Appendix E Traffic Impact Assessment Report · MCU22/0038

of 48

Text shows just the words. Original shows the document exactly as it was published.

Memorandum
      To:         Kelly Alcorn                                        At:         Stockwell Development Group Pty Ltd
      From:       Matthew Creighton / Jeff                            At:         SLR Consulting Australia Pty Ltd
                  Baczynski
      Date:       16 March 2022                                       Ref:        620.30769-M01-v1.0 Traffic Impact
                                                                                  Statement 2022 03 16.docx
      Subject:    Proposed Medical Centre
                  Lot 22, Noosa Business Centre
                  Traffic Impact Statement


CONFIDENTIALITY
This document is confidential and may contain legally privileged information. If you are not a named or
authorised recipient you must not read, copy, distribute or act in reliance on it. If you have received this document
in error, please telephone our operator immediately and return the document by mail.



1           Introduction

1.1         Overview

SLR Consulting Australia Pty Ltd (SLR) has been engaged by Stockwell Development Group Pty Ltd (Stockwell) to
provide traffic engineering advice and prepare a Traffic Impact Statement (TIS) as part of a proposed medical
centre to be located on a new lot (Lot 22) within the Noosa Business Centre in Noosaville. Plans of the subject
development are provided at Attachment A for reference.

The intent of this TIS is to document the traffic engineering advice and assess the consistency of the proposal
against relevant design standards, planning requirements and good engineering practice to inform Noosa Shire
Council’s assessment of a planning application to facilitate construction of the subject development. Specifically,
areas of focus for this TIS include site access as well as the design and supply of car parking infrastructure.

1.2         Planning Context

On 21 September 2021 Noosa Shire Council approved a Request to Apply the Superseded Planning Scheme
(being the Noosa Plan 2006) in relation to the subject development. Consequently, the proponent is lodging a
code assessable development application seeking approval of the proposal pursuant to the requirements of the
Superseded Planning Scheme in place of the impact assessment requirements prescribed for the subject
development within Council’s current planning scheme. This TIS has therefore been written to address relevant
code requirements focussing on internal design aspects given that the proposal involves the development of a
lot within a master planned town centre.




                       SLR Consulting Australia Pty Ltd Level 16, 175 Eagle Street Brisbane QLD 4000 Australia (PO Box 26 Spring Hill QLD 4004)
                                                                                              T: +61 7 3858 4800 E: [email protected]
                                                                                                    www.slrconsulting.com ABN 29 001 584 612
Full text of the other 47 pages

Page 2

 Proposed Medical Centre                                                                   SLR Ref: 620.30769-M01-v1.0 Traffic Impact
 Lot 22, Noosa Business Centre                                                                             Statement 2022 03 16.docx
 Traffic Impact Statement                                                                                        Date: 16 March 2022




2           Subject Site

2.1         Site Context

The proposed development is to be located on a new lot (Lot 22) within the broader Noosa Business Centre
development and fronts both Hoffman Drive to the west and an unnamed private access road separating the
neighbouring Emporium Showroom Complex from the Noosa Civic shopping centre to the south. The site
otherwise houses an access easement along its western boundary which grants access rights to the adjacent Lot
1 as well as a landscape buffer to Eenie Creek Road to the north as shown in Figure 1.

Figure 1      Site Location




The subject site is located within the local government jurisdiction of Noosa Shire Council (Council), with
Council’s Enterprise Mapping System designating the site as being within Precinct 5B – Showroom of the Noosa
Business Centre Precinct.

2.2         Surrounding Road Network

Details of the key roads proximate to the subject site as shown in Figure 1 are summarised within Table 1.

Table 1       Key Surrounding Roads
 Road Name                Authority   Classification   Existing Form                                                  Speed Limit
                                                       Dual carriageway with 2 lanes in each direction plus
 Eenie Creek Road          Council       Arterial                                                                       60km/h
                                                       bicycle lanes, urban cross-section (kerb and channel)
 Hoffman Drive             Council      Collector      2-4 lanes, divided, bicycle lanes, urban cross-section           50km/h
 Unnamed Road              Council        Local        2 lanes, divided, bicycle lanes, urban cross-section             30km/h




                                                              Page 2

Page 3

 Proposed Medical Centre                                                         SLR Ref: 620.30769-M01-v1.0 Traffic Impact
 Lot 22, Noosa Business Centre                                                                   Statement 2022 03 16.docx
 Traffic Impact Statement                                                                              Date: 16 March 2022




2.3         Road Network Planning

In order to ensure that the subject development does not compromise the delivery of any planned infrastructure
works, Council’s Local Government Infrastructure Plan (LGIP) has been reviewed to identify any projects within
the vicinity of the site. Table 2 summarises the details of the works identified as part of this review.

Table 2       Nearby Road Upgrade Projects
 Reference       Description                                                      Timing                     Cost
 R9              Noosaville, Walter Hay Dr / Eenie Creek Rd – Upgrade capacity   2021-2026                $199,551

It is noted that the location of the abovementioned works is not on the immediate frontage of the subject site
and thus, while the exact scope of works is unknown at the time of writing, the proposed development is unlikely
to impede the delivery of the prescribed works.


3           Development Overview

3.1         Yield

Based on the plans prepared by Buchan dated 15 March 2022 (a copy of which is provided at Attachment A), the
subject development is proposed to consist of individual medical tenancies totalling 2,170m2 gross floor area
(GFA).

3.2         Site Access

Access to the subject development is provided from the internal private ring road traversing the broader Noosa
Business Centre site via an existing crossover, which then provides access to some at-grade car parking along
Easement AB and the basement parking area via a ramp at the rear of the site.

No direct road access is proposed owing to the frontage of the site to two roundabouts. The proposed access
arrangements are illustrated on Figure 2.




                                                          Page 3

Page 4

 Proposed Medical Centre                                                       SLR Ref: 620.30769-M01-v1.0 Traffic Impact
 Lot 22, Noosa Business Centre                                                                 Statement 2022 03 16.docx
 Traffic Impact Statement                                                                            Date: 16 March 2022




Figure 2      Proposed Site Access Arrangements




Figure 2 does however confirm that direct pedestrian access to the site’s road frontages will be provided for
convenience and to separate these demands from vehicular traffic movements.

3.3         Car Parking

The majority of the site’s car parking will be housed in two basement levels containing a total of 91 spaces
beneath the proposed medical centre accessed via Easement AB as previously described in Section 3.2. An
additional eight spaces (including two spaces reserved for the use of persons with a disability) are also proposed
along Easement AB adjacent to the pedestrian entry to the facility to accommodate ambulances and mobility
impaired patients, therefore equating to a total parking supply of 99 spaces.

3.4         Bicycle Parking

Bicycle parking facilities are proposed for both customer and staff use, with four racks (accommodating up to
eight bicycles) proposed at the front of the facility adjacent to the lift for public use.




                                                      Page 4

Page 5

 Proposed Medical Centre                                                               SLR Ref: 620.30769-M01-v1.0 Traffic Impact
 Lot 22, Noosa Business Centre                                                                         Statement 2022 03 16.docx
 Traffic Impact Statement                                                                                    Date: 16 March 2022




4           Design Considerations

4.1         Reference Documents

A review of the proposed design of internal traffic and transport infrastructure has been undertaken against the
relevant design standards specified within the following documents:
      ·     The following parts of the Australian Standards for parking facilities (AS2890):
            ·    Part 1: Off-street car parking (AS2890.1).
            ·    Part 2: Off-street commercial vehicle facilities (AS2890.2).
            ·    Part 3: Bicycle parking (AS2890.3).
            ·    Part 6: Off-street parking for people with disabilities (AS2890.6).
      ·     The Driveways and Carparking Code within the Noosa Plan 2006.

The design of each of the relevant traffic and transport components of the proposal are discussed relative to the
requirements of the abovementioned reference documents within the following sections of this TIS.

Swept path drawings have also been prepared for key vehicle movements to demonstrate how vehicles would
access and manoeuvre within the site. Copies of these drawings are provided at Attachment B for reference.

