                                                                                Grader Pavement
                                 @100mm(348M X 4.8M ~167M3)                                  4/11/20
     53                          Lot 5,6,7 Spread Site won topsoil to 100mm 2 days           Fri 6/11/20 Sat 7/11/20                                                                                                                    Grader Pavement
                                 depth
     54                          Road 2 Wilgee Court - Driveway                 28 days      Fri 6/11/20 Tue 8/12/20
     55                            Demolition and disposal of Existing          2 days       Fri 6/11/20 Sat 7/11/20                                                                                                                    Excavator
                                   Driveway
     56                            Excavate to Subgrade                         1 day        Mon 9/11/20Mon 9/11/20                                                                                                                        Excavator
     57                            Trim Subgrade                                1 day        Tue 10/11/20Tue 10/11/20                                                                                                                         Grader Earthworks
     58                            HOLD POINT SUBGRADE INSPECTION               0 days       Tue 10/11/20Tue 10/11/20                                                                                                                         10/11
     59                            Supply and install SW - 0/A- 1/A- 2/A        1 day        Wed 11/11/20Wed 11/11/20                                                                                                                          SW Crew
     60                            FRP Pits                                     3 days       Thu 12/11/20Sat 14/11/20                                                                                                                                      Concretors
     61                            Supply and install Subsoil Drainage ~190M2 days           Mon 16/11/20Tue 17/11/20                                                                                                                                           Trencher
     62                            Supply and place 180mm Subbase               1 day        Wed         Wed                                                                                                                                                     Grader Pavement
                                   627M2 X 0.180M = 112M3                                    18/11/20    18/11/20
     63                            Supply and place Type M1 Kerb and            3 days       Thu         Sat 21/11/20                                                                                                                                                    Kerb SC
                                   Channel                                                   19/11/20
     64                            Supply and install KEU and headwall          0.5 days     Fri 20/11/20 Fri 20/11/20                                                                                                                                               Concretors
     65                            Supply and place 100mm base (534M2 X 1 day                Mon         Mon                                                                                                                                                                 Grader Pavement
                                   0.1M= 53.4M3)                                             23/11/20    23/11/20
     68                            Spread Site won topsoil to 100mm depth 1 day              Tue         Tue                                                                                                                                                                  Posi Track
                                                                                             24/11/20    24/11/20
     66                            Primer Seal                                  3 days       Fri 4/12/20 Mon 7/12/20                                                                                                                                                                                         SEAL Crew
     67                            Supply and place AC surfacing                1 day        Tue 8/12/20 Tue 8/12/20                                                                                                                                                                                          AC Crew
     20                   Submission of QA/ Survey                              5 days       Wed 9/12/20Mon 14/12/20




                                  Task                                     Summary                                Inactive Milestone                      Duration-only                           Start-only                                    External Milestone                          Critical Split
Project: 1. 202009 24 Lake Mac
                                  Split                                    Project Summary                        Inactive Summary                        Manual Summary Rollup                   Finish-only                                   Deadline                                    Progress
Date: Mon 28/09/20
                                  Milestone                                Inactive Task                          Manual Task                             Manual Summary                          External Tasks                                Critical                                    Manual Progress

Construction Program. Submitted in accordance with GCOC                                                                                                 Page 3                                                                                                                             1. 202009 24 Lake MacDonald Program

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.