               10.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      the approved plans/documents and conditions detailed in this Decision Notice;
                      b.      the relevant conditions of the higher order Material Change of Use approval
                              MCU24/0022 to which this approval relates;
                      c.      all relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines;
                      d.      the latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                     Works within Road Reserves
               11.    No removal of street trees is permitted without Council’s prior written approval.
               12.    Safe pedestrian access on all streets in the vicinity of the development must be maintained
                      at all times. Should road closures be necessary to carry out construction works, Council’s
                      Engineering Officer must be notified prior to the proposed closure and all requirements
                      complied with.
               13.    All works must match neatly with existing road and verge features. Additional works beyond
                      the frontage may be required to provide an acceptable transition to existing road and verge
                      profiles.
                     Driveways
               14.    Driveway crossovers must be constructed generally in accordance Council’s Standard
                      Drawings RS-049 and RS-050.
               15.    The verge area must be reinstated to a grassed verge area and must be provided with 100
                      mm topsoil and grass seed or turf and must be maintained by the developer until established.
                      The use of pebbles/rocks/gravel on road reserve is not supported by Council.
               16.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      the driveway surfacing must consist of either an approved hot mixed asphaltic concrete
                              or patterned/plain concrete;
                      b.      the driveway must be in accordance with the requirements of AS2890.1 Off-Street Car
                              Parking for longitudinal and crossfall gradients;
                      c.      the driveway must be constructed so as to not concentrate or direct stormwater runoff
                              onto neighbouring properties;
                      d.      have a minimum clearance of 500mm from any Unitywater/Energex/Telstra asset,
                              unless a written approval is obtained from Unitywater/Energex/Telstra and submitted
                              to Council;
                      e.      any stormwater kerb outlet in close proximity to the edge of the new driveway must be
                              provided with an approved kerb adaptor;
                      f.      any existing kerb sections requiring removal due to the works must be saw-cut and
                              removed to allow for a smooth and neat finish with the new driveway.
               17.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer.
                      Stormwater Drainage
               18.    The constructed driveway must not cause additional ponding on the road formation or the
                      road reserve.




                                                                                                          Page 3 of 6
Document Set ID: 23327801
Version: 4, Version Date: 04/11/2024

Used in these records

About this file

File size
170 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Decision Notice - Approved by Delegation of Authority OPW24_0172 {As Published}.pdf · 170 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.