4.2         Site Access

As previously mentioned in Section 3.2 herein, the subject development does not propose to achieve direct site
access via the public road frontages, but rather makes use of the existing Easement AB along the site’s south-
eastern boundary which is a private road. Consequently, the requirements specified within Council’s standard
drawings are not strictly applicable but rather the proposed form of the access has been dictated by the design
of the adjacent basement access ramp and swept path requirements.

Notwithstanding the above, it is however noted that the width of the access is consistent with that specified for
Type B driveways on Council’s standard drawing RS-051.

4.3         Car Parking & Circulation

The results of an assessment of the design of internal car parking and circulation infrastructure against the
requirements of the standards described in Section 4.1 are summarised within Table 3.

Table 3         Car Parking & Circulation Design Compliance Assessment
 Design Component                                  Proposed Design              Applicable Standard               Compliance
 Parking space dimensions (User Class 3)               2.6m x 5.4m              Figure 2.2, AS2890.1                    ü
                                               2.4m x 5.4m adjacent to a
 PWD parking space dimensions                                                   Figure 2.1, AS2890.6                    ü
                                                2.4x x 5.4m shared area
 Parking aisle width                                Minimum 6.2m                Figure 2.1, AS2890.1                    ü
 Basement ramp width                                      7.1m              Clause 2.5.2(a)(ii), AS2890.1               ü
                                                Maximum 1:5 with 1:10       Clause 2.5.3(a)(ii), AS2890.1
 Basement ramp grade                                                                                                    ü
                                                     transitions           Clause 2.5.3(d) & (e), AS2890.1




                                                            Page 5

Page 6

 Proposed Medical Centre                                                           SLR Ref: 620.30769-M01-v1.0 Traffic Impact
 Lot 22, Noosa Business Centre                                                                     Statement 2022 03 16.docx
 Traffic Impact Statement                                                                                Date: 16 March 2022




The results of the design compliance assessment presented in Table 3 confirm that the proposed design of the
at-grade and basement car parking areas is generally consistent with relevant design standards. It is further
noted that the design includes parking aisles and basement ramps which are wider than those required by
AS2890.1, therefore enhancing internal manoeuvrability and accessibility.

Given the design of the basement access ramps adopts the maximum permissible gradient specified within
AS2890.1, a vertical clearance assessment has been undertaken to ensure that vehicles can travel up and down
the ramps without scraping or bottoming out. The results of this assessment conclude that the proposed ramp
profile can accommodate the movement of B99 vehicles with minimal conflict as shown on the drawing provided
at Attachment C.

It is further noted that the proposed ramp design allows for the storage of one vehicle clear of the main grade
at the top of the ramp, although it is noted that queueing is unlikely to occur given the only vehicles opposing
traffic exiting the basement would be service vehicles accessing the rear service road outside of peak operating
hours. Similarly, while sight distance for vehicles exiting the ramp is generally sufficient for parking aisles when
the ambulance bay is not in use, it is suggested that a convex mirror be installed at the exit from the basement
to improve visibility of any opposing vehicles in the isolated instances when the ambulance bay is occupied.

4.4         Bicycle Parking

The location of the bicycle parking is highly visible at the front of the site, and therefore has high levels of casual
surveillance and is easily accessible by visitors. The parking spaces themselves are envisaged to comprise of dual-
sided racks which would allow for a total of eight bicycles to be stored with sufficient clearance on either side in
accordance with the requirements specified within Section 2.1 of AS2890.3.

The proposed bicycle parking also lends itself well to staff use given its location in an area of high casual
surveillance and visibility from the nearby tenancies and in close proximity to site access points from site access
points from the fronting roads as well as from the basement parking area. This is therefore consistent with the
safety features required for staff bicycle parking facilities as specified within Table 1.1 of AS2890.3.

4.5         Servicing

In the absence of any requirements for medical centres, the provisions for health and wellbeing facilities (i.e.
hospitals) specified within Table 14-51 of Council’s superseded Driveways and Parking Code have been used as
a guide to establish the size and type of servicing infrastructure to support the subject development. Given these
requirements only reference the need to provide space for the parking of emergency vehicles, an ambulance
bay has therefore been provided at the front of the site along Easement AB for easy access should emergency
vehicles need to attend the premises.

In lieu of specific design specifications for ambulances in Queensland, the proposed ambulance space has been
sized to accommodate the largest ambulance vehicles currently operating in New South Wales (noting that
ambulance specifications are generally standardised nationally) with adequate clearances. The swept path
drawings provided at Attachment B confirm that the design of the ambulance space and the surrounding
circulation roads is sufficient to accommodate ingress and egress movements.




                                                        Page 6

Page 7

 Proposed Medical Centre                                                                SLR Ref: 620.30769-M01-v1.0 Traffic Impact
 Lot 22, Noosa Business Centre                                                                          Statement 2022 03 16.docx
 Traffic Impact Statement                                                                                     Date: 16 March 2022




5           Parking Considerations

5.1         Car Parking

It is understood that Council is intending to alter the parking requirements for certain uses within the Noosa
Business Centre as part of the structure plan amendments currently being negotiated to align with those applied
in other centres within the Noosa area. With this in mind, Table 4 summarises the required parking provision for
such a land use of the size proposed herein using the parking rates as put forward by Council.

Table 4       Minimum Car Parking Requirements – Amended Structure Plan Rates
 Level                       Proposed Yield             Minimum Parking Rate                   Minimum Parking Provision
 Ground                          1,003m2 GFA     1 space per 20m2 GFA at ground level                    50.2 spaces
                                       2                            2
 1                               1,167m GFA       1 space per 30m on all other levels                    38.9 spaces
 TOTAL                           2,170m2 GFA                                                           89.1 (89) spaces
 GFA = gross floor area


The information presented in Table 4 suggests that a minimum of 89 parking spaces would be required as part
of the subject development. The proposed provision of 99 parking spaces exceeds this requirement by 10 spaces
and is therefore considered to be sufficient to accommodate peak parking demands in the context of the future
planning

However, given that this application is being lodged under Council’s superseded planning scheme, Table 5
presents the standard parking rates specified for “Commercial – Type 2” uses (as medical centres are defined)
within Table 14-51 of the Driveways and Parking Code for context. It is noted that this rate references total use
area (TUA) in place of GFA, however GFA has been used for the purposes of this assessment for conservativeness
and also given that the TUA and GFA of the subject development are expected to be very similar.

Table 5       Minimum Car Parking Requirements – Superseded Planning Scheme Rates
 Land Use                    Proposed Yield             Minimum Parking Rate                   Minimum Parking Provision
 Commercial – Type                             The greater of 1 space per 20m2 TUA, or 3
                                 2,170m2 GFA                                                         108.5 (109) spaces
 2 (Medical)                                        spaces per medical practitioner

Table 5 concludes that a minimum of 109 parking spaces would be required should the standard parking rates
specified within Council’s superseded planning scheme apply, which is 10 spaces more than currently proposed.
The proposed parking capacity is however considered be acceptable owing to the proponent’s intended delivery
of the nearby multi-modal transport hub, which would increase the attractiveness of public transport to both
employees and customers as an alternative to driving to and from the proposed development.

Additionally, the location of the subject site within the broader Noosa Business Centre means that a significant
portion of development-generated trips are likely to be linked with other uses, therefore reducing peak parking
demand and spreading it across the existing parking areas proximate to the subject site.

5.2         Bicycle Parking

Figure 14-1 within S31 of Council’s superseded Business Uses Code specifies the minimum bicycle parking supply
to be provided at health care facilities such as that proposed. Table 6 summarises these requirements for a
development of the size and type proposed herein.




                                                           Page 7

Page 8

 Proposed Medical Centre                                                          SLR Ref: 620.30769-M01-v1.0 Traffic Impact
 Lot 22, Noosa Business Centre                                                                    Statement 2022 03 16.docx
 Traffic Impact Statement                                                                               Date: 16 March 2022




Table 6       Minimum Bicycle Parking Requirements
 Land Use Group                      Proposed Yield        Minimum Parking Rate         Minimum Parking Provision
 Commercial – Type 2                  2,170m2 GFA              1 space per 50m2 GFA             43.4 (43) spaces

The information presented in Table 6 suggests that the subject development would need to provide at least 43
bicycle parking spaces to meet the requirements of Council’s superseded planning scheme, which equates to
approximately one bicycle parking space for every two car parking spaces. This is however considered to be
excessive given the nature of the proposed use would attract a significant volume of ill, elderly and/or mobility
impaired people who would be unlikely to cycle to and from the site.

