1. 202009 24 Lake MacDonald Program
28/09/2020 - 2406 Lake MacDonald Drive, Cooroy Shadforth
ID Task Task Name Duration Start Finish October 2020 November 2020 December 2020
Mode 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21
1 2406 - Lake MacDonald Drive, Cooroy 75 days Thu 24/09/20Sat 19/12/20
2 Contract Prelims 75 days Thu 24/09/20Sat 19/12/20
3 Execution of Contract 0 days Thu 24/09/20Thu 24/09/20 24/09
4 Submission of Insurances 0 days Thu 24/09/20Thu 24/09/20 24/09
5 Submission of WMP 5 days Thu 24/09/20Tue 29/09/20
6 Submission of EMP 5 days Thu 24/09/20Tue 29/09/20
7 Submission of ESC 5 days Thu 24/09/20Tue 29/09/20
8 Submission of TMP/TGS 5 days Thu 24/09/20Tue 29/09/20
9 Notification to Council of Prestart Documents 5 days Wed Mon
30/09/20 5/10/20
10 OPW Contract Prestart with Council 0 days Mon 5/10/20Mon 5/10/20 5/10
11 Submission of Pre Construction Condition 0 days Mon Mon 5/10
Photographs 5/10/20 5/10/20
12 OPW Clause 16. The developer must notify 0 days Mon Mon 5/10
Council’s Traffic Engineer for any works involving 5/10/20 5/10/20
the removal or modification of existing council
traffic signs and/or parking bays prior to such
works commencing
13 Demobilisation 5 days Tue 15/12/20Sat 19/12/20
14 Demobilise ESC controls 2 days Tue 15/12/20Wed 16/12/20
15 Demobilise site sheds 1 day Thu 17/12/20Thu 17/12/20
16 Demobilise equipment 2 days Fri 18/12/20 Sat 19/12/20
17 Construction Duration Tender 60 days / 10 Weeks 60 days Mon Mon
5/10/20 14/12/20
18 Date of possession 0 days Mon 5/10/20Mon 5/10/20 5/10
19 Practical Completion / On maintenance 0 days Mon 14/12/20Mon 14/12/20 14/12
21 Construction 60 days Tue 6/10/20 Mon 14/12/20
22 Site Establishment 11 days Tue 6/10/20 Sat 17/10/20
23 Letter Box Drop - Community Notification 5 days Tue 6/10/20 Sat 10/10/20 Comms
24 Establish Survey 3 days Tue 6/10/20 Thu 8/10/20 Survey
25 Mobilisation of site sheds and compound 5 days Tue 6/10/20 Sat 10/10/20
28 Survey Pre-Stripped surface 2 days Fri 9/10/20 Sat 10/10/20 Survey
27 Mobilisation of Traffic control devices 0 days Sat 10/10/20 Sat 10/10/20 10/10
29 CBR Testing of subgrades in cut 0 days Sat 10/10/20 Sat 10/10/20 10/10
26 Mobilisation of ESC Controls 6 days Mon 12/10/20Sat 17/10/20 Erosion Sediment Crew
30 Processing of CBRS 5 days Mon 12/10/20Fri 16/10/20 Geotech
31 Pavement Design Approval 0 days Fri 16/10/20 Fri 16/10/20 16/10
69 Road 1 & Lake Macdonald Drive Shoulders 49 days Mon Mon
19/10/20 14/12/20
70 Road 1 44 days Mon 19/10/20
Tue 8/12/20
71 Clearing and Grubbing 4 days Mon 19/10/20Thu 22/10/20 Mulching Services
72 Supply and install SW - 0/X2 - 1/X2 - 2/X2 0.5 days Fri 23/10/20 Fri 23/10/20 SW Crew
73 Supply and install SW - 0/X3 - 1/X3 0.5 days Fri 23/10/20 Fri 23/10/20 SW Crew
74 Strip Topsoil to Windrow 3 days Sat 24/10/20 Tue 27/10/20 Excavator
75 GST to Foundation 4 days Wed 28/10/20Sat 31/10/20 Grader Earthworks
76 Localised Cut to fill 10 days Mon 2/11/20Thu 12/11/20 Excavator,Moxy Crew
78 CBR Testing of subgrades 0 days Thu 12/11/20Thu 12/11/20 12/11
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: 1. 202009 24 Lake Mac
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Mon 28/09/20
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Construction Program. Submitted in accordance with GCOC Page 1 1. 202009 24 Lake MacDonald Program