Minor Change Existing Approval 51988.2770.02

of 9

Page text shows just the words. Original shows the document exactly as it was published.

                      Earthworks and Retaining Walls
               23.    All earthworks and associated batters must be contained entirely within the subject site
                      unless written permission from the respective landowner(s) is provided to Council. All
                      earthworks must be undertaken in accordance with the provisions of Australian Standard
                      AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
                      Damage to Services and Assets
               24.    Infrastructure including reticulated water, sewerage, stormwater, and electricity must be
                      protected from damage and made safe to the standard required by the regulatory authority.
               25.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                              Any repair work which proposes to alter the alignment or level of existing services and
                              assets must first be referred to the relevant service authority for approval.
                      Landscaping Works
               26.    Existing trees on the site must be retained, except where required to be removed to
                      accommodate the approved building. In this regard, the removal of vegetation must not
                      extend beyond 3 metres of the building footprint.
               27.    Existing vegetation in the road reserve must be retained, unless written authorisation from
                      Council is granted for the clearing.
               28.    Trees to be retained must be protected from clearing or construction activities by:
                      a.      clearly marking vegetation to be retained with flagging tape
                      b.      installing protective fencing around the drip line of the vegetation
                      c.      restricting stockpiling, storage and vehicle parking to those areas which are already
                              cleared
                      d.      using low impact construction techniques around vegetation.
               29.    The development site must be landscaped. The works must be undertaken in accordance
                      with the Noosa Plan for that specific area and must include:
                      a.      provision of dense screen planting for a minimum length of 60m along the Mckinnon
                              Drive frontage (west of the Sports Complex Entrance) to screen the building from
                              Mckinnon Drive, in accordance with Planning Scheme Policy PSP2 – Landscaping.
                      b.      Landscape screening provided in the areas identified on the Council annotated plan.
                              The landscaping is to incorporate trees, shrubs and ground covers capable of
                              screening the built form at maturity. The species must be selected in accordance with
                              Planning Scheme Policy 2 – Landscaping.
               30.    All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
                      Demolition
               31.    All building materials containing asbestos, including asbestos cement sheeting or roofing and
                      lagging, are removed from the building prior to demolition or relocation.
               32.    Removal of building materials containing asbestos must be undertaken by a licensed
                      asbestos removalist.




                                                                                                        Page 5 of 9
Document Set ID: 23255088
Version: 4, Version Date: 23/09/2024
Log in to download the original file

Minor Change Existing Approval 51988.2770.02.pdf · 163 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.