Whilst not directly comparable this provision would be much higher than that inferred as being required by the
Australian Bureau of Statistics’ (ABS) Journey to Work data, which recorded a 2.8% bicycle mode share for
employees within the Noosaville area given it is expected that the primary generator of bicycle demands within
the site would be staff. On the other hand, the proposed provision of eight bicycle parking spaces would equate
to a supply of one space per 12 car parking spaces and provide sufficient capacity to accommodate a mode share
of up to 8%, which is almost three times higher than that recorded by the ABS.

With this in mind, the provision of eight bicycle spaces at the front of the building are considered to be more
than sufficient in accommodating the functional requirements of the facility.

5.3         PWD Parking

Council’s superseded Driveways and Parking Code defers to the requirements of the AS2890 suite of Australian
Standards regarding the required supply of parking spaces for Persons with a Disability (PWD). AS2890.6, in turn,
references the Building Code of Australia (BCA) for PWD parking supply rates, which for a building of the type
and size proposed herein (being Class 9a as defined within Part A6 therein) requires the provision of one PWD
space for every 50 parking spaces of part thereof.

Given the subject development proposes to provide a total of 99 parking spaces, the provision of two PWD
spaces is therefore considered to be sufficient and in accordance with BCA requirements.

6           Servicing Considerations

As previously mentioned in Section 4.5 herein, Council’s superseded planning scheme is silent on service vehicle
requirements for medical centres such as that proposed. Consequently, the subject development has made
provision for ambulance vehicles only based on the minimum requirements for Type 1 wellbeing uses (i.e.
hospitals) as defined within the superseded Driveways and Carparking Code, with the ambulance bay sized to
accommodate all emergency vehicles up to and including bariatric ambulances. The swept path drawings
provided at Attachment B confirm that ambulances can enter and exit the site with suitable clearances as
needed.

Regarding waste storage and collection, the proponent has advised that medical waste will be managed via the
individual tenancies within the development, which would generally consist of vehicles no larger than a van
arriving at the site to collect and dispose of any medical or biological waste. General waste and recycling will be
stored within two 1,100L bulk bins along Easement AB for easy access by the centre’s existing third-party waste
collection contractor, who will prop in the service road behind the Emporium Showroom Complex and wheel
the bins to the vehicle as currently occurs.




                                                      Page 8

Page 9

 Proposed Medical Centre                                                          SLR Ref: 620.30769-M01-v1.0 Traffic Impact
 Lot 22, Noosa Business Centre                                                                    Statement 2022 03 16.docx
 Traffic Impact Statement                                                                               Date: 16 March 2022




It is also noted that the broader Noosa Civic centre in which the subject site is situated currently has a detailed
Waste Management Plan (WMP) in place to service the surrounding tenancies. It is therefore expected that
waste collection and servicing activities associated with the proposed development would be undertaken in
accordance with these pre-existing procedures, with waste collection vehicles continuing to enter via Easement
AB and circulate to the rear of the existing Emporium Showroom Complex. The subject development is therefore
expected to generate no material impact to service vehicle movements or demands.


7           Traffic Impact Considerations

While Council has agreed to assess the subject development at a code level, a high-level consideration of the
site’s peak traffic generation potential has been undertaken herein. This review has made reference to a number
of widely cited industry guidance documents which summarise the results of traffic generation surveys at similar
sites within New South Wales. These documents include the following:
     ·      Guide to Traffic Generating Developments published by the-then New South Wales Roads and Traffic
            Authority in 2002.
     ·      Trip Generation Surveys: Medical Centres prepared by TEF Consulting on behalf of the-then New South
            Wales Roads and Maritime Services in 2015.

The key finding specified within these documents is that it is difficult to identify a representative traffic
generation rate for medical centres owing to the unique traffic generation characteristics of each surveyed site.
The survey data collected as part of these studies however suggests that the proposed site, while larger than
those surveyed, would be unlikely to generate a material increase in traffic demand relative to those currently
generated by the broader Noosa Civic centre.

Additionally, it is likely that there would be a significant proportion of linked trips between the subject site and
the surrounding retail tenancies which would further reduce net development-generated traffic demands. With
these factors in mind, a code-level assessment of the subject development is therefore considered to be
appropriate.


8           Code Response

The traffic and transport aspects of the proposed development have been assessed against the relevant
requirements of the following codes included within Council’s superseded planning scheme:
     ·      Driveways and Parking Code.
     ·      Transport, Roads and Drainage Code.

Responses to each of these codes are provided at Attachment D and confirm that the subject development is
generally consistent with relevant code requirements.


9           Summary

SLR has been engaged by Stockwell to provide traffic engineering advice and prepare a Traffic Impact Statement
as part of a proposed medical centre to be located on Lot 22 within the Noosa Business Centre in Noosaville.
The findings documented herein can be summarised as follows:
     ·      Internal access, circulation and parking infrastructure is generally designed in accordance with relevant
            standards and meets the functional requirements of the development.



                                                        Page 9

Page 10

Proposed Medical Centre                                                          SLR Ref: 620.30769-M01-v1.0 Traffic Impact
Lot 22, Noosa Business Centre                                                                    Statement 2022 03 16.docx
Traffic Impact Statement                                                                               Date: 16 March 2022




    ·      The proposed parking provision is 10 spaces above that required for the subject development by
           Council’s proposed parking supply rates which are to be imposed as part of structure plan amendments
           for the broader Noosa Business Centre area. The proposed parking supply is therefore considered to
           be sufficient to accommodate peak parking demands.
    ·      When assessing the proposed parking provision against the requirements of the superseded planning
           scheme, the subject development contains 10 parking spaces less than the minimum requirement. This
           is however considered acceptable owing to the proximity of the subject site to the future multi-modal
           transport hub as well as the high proportion of linked trips which would be expected to access the
           proposed development.
    ·      The bicycle parking rate prescribed for the subject development within the superseded planning
           scheme is considered to be excessive given the proposed use of the site. Consequently, an alternative
           solution is proposed whereby sufficient bicycle parking capacity is provided to accommodate a total
           bicycle mode share of approximately 8%, which is roughly three times that recorded for the Noosaville
           area by the Australian Bureau of Statistics.
    ·      In lieu of specific requirements for medical centres, the subject development includes provision for
           ambulance vehicles in accordance with the requirements of Council’s superseded planning scheme for
           hospital facilities, with the proposed ambulance bay sized to accommodate the largest ambulance
           vehicles with adequate clearances. The swept path drawings provided at Attachment B confirm that
           an ambulance could enter and exit this space as needed.
    ·      Refuse collection is proposed to be undertaken along the existing service road at the rear of the
           neighbouring tenancies using bulk bins. This is considered to be acceptable owing to the low volume
           of waste expected to be generated by the proposed development and the resulting frequency of waste
           collection, noting that such activities already occur at this location for the existing tenancies.
    ·      It is difficult to accurately quantify the peak traffic generation potential of the proposed development,
           however it is unlikely to be of a magnitude which would generate a material impact on local traffic
           conditions relative to the traffic demands generated by the broader Noosa Civic shopping centre.
           Consequently, a code-level assessment not including a detailed operational assessment of the
           surrounding road network is considered to be acceptable.
    ·      The code responses provided at Attachment D confirm that the subject development is generally in
           accordance with the relevant requirements of the superseded planning scheme.



