1. 202009 24 Lake MacDonald Program
28/09/2020 - 2406 Lake MacDonald Drive, Cooroy Shadforth
ID Task Task Name Duration Start Finish October 2020 November 2020 December 2020
Mode 16 19 22 25 28 1 4 7 10 13 16 19 22 25 28 31 3 6 9 12 15 18 21 24 27 30 3 6 9 12 15 18 21
39 HOLD POINT SUBGRADE INSPECTION 0 days Tue 3/11/20 Tue 3/11/20 3/11
40 Construct Site Entrance 1 day Wed 4/11/20Wed 4/11/20 Grader Pavement
41 Lot 4,8Supply and place 2.4 subbase 2 days Thu 5/11/20 Fri 6/11/20 Grader Pavement
@100mm (375M X 5.6M ~210M3)
42 Lot 4,8 Supply and place 2.2 base 2 days Sat 7/11/20 Mon Grader Pavement
@100mm(375M X 4.8M ~180M3) 9/11/20
43 Lot 4,8 Spread Site won topsoil to 100mm 2 days Tue Wed Grader Pavement
depth 10/11/20 11/11/20
44 Road 2 Wilgee Court - Lot 5,6 7 39 days Sat 24/10/20Tue 8/12/20
45 Resident Consultation with Driveway 0 days Sat 24/10/20 Sat 24/10/20 24/10
Access
46 Clearing and Grubbing 1 day Mon 26/10/20Mon 26/10/20 Mulching Services
47 Strip Topsoil to Windrow 2 days Tue 27/10/20Wed 28/10/20 Topsoil crew
48 Localised Cut to fill 2 days Thu 29/10/20Fri 30/10/20 Excavator,Moxy Crew
49 Trim Subgrades on Lot 5,6,7 (348m x 5.6m = 2 days Sat 31/10/20 Mon Grader Earthworks
1948m2) 2/11/20
50 HOLD POINT SUBGRADE INSPECTION 0 days Mon 2/11/20Mon 2/11/20 2/11
51 Lot 5,6,7 Supply and place 2.4 subbase 1 day Tue 3/11/20 Tue 3/11/20 Grader Pavement
@100mm (348M X 5.6M ~194M3)
52 Lot 5,6,7 Supply and place 2.2 base 2 days Wed Thu 5/11/20 Grader Pavement
@100mm(348M X 4.8M ~167M3) 4/11/20
53 Lot 5,6,7 Spread Site won topsoil to 100mm 2 days Fri 6/11/20 Sat 7/11/20 Grader Pavement
depth
54 Road 2 Wilgee Court - Driveway 28 days Fri 6/11/20 Tue 8/12/20
55 Demolition and disposal of Existing 2 days Fri 6/11/20 Sat 7/11/20 Excavator
Driveway
56 Excavate to Subgrade 1 day Mon 9/11/20Mon 9/11/20 Excavator
57 Trim Subgrade 1 day Tue 10/11/20Tue 10/11/20 Grader Earthworks
58 HOLD POINT SUBGRADE INSPECTION 0 days Tue 10/11/20Tue 10/11/20 10/11
59 Supply and install SW - 0/A- 1/A- 2/A 1 day Wed 11/11/20Wed 11/11/20 SW Crew
60 FRP Pits 3 days Thu 12/11/20Sat 14/11/20 Concretors
61 Supply and install Subsoil Drainage ~190M2 days Mon 16/11/20Tue 17/11/20 Trencher
62 Supply and place 180mm Subbase 1 day Wed Wed Grader Pavement
627M2 X 0.180M = 112M3 18/11/20 18/11/20
63 Supply and place Type M1 Kerb and 3 days Thu Sat 21/11/20 Kerb SC
Channel 19/11/20
64 Supply and install KEU and headwall 0.5 days Fri 20/11/20 Fri 20/11/20 Concretors
65 Supply and place 100mm base (534M2 X 1 day Mon Mon Grader Pavement
0.1M= 53.4M3) 23/11/20 23/11/20
68 Spread Site won topsoil to 100mm depth 1 day Tue Tue Posi Track
24/11/20 24/11/20
66 Primer Seal 3 days Fri 4/12/20 Mon 7/12/20 SEAL Crew
67 Supply and place AC surfacing 1 day Tue 8/12/20 Tue 8/12/20 AC Crew
20 Submission of QA/ Survey 5 days Wed 9/12/20Mon 14/12/20
Task Summary Inactive Milestone Duration-only Start-only External Milestone Critical Split
Project: 1. 202009 24 Lake Mac
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline Progress
Date: Mon 28/09/20
Milestone Inactive Task Manual Task Manual Summary External Tasks Critical Manual Progress
Construction Program. Submitted in accordance with GCOC Page 3 1. 202009 24 Lake MacDonald Program