1. 202009 24 Lake MacDonald Program

of 3

Page text shows just the words. Original shows the document exactly as it was published.

28/09/2020 - 2406 Lake MacDonald Drive, Cooroy                                                                                                                                                                                                                                                                                  Shadforth
ID          Task     Task Name                                                  Duration     Start       Finish                                       October 2020                                                      November 2020                                                      December 2020
            Mode                                                                                                           16     19   22   25   28    1       4     7     10     13   16   19   22    25       28     31    3      6      9     12         15   18      21   24     27   30    3      6         9   12    15     18   21
     77                            Subgrade Prep ~3100m2                        2 days       Fri 13/11/20 Sat 14/11/20                                                                                                                                  Grader Earthworks
     79                            Submission of Pavement CBR Results for 5 days             Fri 13/11/20 Wed                                                                                                                                                      Geotech
                                   approval                                                               18/11/20
     80                            HOLD POINT SUBGRADE INSPECTION               0 days       Wed 18/11/20Wed 18/11/20                                                                                                                                                 18/11
     81                            Supply and install SW - 0/B- 1/B- 2/B-3/B 1 day           Thu         Thu                                                                                                                                                          SW Crew
                                                                                             19/11/20    19/11/20
     84                            Supply and install Subsoil Drainage ~190M4 days           Thu 19/11/20Mon 23/11/20                                                                                                                                                         Trencher
     82                            Supply and install SW - 0/C- 1/C- 2/C        0.5 days     Fri 20/11/20 Fri 20/11/20                                                                                                                                                 SW Crew


     83                            FRP Pits                                     3 days       Fri 20/11/20 Tue 24/11/20                                                                                                                                                        Concretors
     85                            Supply and place 200mm Subbase               2 days       Tue         Wed                                                                                                                                                                       Grader Pavement
                                   ~3048M2 X 0.2M = 610M3                                    24/11/20    25/11/20
     86                            Supply and place Type M1 Kerb and            5 days       Thu         Tue 1/12/20                                                                                                                                                                         Kerb SC
                                   Channel 915m                                              26/11/20
     88                            Supply and install KEU and headwall          2 days       Mon 30/11/20Tue 1/12/20                                                                                                                                                                         Concretors
     87                            Spread Site won topsoil to 100mm depth 3 days             Wed         Fri 4/12/20                                                                                                                                                                                 Posi Track
                                                                                             2/12/20
     89                            Supply and place 120mm base (2807M2 2 days                Wed         Thu 3/12/20                                                                                                                                                                              Grader Pavement
                                   X 0.120M= 337M3)                                          2/12/20
     90                            Primer Seal                                  3 days       Fri 4/12/20 Mon 7/12/20                                                                                                                                                                                           SEAL Crew
     91                            Supply and place AC surfacing                1 day        Tue 8/12/20 Tue 8/12/20                                                                                                                                                                                            AC Crew
     92                          Lake MacDonald Drive Shoulders                 37 days      Tue 27/10/20Tue 8/12/20
     93                            Clearing and Grubbing                        2 days       Tue 27/10/20Wed 28/10/20                                                                                              Mulching Services
     94                            Strip Topsoil to Windrow                     2 days       Thu 29/10/20Fri 30/10/20                                                                                                 Excavator
     95                            Saw Cut to Existing pavement                 1 day        Sat 31/10/20 Sat 31/10/20                                                                                                  Saw Cutter
     96                            Excavate and dispose of shoulder             3 days       Mon 2/11/20Wed 4/11/20                                                                                                             Excavator
     97                            GST to Foundation                            1 day        Thu 5/11/20 Thu 5/11/20                                                                                                              Posi Track
     98                            Subgrade Prep                                1 day        Fri 6/11/20 Fri 6/11/20                                                                                                                 Posi Track
     99                            HOLD POINT SUBGRADE INSPECTION               0 days       Fri 6/11/20 Fri 6/11/20                                                                                                                    6/11
 100                               Supply and place 260mm Subbase               3 days       Sat 7/11/20 Tue                                                                                                                                   Posi Track
                                   372M2 X 0.260M = 97M3                                                 10/11/20
 101                               Supply and place 140mm base (372M2 X 3 days               Wed         Fri 13/11/20                                                                                                                                 Posi Track
                                   0.140M= 53M3)                                             11/11/20
 102                               Spread Site won topsoil to 100mm depth 1 day              Sat 14/11/20 Sat 14/11/20                                                                                                                                      Posi Track


 103                               Primer Seal                                  3 days       Fri 4/12/20 Mon 7/12/20                                                                                                                                                                                           AC Crew,SEAL Crew
 104                               Supply and place AC surfacing                1 day        Tue 8/12/20 Tue 8/12/20                                                                                                                                                                                            AC Crew
 105                             Finishing Works                                5 days       Wed 9/12/20Mon 14/12/20
 106                               Line marking and signage                     1 day        Wed 9/12/20Wed 9/12/20
 107                               Hydromulch                                   2 days       Thu 10/12/20Fri 11/12/20
 108                               Turf                                         2 days       Sat 12/12/20 Mon 14/12/20
     32                      DW08 - Middle Lots 4,8                             17 days      Fri 23/10/20 Wed 11/11/20
     33                          Clearing and Grubbing                          2 days       Fri 23/10/20 Sat 24/10/20                                                                                 Mulching Services
     34                          Strip Topsoil to Windrow                       2 days       Mon 26/10/20Tue 27/10/20                                                                                           Topsoil crew
     35                          GST to Foundation                              2 days       Wed 28/10/20Thu 29/10/20                                                                                                Grader Earthworks
     36                          Localised Cut to fill                          2 days       Fri 30/10/20 Sat 31/10/20                                                                                                  Excavator,Moxy Crew
     37                          Extend Dam                                     2 days       Mon 2/11/20Tue 3/11/20                                                                                                            Excavator,Moxy Crew
     38                          Trim Subgrades on Lot 4,8 (375m x 5.6m = 2 days             Mon         Tue 3/11/20                                                                                                           Grader Earthworks
                                 2100m2)                                                     2/11/20

                                  Task                                     Summary                                Inactive Milestone                      Duration-only                           Start-only                                     External Milestone                           Critical Split
Project: 1. 202009 24 Lake Mac
                                  Split                                    Project Summary                        Inactive Summary                        Manual Summary Rollup                   Finish-only                                    Deadline                                     Progress
Date: Mon 28/09/20
                                  Milestone                                Inactive Task                          Manual Task                             Manual Summary                          External Tasks                                 Critical                                     Manual Progress

Construction Program. Submitted in accordance with GCOC                                                                                                 Page 2                                                                                                                               1. 202009 24 Lake MacDonald Program
Log in to download the original file

1. 202009 24 Lake MacDonald Program.pdf · 758 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.