Checked/
Authorised by: JB




                                                       Page 10

Page 11

Memorandum




                                                                                        ATTACHMENT A
                                                         Proposed Development Plans




         SLR Consulting Australia Pty Ltd Level 16, 175 Eagle Street Brisbane QLD 4000 Australia (PO Box 26 Spring Hill QLD 4004)
                                                                                T: +61 7 3858 4800 E: [email protected]
                                                                                      www.slrconsulting.com ABN 29 001 584 612

Page 12

                                                                                                                                                                                                                                                                                   Rev.      Date       Description                                 Iss.     Appr.
                                                                                                                                                                                                                                   AREAS                                           A
                                                                                                                                                                                                                                                                                   B
                                                                                                                                                                                                                                                                                             24.01.22
                                                                                                                                                                                                                                                                                             15.02.22
                                                                                                                                                                                                                                                                                                        PRELIMINARY
                                                                                                                                                                                                                                                                                                        WIP DA LAYOUT
                                                                                                                                                                                                                                                                                                                                                    PW
                                                                                                                                                                                                                                                                                                                                                    PW
                                                                                                                                                                                                                                                                                                                                                             PW
                                                                                                                                                                                                                                                                                                                                                             PW
                                                                                                                                                                                                                                                                                   C         23.02.22   WIP LAYOUT                                  PW       PW
                                                                                                                                                                                                                                                                                   D         24.02.22   WIP LAYOUT                                  PW       PW


                                                                                                                                                                                                                                   GFA
                                                                                                                                                                                                                                                                                   E         01.03.22   WIP LAYOUT                                  PW       PW
                                                                                                                                                                                                                                                                                   F         02.03.22   WIP LAYOUT                                  PW       PW




                                    9"
                                                                                                                                                                                                                                                                                   G         09.03.22   WIP DA                                      PW       PW

                                                                                                                                                                                                                                          GROUND           1,003.1m²




                            10.60 m
                            9° 57' 2
                                                                                                                                                                                                                                                                                   H         11.03.22   DEVELOPMENT APPLICATION                     PW       PW
                                                                                                                                                                                                                                                                                   I         14.03.22   DEVELOPMENT APPLICATION                     PW       PW

                                                                                                                                                                                                                                          LEVEL 01         1,167.0m²               J         15.03.22   DEVELOPMENT APPLICATION                     PW       PW



                                                                                                                                                                                                                                                           2,170.1m²


                                                                                                                                                                                                                                   NLA




                            349° 29
                                                                                                                                                                                                                                          GROUND             968.9m²




                               8.39 m
                                                                                                                                                                                                                                          LEVEL 01         1,128.4m²




                                   ' 58"
                                                                                                                           119
                                                                                                                               °2
                                                                                                                           76. 0' 45
                                                                                                                                                                                                                                                           2,097.3m²
                                                            11154




                                                                                                    00
                                                                                                                              42    "




                                                                                                 130
                                                           9494                                                                  m
                                                                                                                                                                                                                                   CARS




                                 355° 52' 33"
                                                                                                                                                                                                                                          GROUND             8 BAYS (inc. 2 PWD)




                                   7.46 m
                                                                                                                                                                                                                                                             1 AMBULANCE
                                                                                                                                                                                                                                          BASEMENT 01       46 BAYS
                                                                                                                                                                                                                                          BASEMENT 02       45 BAYS                Do not scale this drawing. Verify all dimensions on site before commencing
                                                                                                                                                                                                                                                                                   any work. Copyright © 2020 Buchan. This drawing remains the property of
                                                                                                                                                                                                                                                                                   The Buchan Group Australia Pty Ltd. Reproduction in whole or in part without

                                                                                                                                                                                                                                                            99 BAYS (+ AMB)        prior consent is forbidden.




                                 4° 31' 34"
                                  7.47 m
                                                                                                                                                                                                                                                                                   File



                                                                                                                                                                                                                                   BICYCLES
                                                                                                                                                                                                                 119
                                                                                                                                                                                                                     °2
                                                                                                                                                                                                                 13. 0' 45




                                                                                                                                                                                          63. 9' 33"
                                                            UP
                                                                                                                                                                                                                    00    "               GROUND           8 PARKS




                                                                                                                                                                                                 m
                                                                                                                                                                                                                       m




                                 ' 35"




                                                                                                                                                                                               2
                                                                                                                                                                                             44
                                                                                                                                                                                           29°
                            7.46 m
                           13° 10
                               "
                          7' 21
                           m
                      9.17
                     15° 2




                                                  ionent
                                                Bio-R




                                                                                                                                                                                                                         "
                                                                                                                                                                                                                63. 8' 15
                                           10m²




                                                                                                                                                                                                                      m
                                                                                                                                                                                                                    °2
                                                                                                                                                                                                                   44
                                                                                                                                                                                                                209
                                                                                                                                                                               AB
                                                                                                                                                                                                                     EA
                                                                                                                                                                                                                       SE




                                                                                                                                                                            NT
                                                                                                                                                                                                       RE
                                                                                                                                                                                                         FU              ME
                                                                                                                                                                                                           SE
                                                                                                                                                                                                                           NT




                                                                                                                                                                     EA 3500
              2° 04' 31"




                                                                                                                                                                         ME
               8.76 m




                                                                                                                                                                                                                              AC




                                                                                                                                                                       SE
                                                                                                                                                                    0
                                                                                                                                                                 260
                                                                                                                                                                0
                                                                                                                                                             260
                           5421




                                                                                                                                                 G
                                                                                                                                              KIN



                                                                                                                                                           0
                                                                                                                                                        260
                                                                                                                                           AR
                      2931




                                                                                                                                                                                    G
                                                                                                                                                                                    KIN
                                                                                                                                            P
                                                                                                                                         AR



                                                                                                                                                        0
                                                                                                                                                     260




                                                                                                                                                                                  AR
                                                                                                                                     DC
                  345°




                                                                                                                                                                                RP
                     8.76 m




                                                                                                                                                    0
                                                                                                                                       E




                                                                                                                                                                              CA
                                                                                                                                                 260
                       50' 33




                                                                                                                                    OS
                                     19




                                                                                                                                 OP




                                                                                                                                                                            and
                                   53




                                                                                                                                               0
                             "




                                                                                                                                            260
                                                                                                                               PR




                                                                                                                                                                         SS
                                                                                                                                                                       CE
                                                                                                                                             0
                                                                 10m




                                                                                                                                          240




                                                                                                                                                                     AC
                                                                     ²
                                   31 10.3




                                                                         Bio
                                                                            -Re
                                     5° 8




                                                                                                                                      400
                                                                               ntio




                                                                                                                                                                    ING
                                       14 m




                                                                                   n
                                         '1




                                                                                                                                   0 2




                                                                                                                                                                 IST
                                           0"




                                                                                                                                240




                                                                                                                                                               EX
                                                                                       979 793
                                                                                          11




                                                                                                                                  656
                                                                                          3




                                                                         30                                                          2
                                                                            4°                                                                                                                                                                                                     Project
                                                                         10 36' 0
                                                                           .38   9
                                                                               m "
                                                                                                                                                     540
                                                                                                                                                        0                                                                                                                          Lot 22 Medihub
                                                                                                                           AB
                                                                                                                        NT



                                                                                                                                                                                                                                                                                   Noosa Business Centre
                                                                                                                      ME




                                                                                                                                                                                                                                                                                   28 Eenie Creek Road
                                                                                                  299
                                                                                                                  3




                                                                                                                                                                                                                                                                                   Noosaville QLD
                                                                                                                    SE
                                                                                                               794




                                                                                                      °2
                                                                                                  25. 0' 43
                                                                                                           "
                                                                                                                  EA




                                                                                                     50
                                                                                                        m
                                                                                                                                                                                                                                                                                   Project Number
                                                                                                                  299                                                                                                                                                              721072
                                                                                                                      °2
                                                                                                                  13. 0' 43                                                                                                                                                        Status
                                                                                                                     02    "                                                    ILS
                                                                                                                        m                                                                                                                                                          Date Plotted
                                                                                                                                                                                   /15                                                                                                             15-Mar-22 10:16:53 AM

                                                                                                                                                                  25                  0                                                                                            Date Issued

                                                                                                                                                                2             IL4                                                                                                                  15.03.22

                                                                                                                                                              S/        7        .59                                                                                               Scale

                                                                                                                                                             L         1            8
                                                                                                                                                            I        .5
                                                                                                                                                                                                                                                                                   0          2         4                  8                  12M

