1. 202009 24 Lake MacDonald Program

of 3

Page text shows just the words. Original shows the document exactly as it was published.

28/09/2020 - 2406 Lake MacDonald Drive, Cooroy                                                                                                                                                                                                                                                                                Shadforth
ID          Task     Task Name                                                  Duration     Start       Finish                                       October 2020                                                      November 2020                                                    December 2020
            Mode                                                                                                           16     19   22   25   28    1       4     7     10     13   16   19   22    25        28    31    3      6     9     12         15   18      21   24    27   30    3      6         9   12    15     18   21
     39                          HOLD POINT SUBGRADE INSPECTION                 0 days       Tue 3/11/20 Tue 3/11/20                                                                                                           3/11
     40                          Construct Site Entrance                        1 day        Wed 4/11/20Wed 4/11/20                                                                                                               Grader Pavement
     41                          Lot 4,8Supply and place 2.4 subbase            2 days       Thu 5/11/20 Fri 6/11/20                                                                                                                  Grader Pavement
                                 @100mm (375M X 5.6M ~210M3)
     42                          Lot 4,8 Supply and place 2.2 base              2 days       Sat 7/11/20 Mon                                                                                                                               Grader Pavement
                                 @100mm(375M X 4.8M ~180M3)                                              9/11/20
     43                          Lot 4,8 Spread Site won topsoil to 100mm       2 days       Tue         Wed                                                                                                                                   Grader Pavement
                                 depth                                                       10/11/20    11/11/20
     44                      Road 2 Wilgee Court - Lot 5,6 7                    39 days      Sat 24/10/20Tue 8/12/20
     45                          Resident Consultation with Driveway            0 days       Sat 24/10/20 Sat 24/10/20                                                                                24/10
                                 Access
     46                          Clearing and Grubbing                          1 day        Mon 26/10/20Mon 26/10/20                                                                                          Mulching Services
     47                          Strip Topsoil to Windrow                       2 days       Tue 27/10/20Wed 28/10/20                                                                                              Topsoil crew
     48                          Localised Cut to fill                          2 days       Thu 29/10/20Fri 30/10/20                                                                                                 Excavator,Moxy Crew
     49                          Trim Subgrades on Lot 5,6,7 (348m x 5.6m = 2 days           Sat 31/10/20 Mon                                                                                                               Grader Earthworks
                                 1948m2)                                                                  2/11/20
     50                          HOLD POINT SUBGRADE INSPECTION                 0 days       Mon 2/11/20Mon 2/11/20                                                                                                          2/11
     51                          Lot 5,6,7 Supply and place 2.4 subbase         1 day        Tue 3/11/20 Tue 3/11/20                                                                                                          Grader Pavement
                                 @100mm (348M X 5.6M ~194M3)
     52                          Lot 5,6,7 Supply and place 2.2 base            2 days       Wed         Thu 5/11/20                                                                                                                Grader Pavement
                                 @100mm(348M X 4.8M ~167M3)                                  4/11/20
     53                          Lot 5,6,7 Spread Site won topsoil to 100mm 2 days           Fri 6/11/20 Sat 7/11/20                                                                                                                    Grader Pavement
                                 depth
     54                          Road 2 Wilgee Court - Driveway                 28 days      Fri 6/11/20 Tue 8/12/20
     55                            Demolition and disposal of Existing          2 days       Fri 6/11/20 Sat 7/11/20                                                                                                                    Excavator
                                   Driveway
     56                            Excavate to Subgrade                         1 day        Mon 9/11/20Mon 9/11/20                                                                                                                        Excavator
     57                            Trim Subgrade                                1 day        Tue 10/11/20Tue 10/11/20                                                                                                                         Grader Earthworks
     58                            HOLD POINT SUBGRADE INSPECTION               0 days       Tue 10/11/20Tue 10/11/20                                                                                                                         10/11
     59                            Supply and install SW - 0/A- 1/A- 2/A        1 day        Wed 11/11/20Wed 11/11/20                                                                                                                          SW Crew
     60                            FRP Pits                                     3 days       Thu 12/11/20Sat 14/11/20                                                                                                                                      Concretors
     61                            Supply and install Subsoil Drainage ~190M2 days           Mon 16/11/20Tue 17/11/20                                                                                                                                           Trencher
     62                            Supply and place 180mm Subbase               1 day        Wed         Wed                                                                                                                                                     Grader Pavement
                                   627M2 X 0.180M = 112M3                                    18/11/20    18/11/20
     63                            Supply and place Type M1 Kerb and            3 days       Thu         Sat 21/11/20                                                                                                                                                    Kerb SC
                                   Channel                                                   19/11/20
     64                            Supply and install KEU and headwall          0.5 days     Fri 20/11/20 Fri 20/11/20                                                                                                                                               Concretors
     65                            Supply and place 100mm base (534M2 X 1 day                Mon         Mon                                                                                                                                                                 Grader Pavement
                                   0.1M= 53.4M3)                                             23/11/20    23/11/20
     68                            Spread Site won topsoil to 100mm depth 1 day              Tue         Tue                                                                                                                                                                  Posi Track
                                                                                             24/11/20    24/11/20
     66                            Primer Seal                                  3 days       Fri 4/12/20 Mon 7/12/20                                                                                                                                                                                         SEAL Crew
     67                            Supply and place AC surfacing                1 day        Tue 8/12/20 Tue 8/12/20                                                                                                                                                                                          AC Crew
     20                   Submission of QA/ Survey                              5 days       Wed 9/12/20Mon 14/12/20




                                  Task                                     Summary                                Inactive Milestone                      Duration-only                           Start-only                                    External Milestone                          Critical Split
Project: 1. 202009 24 Lake Mac
                                  Split                                    Project Summary                        Inactive Summary                        Manual Summary Rollup                   Finish-only                                   Deadline                                    Progress
Date: Mon 28/09/20
                                  Milestone                                Inactive Task                          Manual Task                             Manual Summary                          External Tasks                                Critical                                    Manual Progress

Construction Program. Submitted in accordance with GCOC                                                                                                 Page 3                                                                                                                             1. 202009 24 Lake MacDonald Program
Log in to download the original file

1. 202009 24 Lake MacDonald Program.pdf · 758 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