1. 202009 24 Lake MacDonald Program
28/09/2020 - 2406 Lake MacDonald Drive, Cooroy Shadforth
ID Task Task Name Duration Start Finish October 2020 November 2020 December 2020
Mode 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21
77 Subgrade Prep ~3100m2 2 days Fri 13/11/20 Sat 14/11/20 Grader Earthworks
79 Submission of Pavement CBR Results for 5 days Fri 13/11/20 Wed Geotech
approval 18/11/20
80 HOLD POINT SUBGRADE INSPECTION 0 days Wed 18/11/20Wed 18/11/20 18/11
81 Supply and install SW - 0/B- 1/B- 2/B-3/B 1 day Thu Thu SW Crew
19/11/20 19/11/20
84 Supply and install Subsoil Drainage ~190M4 days Thu 19/11/20Mon 23/11/20 Trencher
82 Supply and install SW - 0/C- 1/C- 2/C 0.5 days Fri 20/11/20 Fri 20/11/20 SW Crew
83 FRP Pits 3 days Fri 20/11/20 Tue 24/11/20 Concretors
85 Supply and place 200mm Subbase 2 days Tue Wed Grader Pavement
~3048M2 X 0.2M = 610M3 24/11/20 25/11/20
86 Supply and place Type M1 Kerb and 5 days Thu Tue 1/12/20 Kerb SC
Channel 915m 26/11/20
88 Supply and install KEU and headwall 2 days Mon 30/11/20Tue 1/12/20 Concretors
87 Spread Site won topsoil to 100mm depth 3 days Wed Fri 4/12/20 Posi Track
2/12/20
89 Supply and place 120mm base (2807M2 2 days Wed Thu 3/12/20 Grader Pavement
X 0.120M= 337M3) 2/12/20
90 Primer Seal 3 days Fri 4/12/20 Mon 7/12/20 SEAL Crew
91 Supply and place AC surfacing 1 day Tue 8/12/20 Tue 8/12/20 AC Crew
92 Lake MacDonald Drive Shoulders 37 days Tue 27/10/20Tue 8/12/20
93 Clearing and Grubbing 2 days Tue 27/10/20Wed 28/10/20 Mulching Services
94 Strip Topsoil to Windrow 2 days Thu 29/10/20Fri 30/10/20 Excavator
95 Saw Cut to Existing pavement 1 day Sat 31/10/20 Sat 31/10/20 Saw Cutter
96 Excavate and dispose of shoulder 3 days Mon 2/11/20Wed 4/11/20 Excavator
97 GST to Foundation 1 day Thu 5/11/20 Thu 5/11/20 Posi Track
98 Subgrade Prep 1 day Fri 6/11/20 Fri 6/11/20 Posi Track
99 HOLD POINT SUBGRADE INSPECTION 0 days Fri 6/11/20 Fri 6/11/20 6/11
100 Supply and place 260mm Subbase 3 days Sat 7/11/20 Tue Posi Track
372M2 X 0.260M = 97M3 10/11/20
101 Supply and place 140mm base (372M2 X 3 days Wed Fri 13/11/20 Posi Track
0.140M= 53M3) 11/11/20
102 Spread Site won topsoil to 100mm depth 1 day Sat 14/11/20 Sat 14/11/20 Posi Track
103 Primer Seal 3 days Fri 4/12/20 Mon 7/12/20 AC Crew,SEAL Crew
104 Supply and place AC surfacing 1 day Tue 8/12/20 Tue 8/12/20 AC Crew
105 Finishing Works 5 days Wed 9/12/20Mon 14/12/20
106 Line marking and signage 1 day Wed 9/12/20Wed 9/12/20
107 Hydromulch 2 days Thu 10/12/20Fri 11/12/20
108 Turf 2 days Sat 12/12/20 Mon 14/12/20
32 DW08 - Middle Lots 4,8 17 days Fri 23/10/20 Wed 11/11/20
33 Clearing and Grubbing 2 days Fri 23/10/20 Sat 24/10/20 Mulching Services
34 Strip Topsoil to Windrow 2 days Mon 26/10/20Tue 27/10/20 Topsoil crew
35 GST to Foundation 2 days Wed 28/10/20Thu 29/10/20 Grader Earthworks
36 Localised Cut to fill 2 days Fri 30/10/20 Sat 31/10/20 Excavator,Moxy Crew
37 Extend Dam 2 days Mon 2/11/20Tue 3/11/20 Excavator,Moxy Crew
38 Trim Subgrades on Lot 4,8 (375m x 5.6m = 2 days Mon Tue 3/11/20 Grader Earthworks
2100m2) 2/11/20
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: 1. 202009 24 Lake Mac
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Mon 28/09/20
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Construction Program. Submitted in accordance with GCOC Page 2 1. 202009 24 Lake MacDonald Program