                                                                                                                                                                   4
                                                                                                                                                                 IL                                                                                                                Drawing Title

                                                                                                                                                                                                                                                                                   SITE PLAN




                                                                                                                                                                                                                                                                                   Drawing Number                                                          Revision

                                                                                                                                                                                                                                                                                   A-DA-0002                                                                   J




                                                                                                                                                 DEVELOPMENT APPLICATION
                                                                                                                                                                                                                                                       85
1   SITE                                                                                                                                                                                                                                                 .85
                                                                                                                                                                                                                                                     0.6    7
    1 : 200                                                                                                                                                                                                                                             7%                         Brisbane Studio
                                                                                                                                                                                                                                                                                   + 61 7 3859 9222 / buchangroup.com.au

Page 13

                                                                                                                                                                                                                                                                                                  Rev.      Date       Description                                 Iss.     Appr.
                                                                                                                                                                                                                                                                                                  A         24.01.22   PRELIMINARY                                 PW       PW
                                                                                                                                                                                                                                                                                                  B         15.02.22   WIP DA LAYOUT                               PW       PW
                                                                                                                                                                                                                                                                                                  C         23.02.22   WIP LAYOUT                                  PW       PW
                                                                                                                                                                                                                                                                                                  D         24.02.22   WIP LAYOUT                                  PW       PW
                                                                                                                                                                                                                                                                                                  E         01.03.22   WIP LAYOUT                                  PW       PW
                                                                                                                                                                                                                                                                                                  F         02.03.22   WIP LAYOUT                                  PW       PW

                                                                                         1        2                                                   3                                                                                                                                           G
                                                                                                                                                                                                                                                                                                  H
                                                                                                                                                                                                                                                                                                            08.03.22
                                                                                                                                                                                                                                                                                                            08.03.22
                                                                                                                                                                                                                                                                                                                       WIP ELEVATIONS
                                                                                                                                                                                                                                                                                                                       WIP ELEVATION
                                                                                                                                                                                                                                                                                                                                                                   PW
                                                                                                                                                                                                                                                                                                                                                                   PW
                                                                                                                                                                                                                                                                                                                                                                            PW
                                                                                                                                                                                                                                                                                                                                                                            PW
                                                                                        3000     2000                                                2000                                                                                                                                         I         09.03.22   WIP DA                                      PW       PW
                                                                                                                             PLANT/RAIN WATER TANK                                                                                                                                                J         11.03.22   DEVELOPMENT APPLICATION                     PW       PW
                                                                                                                       (RAISED ABOVE OVERLAND FLOW PATH)                                                                                                                                          K
                                                                                                                                                                                                                                                                                                  L
                                                                                                                                                                                                                                                                                                            14.03.22
                                                                                                                                                                                                                                                                                                            15.03.22
                                                                                                                                                                                                                                                                                                                       DEVELOPMENT APPLICATION
                                                                                                                                                                                                                                                                                                                       DEVELOPMENT APPLICATION
                                                                                                                                                                                                                                                                                                                                                                   PW
                                                                                                                                                                                                                                                                                                                                                                   PW
                                                                                                                                                                                                                                                                                                                                                                            PW
                                                                                                                                                                                                                                                                                                                                                                            PW




                                                                        FROM BASEMENT


                                                                          UP

                                                                                                                                                                                  TO BASEMENT 01
          1




                                                                                                                                                                                                                     7100
                                                                                                                                                                 RAMP   RAMP
                                                                                                                                                                 1:5    1:10                                                                                                             REFUSE
         2000




                      9244
                                                                                                                                                                           7300
                                                                                                                                                            UP

                                                                                                                                                                                                                                                                                                  Do not scale this drawing. Verify all dimensions on site before commencing




                                 TO L




                                                                                                                                                                                                                            EASEMENT AB
                                                                                                                                                                                                                                                                                                  any work. Copyright © 2020 Buchan. This drawing remains the property of
                                                                                                                                                                                                                                                                                                  The Buchan Group Australia Pty Ltd. Reproduction in whole or in part without
                                                                                                                                                  FROM LEVEL 1                                                                                                                                    prior consent is forbidden.




                                                                                                                                                                                                                     3500
                                      EVEL
                                                                                                                                                                        AMBULANCE
                                                                                                                                                                                                                                                                                                  File



                                      1




                                                                                                                                                                                                                     2600
                                             UP




                                                                                                                                                                                                                     2600
                                        7970




                                                                                                                                                                                                                     2600
                                                                                        GROUND FLOOR GFA:                                                                      5400                                            6539                                               5400
                                                                                        1,003m²




                                                                                                                                                                                                                     2600
                                                                                        SSL 10.3m




                                                                                                                                                                                                                                                 EXISTING ACCESS and CARPARKING
                             2                                                                                                                                                                                                             1
                                                  10m²




                                                                                                                                                                                                                     2600
                             3000                                                                                                                                                                                                         3001
                                                   BIO-B
                                                        A S IN




                                                                                                                                                                                              8 BAYS + 1 AMBULANCE
                                                                                                                                                                                                                     2600
                                                                                        NOTE: INTERTENANCY WALLS INDICATIVE ONLY




                                                                                                                                                                                                                     2400
                                                                                                                                                                         PWD




                                                                                                                                                                                                                     2400
                                                                                                                                                                         SHARED
                                                                                                                                                                         ZONE




                                                                                                                                                                                                                     2400
                                                                                                                                                                                                                                                                                                  Project


                                                                                                                                                                                                                                                                                                  Lot 22 Medihub
                                                                                                                                                                          8 BICYCLES
                                                                                                                                                                                                                                                                                                  Noosa Business Centre
                                                                                                                                                                                                                                                                                                  28 Eenie Creek Road
                                                                                                                                                                                                                                                                                                  Noosaville QLD
                                                                                                                                                                                   LIFT
                                                                   21                                                                                                                                                                                                                             Project Number

                                                                 54                                                                                                                                                                                                                               721072
                                                                                                                                                                         TO LEVEL 01                                                                                                              Status

                                                                                                                                                                                                                                                                                                  Date Plotted
                                                                                                                                                                                                                                                                                                                  15-Mar-22 9:37:29 AM
                                                                                                                                                                                                                                                                                                  Date Issued
                                                                                                                                                                                                                                                                                                                  15.03.22
                                                                                                                                                                        FROM BASEMENT
                                                                                                                                                                                                                                                                                                  Scale
                                                                               7663




                                                                                                                                                                                                                                                                                                  0          1         2                  4                   6M




                                                                                                                                                                                                                            EASEMENT AB
                                                                                                                                                                                                                                                                                                  Drawing Title

                                                                                                      10m² BIO-BASIN                                                                                                                                                                              GROUND FLOOR
                                                                                                                                     11793




                                                                                                                                                                                                   7943
                                                                                                                                                                                                                                                                                                  Drawing Number                                                          Revision

                                                                                                                 2                                                                                                                                                                                A-DA-1000                                                                   L
                                                                                                                3001



1      GROUND FLOOR
2000   1 : 100

                                                                                                                           DEVELOPMENT APPLICATION                                                                                                                                                Brisbane Studio
                                                                                                                                                                                                                                                                                                  + 61 7 3859 9222 / buchangroup.com.au

Page 14

                                                                                                                                                              Rev.      Date       Description                                 Iss.     Appr.
                                                                                                                                                              A         24.01.22   PRELIMINARY                                 PW       PW
                                                                                                                                                              B         15.02.22   WIP DA LAYOUT                               PW       PW
                                                                                                                                                              C         23.02.22   WIP LAYOUT                                  PW       PW
                                                                                                                                                              D         24.02.22   WIP LAYOUT                                  PW       PW
                                                                                                                                                              E         01.03.22   WIP LAYOUT                                  PW       PW

                                                                2                                                       3                                     F
                                                                                                                                                              G
                                                                                                                                                                        02.03.22
                                                                                                                                                                        08.03.22
                                                                                                                                                                                   WIP LAYOUT
                                                                                                                                                                                   WIP ELEVATION
                                                                                                                                                                                                                               PW
                                                                                                                                                                                                                               PW
                                                                                                                                                                                                                                        PW
                                                                                                                                                                                                                                        PW
                                                               2000                                                   2000                                    H         09.03.22   WIP DA                                      PW       PW
                                                                                                                                                              I         11.03.22   DEVELOPMENT APPLICATION                     PW       PW
                                                                                                                                                              J         15.03.22   DEVELOPMENT APPLICATION                     PW       PW




                           UP
                                                                        RAMP     RAMP                  RAMP   RAMP
                                                                        1:10     1:5                   1:5    1:10
                     1




                                                                                        7100
                                                          RAMP UP TO                                                  RAMP DOWN TO
                    2000                                    GROUND                                                    BASMENT 02




                                       2600




                                                                                                                                         2600
                                       2600
                                                                                                                                                              Do not scale this drawing. Verify all dimensions on site before commencing
                                                                                                                                                              any work. Copyright © 2020 Buchan. This drawing remains the property of
                                                                                                                                                              The Buchan Group Australia Pty Ltd. Reproduction in whole or in part without
                                                                                                                                                              prior consent is forbidden.


