Noosa on Weyba
QCP Assessment
                                                                                         CI"Cardnoe

5                 Flood Modelling


5.1      Summary
Flood modelling has been conducted for the site to determine the local and regional peak flood levels and to

help determine the potential impact of development.               For this erosion area analysis the flood model was
used to run a tidal simulation based on the 2100 HAT to determine the actual future tidal inundation extents.
A summary of the flood model set up is provided in this section, for further details please refer to the Cardno
Flood Study (October,2012).


5.2      Flood Modelling

5.2.1            Available Models

Regional flood modelling of the Noosa River has previously been conducted by Sunshine Coast Regional
Council using the Mike 11 computer program. The results of this study are outlined in the Noosa River Flood

Study (JWP,1995). This modelling was recently updated by Council to use Version 2010 of Mike 11. This
modelling does not include the local tributaries, including Eenie Creek and Keyser Creek, and therefore was
not of sufficient quality to determine flood levels throughout the site. It is noted that the regional flood

modelling does account for the impact of storm-tide. The regional flood levels in Lake Weyba are:

      .    100 year ARI      =   2.09 mAHD

      .    20 year ARI = 1.53 mAHD

      .    10 year ARI = 1.45 mAHD




The peak 100 year ARI regional flood level in Lake Weyba was determined as a combination of 100 year
ARI inflows and the 20 year ARI storm surge (per comm. Geoff Newell, SCRC). An equivalent 100 year ARI
event is considered to be the 20 year ARI inflows and the 100 year ARI storm surge. The maximum of these
two events was used to determine the 100 year ARI regional flood levels in Noosa River. The 30 hour storm
was the    peak regional event for Lake Weyba.
The storm-tide levels used as tailwater conditions in the Noosa River Flood Study (JWP,1995)were:

      .    100 year ARI = 1.8 mAHD

      .    20 year ARI = 1.5 mAHD

A detailed storm tide study of the Noosa River has recently been conducted for Sunshine Coast Regional
Council (SCRC). However, at the time of writing the final results of this analysis were not available and the
report has yet to undergo peer review.

5.2.2            TUFLOW Model

The flow patterns and interactions between the different creeks and Lake Weyba are quite complex and it
was determined           the software TUFLOW should be used for analytical purposes. TUFLOW is a two and one
dimensional hydrodynamic modelling              system. The model extent included Eenie Creek and its tributaries,
Keyser Creek, Lake Weyba and Weyba Creek. Lake Weyba and Weyba Creek were modelled in 1 Dusing
the Mike 11 cross-sections from the regional flood model, and trimmed where necessary to avoid a double

up of storage. The model extended downstream to section Weyba 6.5, which is located at Weyba Road.
For the remaining areas, Aerial Laser Survey (ALS) obtained from the Department of Environment and
Heritage Protection (DEHP),formerly DERM, was used to develop the Digital Terrain Model (DTM).
The TUFLOW model              was   validated   against the February 2012 flood event which resulted in significant
inundation of properties along Lake Entrance Boulevard.




Northbrook Corp Pty Ltd and J&K Hofmann                     Version 2                                  15 October 2012
QCP Assessment v2.docx                               Commercial in Confidence                                  Page 5

Used in these records

About this file

File size
26.4 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Part 10 of 37 Appendix 8 - Queensland Coastal Plan Assessment MCU12_0208.pdf · 26.4 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.