Minor Change Existing Approval 51988.2770.02
5. The ‘Plumbing and Drainage Regulation 2019’ states work necessary for installing, replacing
or removing a testable backflow prevention device is included work for Notifiable Work.
Removal must be carried out by a suitably licenced plumber who shall submit a Form 9
(Registration & Report on Inspection and Testing of Backflow Prevention Devices) and Form
4 (Notifiable Works Form) to the QBCC (Queensland Building Construction Commission)
within 10 days of completing the work. Notification to Council once works and document
submission is complete allows removal of backflow prevention devices from Council’s
backflow register.
6. All activities associated with the removal or demolition must be contained within the property
boundaries at all times with site gateways opening inwards and at approved locations only.
If the works cannot be contained within the site, a road and footpath permit must be applied
for.
7. PROPERTY NOTES
Not Applicable
8. VARIATION APPROVAL DETAILS
Not Applicable
9. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Building Works All building work.
10. SUBMISSIONS
Not Applicable
11. RIGHTS OF APPEAL
You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Planning Act 2016 is attached.
12. OTHER DETAILS
If you wish to obtain more information about the decision, electronic copies are available on line at
www.noosa.qld.gov.au or at Council Offices.
Yours faithfully,
Patrick Murphy
Manager, Development Assessment
Development & Regulation
Enc: Appeal Rights
Infrastructure Charge Notice
Approved Plans/Documents
Page 7 of 9
Document Set ID: 23255088
Version: 4, Version Date: 23/09/2024
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the original