                                                                                                                                                              File




                                       2600




                                                                                                                                         2600
                                       2600




                                                                                                                                         2600
                                5400           6200                            5400                   5400                     6200             5400




                                              RAMP 1:40




                                                                                                                             RAMP 1:40
                                       2600




                                                                                                                                         2600
                                                            46 CARS




                                                                                               6350
                                                                                                                                                              Project
                                       2600




                                                                                                                                         2600
                                                                                                                                                              Lot 22 Medihub
                                                2600             2600          2600            2600   2600           2600     2600
                                                                                                                                                              Noosa Business Centre
                                                                                                                                                              28 Eenie Creek Road
                                                                                                                                                              Noosaville QLD
                                                                                                                                                       LIFT
                                                                                                                                                              Project Number

                                                                                               5400                                                           721072
                                                                                                                                                              Status

                                                                                                                                                              Date Plotted
                                                                                                                                                                              15-Mar-22 9:34:48 AM
                                                                                                                                                              Date Issued
                                                                                                                                                                              15.03.22
                                                                                                                                                              Scale
                                                                                                                                                              0          1         2                  4                   6M


                                                                                                                                                              Drawing Title

                                                                                                                                                              BASEMENT 01




                                                                                                                                                              Drawing Number                                                          Revision

                                                                                                                                                              A-DA-100-B1                                                                 J


1      BASEMENT 1

                                                                               DEVELOPMENT APPLICATION
2000   1 : 100

                                                                                                                                                              Brisbane Studio
                                                                                                                                                              + 61 7 3859 9222 / buchangroup.com.au

Page 15

                                                                                                                                                                Rev.      Date       Description                                 Iss.     Appr.
                                                                                                                                                                A         24.01.22   PRELIMINARY                                 PW       PW
                                                                                                                                                                B         15.02.22   WIP DA LAYOUT                               PW       PW
                                                                                                                                                                C         23.02.22   WIP LAYOUT                                  PW       PW
                                                                                                                                                                D         24.02.22   WIP LAYOUT                                  PW       PW

                                                             2                                                    3                                             E
                                                                                                                                                                F
                                                                                                                                                                          01.03.22
                                                                                                                                                                          02.03.22
                                                                                                                                                                                     WIP LAYOUT
                                                                                                                                                                                     WIP LAYOUT
                                                                                                                                                                                                                                 PW
                                                                                                                                                                                                                                 PW
                                                                                                                                                                                                                                          PW
                                                                                                                                                                                                                                          PW
                                                            2000                                                2000                                            G         09.03.22   WIP DA                                      PW       PW
                                                                                                                                                                H         11.03.22   DEVELOPMENT APPLICATION                     PW       PW
                                                                                                                                                                I         15.03.22   DEVELOPMENT APPLICATION                     PW       PW




                                                                                                                                                TURN
                                                                                                                                                AROUND BAY
                        UP
                                                                     RAMP      RAMP
                                                                     1:10      1:5
                    1




                                                                                      7100
                                                       RAMP UP TO                                   STORAGE/
                 2000                                  BASEMENT 1                                   PLANT




                                    2600




                                                                                                                                         2600
                                    2600
                                                                                                                                                                Do not scale this drawing. Verify all dimensions on site before commencing
                                                                                                                                                                any work. Copyright © 2020 Buchan. This drawing remains the property of
                                                                                                                                                                The Buchan Group Australia Pty Ltd. Reproduction in whole or in part without
                                                                                                                                                                prior consent is forbidden.


                                                                                                                                                                File




                                    2600




                                                                                                                                         2600
                                    2600




                                                                                                                                         2600
                             5400           6200                            5400                    5400                       6200               5400




                                           RAMP 1:40




                                                                                                                             RAMP 1:40
                                                                                                                      2600
                                                                                                                      2600
                                                                                                                      2600
                                    2600




                                                                                                                                         2600
                                                                                                      6350
                                                                            45 CARS                                                                             Project
                                    2600




                                                                                                                                         2600
                                                                                                                                                                Lot 22 Medihub
                                             2600             2600          2600             2600   2600       2600           2600

                                                                                                                                                                Noosa Business Centre
                                                                                                                                                                28 Eenie Creek Road
                                                                                                                                                         LIFT   Noosaville QLD




                                                                                                      5400
                                                                                                                                                                Project Number

                                                                                                                                                                721072
                                                                                                                                                                Status

                                                                                                                                                                Date Plotted
                                                                                                                                                                                15-Mar-22 9:35:58 AM
                                                                                                                                                                Date Issued
                                                                                                                                                                                15.03.22
                                                                                                                                                                Scale
                                                                                                                                                                0          1         2                  4                   6M


                                                                                                                                                                Drawing Title

                                                                                                                                                                BASEMENT 02




                                                                                                                                                                Drawing Number                                                          Revision

                                                                                                                                                                A-DA-100-B2                                                                    I
1      BASEMENT 2
2000   1 : 100




                                                                              DEVELOPMENT APPLICATION                                                           Brisbane Studio
                                                                                                                                                                + 61 7 3859 9222 / buchangroup.com.au

Page 16

Memorandum




                                                                                         ATTACHMENT B
                                               Swept Path Assessment Drawings




         SLR Consulting Australia Pty Ltd Level 16, 175 Eagle Street Brisbane QLD 4000 Australia (PO Box 26 Spring Hill QLD 4004)
                                                                                T: +61 7 3858 4800 E: [email protected]
                                                                                      www.slrconsulting.com ABN 29 001 584 612

Page 17

                                LY
                          ON
                   PT
            N   CE
         CO




                         1        2                                                   3
                        3000     2000                                                2000
                                                             PLANT/RAIN WATER TANK
                                                       (RAISED ABOVE OVERLAND FLOW PATH)


FROM BASEMENT


  UP

                                                                                                                        TO BASEMENT 01

                                                                                                                                                              7100
                                                                                                       RAMP   RAMP
                                                                                                       1:5    1:10                                                                                                                              REFUSE




                                                                                                                 7300
                                                                                             UP
                                                                                                                                                                     EASEMENT AB




                                                                                   FROM LEVEL 1
                                                                                                                                                              3500




                                                                                                               AMBULANCE
                                                                                                                                                              2600
                                                                                                                                                              2600
                                                                                                                                                              2600




                        GROUND FLOOR GFA:                                                                            5400                                             6539                                                           5400
                                                                                                                                                              2600




                        1,003m²
                        SSL 10.3m
                                                                                                                                                                                              EXISTING ACCESS and CARPARKING




                                                                                                                                                                                    1
                                                                                                                                                              2600




                                                                                                                                                                                   3001
                                                                                                                                     8 BAYS + 1 AMBULANCE
                                                                                                                                                              2600




                        NOTE: INTERTENANCY WALLS INDICATIVE ONLY
                                                                                                                                                              2400




                                                                                                               PWD
                                                                                                                                                              2400




                                                                                                               SHARED
                                                                                                               ZONE
                                                                                                                                                              2400




                                                                                                                8 BICYCLES




                                                                                                                        LIFT

                                                                                                               TO LEVEL 01


                                                                                                              FROM BASEMENT
       7663




                                                                                                                                                                     EASEMENT AB




                                      10m² BIO-BASIN
                                                                     11793




                                                                                                                                         7943




                                                 2
                                                3001




                                      15 ASTOR TERRACE             Project No:              620.30769                        SWEPT PATH LEGEND
                                                                                                                                                                                                                                                                     Stockwell Development Group Pty Ltd
                                        SPRING HILL 4000                                                                                                    Vehicle Path
                                                AUSTRALIA          Date:                   15/03/2022                                                       Vehicle Body
                                          T: 61 7 3858 4800                                                                                                                                                                                                          Noosaville Hoffman Drive Medical Centre
                                      www.slrconsulting.com        Drawn by:               MC                                                               Body Clearance                                                              N
                                                                   Scale:                   AS SHOWN                                                                                                                                                                    Ambulance Swept Path
The content contained within this document may                                                                                                                                          0.0                                    2.5          5        7.5        10
be based on third party data.                                      Sheet Size:              A3                                                                                                                                                             METRES
SLR Consulting Australia Pty Ltd does not                          Projection:             (GDA94) MGA Zone                                                                                                                          SCALE 1:250
guarantee the accuracy of any such information.                                                                                                                                                                                                                                   FIGURE 1

Page 18

Memorandum




                                                                                         ATTACHMENT C
                                                                     Vertical Clearance Check




         SLR Consulting Australia Pty Ltd Level 16, 175 Eagle Street Brisbane QLD 4000 Australia (PO Box 26 Spring Hill QLD 4004)
                                                                                T: +61 7 3858 4800 E: [email protected]
                                                                                      www.slrconsulting.com ABN 29 001 584 612

Page 19

   1                                  2                                                            3          4                                             5                        6




                            LY
                         ON
             T
           EP
        NC
                                                                                             2                     3
     CO

                                                                                            2000                  2000




                                                                                                                  2975
                                                                                                       2775
                                                                         2975
                                                             2775




                                                                                                                               2390
                                                                                                                                        2190
                                L16 175 EAGLE STREET
                                                           Project No:          620.30769                                                                              Stockwell Development Group Pty Ltd
                                  BRISBANE CITY 4000
                                             AUSTRALIA
                                                           Date:                15/03/2022
                                       T: 61 7 3858 4800                                                                                                              Noosaville Hoffman Drive Medical Centre
                                  www.slrconsulting.com
                                                           Drawn by:            MC
                                                           Scale:               AS SHOWN                                                                                 Vertical Clearance Check
                                                                                                                         0.0     1.0       2.0       3.0        4.0
The content contained within this document may be based
on third party data.                                       Sheet Size:          A3                                                                         METERS                    B99
SLR Consulting Australia Pty Ltd does not guarantee the                                                                                SCALE 1:100
                                                           Projection:          -                                                                                                 FIGURE 2
accuracy of any such information.

Page 20

Memorandum




                                                                                        ATTACHMENT D
                Superseded Planning Scheme Code Responses




         SLR Consulting Australia Pty Ltd Level 16, 175 Eagle Street Brisbane QLD 4000 Australia (PO Box 26 Spring Hill QLD 4004)
                                                                                T: +61 7 3858 4800 E: [email protected]
                                                                                      www.slrconsulting.com ABN 29 001 584 612

Page 21

Division 13 – Driveways and Car Parking Code
Table 14-49 - Driveways
 Specific Outcomes                                           Probable Solutions                                    Compliance    Response
                                                                                                                     ü/û/NA
 General
 O1                                                         S1.1                                                           ü     Complies with S1.1
 Vehicular access does not adversely                        Vehicular access is located and                                      The subject development does not propose a new
 impact on safety, capacity and operations                  designed in accordance with                                          access to the public road network but rather
 of the existing or planned road network, the               AS/NZS2890.1:2004;                                                   proposes to feed into a current driveway.
 proposed driveway, cycleways or                            AND                                                                  Notwithstanding this, the location of the basement
 pedestrian pathway systems.                                S1.2                                                           ü     access ramp is consistent with the requirements of
                                                            Only one footpath crossing is provided1;                             AS2890.1.
                                                            AND                                                                  Complies with S1.2
                                                            S1.3                                                           ü     The subject development does not introduce any
                                                            Driveways, have a maximum grade in                                   new vehicle-pedestrian conflicts.
                                                                                                                                 Complies with S1.3
                                                            accordance with Council’s standard
                                                                                                                                 While the existing fronting driveways remain
                                                            requirements.
                                                                                                                                 unchanged, the design of the basement access ramp
                                                                                                                                 aligns with the requirements of AS2890.1.
 O2                                                         S2.1                                                           N/A   S2.1 not applicable
 Driveways and crossovers—                                  Design of the driveway across the                                    The subject development does not propose any new
 a) are suitable and safe for their intended                footpath is in accordance with Council’s                             vehicular crossings of footpaths.
     use; and                                               Standard Drawing requirements as                                     Complies with S2.2
 b) match Council infrastructure.                           appropriate for the particular type of                               While the subject development does not propose any
                                                            development as annotated on the                                      new public driveways, the basement access ramp
                                                            drawings;                                                            has been designed in accordance with the relevant
                                                            AND                                                                  requirements of AS2890.1 and the swept path of key
                                                            S2.2                                                           ü     vehicle movements. It is however noted that the
                                                            Driveways are designed and                                           width of the basement access is consistent with that
                                                            constructed in accordance with Council                               specified for Type B driveways on Council’s standard
                                                            Standard Drawing requirements , as                                   drawing RS-051.
                                                            appropriate for the particular type of
                                                            development as annotated on the
                                                            drawings;

 1
     Justification for additional driveways may need to be supported by a detailed Traffic Study. See PSP 1 for details.

Page 22

                                              AND
                                              S2.3                                           ü   Complies with S2.3
                                              The change in grades in the driveways              The design of the basement access ramp aligns with
                                              and ramps is in accordance with                    the vertical geometry requirements specified within
                                              Council’s Standard Drawing                         AS2890.1.
                                              requirements.
O3                                            S3.1                                           ü   Complies with S3.1
In commercial zoned areas, the number of      Design of multi-tenanted developments              The development proposes consolidated and shared
driveways across pedestrian footpaths is      in commercial zoned areas include                  site access and parking areas.
minimised.                                    shared driveways and parking areas;
                                              AND
                                              S3.2                                           ü   Complies with S3.2
                                              Driveways are located so they abut                 The subject development proposes to make shared
                                              existing driveways of adjoining                    use of existing driveways through the application of
                                              development where practicable and                  easements. The width of sealed driveways would
                                              reciprocal easements are created to                therefore remain unchanged with the subject
                                              reduce the sealed driveway width.                  development in place.
O4                                            S4.1                                           ü   Complies with S4.1
Vehicular access does not adversely           Footpath and kerb crossings are located            Existing public footpath and kerb infrastructure is to
impact on the capacity, operations and        clear of existing stormwater inlet                 generally remain unchanged with the subject
maintenance of the existing infrastructure;   structures, water and sewerage                     development in place, and therefore no new services
AND                                           infrastructure fittings, any other exiting         conflicts are created.
                                              utility infrastructure, existing landscaping
                                              and vegetation.


O5                                            S5.1                                           ü   Complies with S5.1
Vehicular access does not adversely           Vehicular access avoids disturbance to             Vegetation considerations are beyond the scope of
impact on the health and integrity of         the tree protection zone of trees on               this traffic assessment; however no new public
existing landscaping or native vegetation,    public land.                                       vehicular accesses are proposed and therefore the
where possible.                                                                                  subject development would be expected to have an
                                                                                                 immaterial impact on trees located on public land.

Page 23

 O6                                              S6.1                                             N/A     S6.1 not applicable
 Driveway run-off is filtered prior to leaving   For—                                                     Stormwater quality considerations are beyond the
 the premises.                                   a)   Ancillary dwelling unit, Multiple                   scope of this traffic assessment.
                                                      housing Type 2 if less than 5
                                                      carparking spaces, Visitor
                                                      accommodation Type 1 and
                                                      Homebased business Type 3—
                                                      the driveway is formed to drain to
                                                      landscaped areas; and
                                                 b)   for other uses—grease and oil
                                                      arrestors or stormwater quality
                                                      improvement devices are
                                                      incorporated into the design to
                                                      treat run-off prior to run-off exiting
                                                      from the premises.


 Table 14-50 – Car Parking and manoeuvring
Specific Outcomes                                 Probable solutions                           Compliance Response
                                                                                                 ü/û/NA
 Carpark design and layout
O7                                               S7.1                                              ü      Complies with O7
 Sufficient carparking is provided to            The number of parking and loading                        The proposed parking provision is in excess of the
 accommodate the number and type of              bays is not less than the minimum                        parking rates suggested by Council for
 vehicles likely to be generated by the          number specified in Table 14-51                          implementation as part of forthcoming structure plan
 development having regard to the                Vehicle Parking                                          amendments (and already applied at other centres
 specifics of the use including—                 Requirements;                                            throughout the Noosa LGA) currently being
                                                                                                          negotiated with the proponent and is therefore
 a) the type and intensity of land use;
                                                                                                          considered to be sufficient to meet peak parking
 b) any existing parking available on the
                                                                                                          demands.
 site;                                                                                                    Notwithstanding the above, it is also noted that the
 c) hours of operation;                                                                                   subject site is located proximate to a proposed multi-
 d) likely numbers of users;                                                                              modal hub, which would encourage the use of public
 e) the peak parking demand periods of                                                                    transport to access the site as an alternative to
 uses on the site; and                                                                                    private vehicles. The location of the subject site is
 f) the availability of alternative                                                                       also likely to result in a significant proportion of
 carparking.                                                                                              linked trips with surrounding tenancies, therefore

Page 24

                                                                                                reducing peak parking demands and spreading them
                                                                                                across the parking supply already provided within
                                                                                                the Noosa Business Centre.
O8                                              S8.1                                        ü   Complies with S8.1
The layout of the development provides          Parking bays, manoeuvring areas,                Section 4.3 of the attached traffic assessment
adequate, clearly defined and easily            queuing areas, loading, setdown and             prepared by SLR Consulting confirms that the
accessible— a)          on-site vehicle         pickup areas and driveways are                  design of internal car parking and manoeuvring
parking and manoeuvring areas; and              designed to the standards set out in            infrastructure generally aligns with the relevant
b)    loading and manoeuvring areas for         the Australian Standards for Off-street         requirements of the AS2890 suite of Australian
      delivery and service vehicles.            Carparking and Off-street Commercial            Standards.
                                                Vehicles Parking.                               Complies with S8.2
                                                AND                                             It is noted that Table 14-51 does not specify loading
                                                S8.2                                        ü   requirements for medical centres, and therefore the
                                                The number of loading bays is not less          specification for hospitals has been adopted herein
                                                than the minimum number specified in            instead. Consequently, an ambulance bay has been
                                                Table 14-51.                                    provided to accommodate emergency vehicles up
                                                                                                to and including bariatric ambulances.
O9                                              S9.1                                        ü   Complies with S9.1
Parking areas are located where they will       Carparking areas are accessed from              All parking to be provided as part of the subject
not                                             rear laneways where practicable.                development will be accessed off the public road
unduly conflict with pedestrians and will not                                                   network via Easement AB.
dominate the streetscape.
O10                                             S10.1                                       ü   Complies with S10.1
Provision is made for a reasonable number       Carparking spaces are provided for              AS2890.6 defers to the Building Code of Australia
of on site carparking spaces identified and     people with disabilities at the rate            with regard to the provision of parking for Persons
reserved for people with disabilities.          specified in the Australian Standards for       with a Disability (PWD). Section 5.3 of the attached
                                                Off-street Carparking.                          traffic assessment confirms that the proposed PWD
                                                                                                parking provision aligns with the requirements
                                                                                                specified therein.
O11                                             S11.1                                       ü   Complies with S11.1
Access and egress points do not impact on       Vehicle manoeuvring areas are                   Section 4.3 of the attached traffic assessment
the safety and operations of the road           provided in accordance with Australian          confirms that proposed internal manoeuvring areas
system.                                         Standards for Off-street Carparking so          are designed in accordance with or in excess of
                                                vehicles enter and leave the site in a          relevant design standards, therefore allowing
                                                forward gear.                                   vehicles to enter and leave the site in a forward
                                                                                                gear.

Page 25

O12                                            S12.1 At locations where pedestrian         ü     Complies with S12.1
Parking areas are designed to -                and vehicle conflicts are likely to occur         The proposed development has been designed to
 a)   provide a progressive reduction in       –                                                 avoid introducing new pedestrian-vehicle conflicts by
      speed between the external road and       a)    sight distances of at least 2.5            providing direct and dedicated pedestrian
      internal parking spaces;                        seconds of travel time at the              connections to the fronting road network and car
 b)   ensure lower speeds near areas of               designated speed are provided;             parking areas.
      high pedestrian activity through the      b)    splayed corners on structures
      use of appropriate road geometry or             are incorporated;
      devices designed to limit speed; and      c)    landscaping is designed to allow
 c)   maintain sight distances which are              clear views; and
      appropriate for the likely operating      d)    sign  placement ensures that
      speeds in all areas of potential                sight distance requirements are
      pedestrian/vehicle and vehicle/vehicle          not impeded.
      conflict.
O13                                            S13.1                                       N/A   S13.1 not applicable
A clearly defined pedestrian network is        In large open car parks with greater              The subject development does not include large
provided that –                                than 200 car parking spaces, a                    open car parking areas with greater than 200
 a)   is located in areas where people will    pedestrian path between parking                   parking spaces.
      choose to walk;                          spaces is provided on every second
 b)   ensures that pedestrian movement         aisle.
      through car parking areas or
      structures are along aisles rather than
      across them.
O14                                           S14.1                                        ü     Complies with O14
Provision is made for pedestrian and          No probable solution identified                    It is noted that the location of the proposed
vehicular queues at conflict points.                                                             basement access ramp minimises conflict as all
                                                                                                 vehicles would be expected to be turning into and
                                                                                                 out of the basement, with the only potential conflict
                                                                                                 being with service vehicles entering the service lane
                                                                                                 behind the Emporium Showroom tenancies. This is
                                                                                                 however expected to be infrequent and
                                                                                                 concentrated outside of peak trading periods of the
                                                                                                 subject development.
                                                                                                 Notwithstanding this, provision has been made for
                                                                                                 the storage of one vehicle at the top of the ramp
                                                                                                 clear of the primary ramp gradient. This is

Page 26

                                                                                                                  considered to be sufficient given the expected low
                                                                                                                  occurrence of possible conflicts.
O15 Parking areas are lit to provide security               S15.1                                           N/A   S15.1 not applicable
for night-time users.                                       Lighting is provided in accordance with               Lighting considerations are beyond the scope of this
                                                            the Australian Standard for Road                      traffic assessment.
                                                            Lighting - Vehicular Traffic (Category
                                                            V) Lighting - Performance Installation
                                                            and Design Requirements.
O16                                                         S16.1                                           N/A   S16.1 & S16.2 not applicable
In mixed use areas of Business centres                      Resident carparking is limited to one                 The subject development does not propose any
residents do not compete with customers for                 space per dwelling unit or                            residential land uses.
carparking spaces.                                          accommodation unit;
                                                            AND
                                                            S16.2                                           N/A
                                                            Resident carparking is not located in
                                                            the road reserve or between the
                                                            residential or business building and the
                                                            principal street frontage.
O17 Car parking areas are landscaped                        No solution provided                            N/A   O17 not applicable
to— a) provide shade;                                                                                             Landscaping considerations are beyond the scope
 b)     maximise infiltration of stormwater                                                                       of this traffic assessment.
        run-off;
 c)     define parking areas;
 d)     reduce direct visibility of car parking
        areas from external viewpoints; and
 e)     soften views of hardstand areas.
O18                                                         No solution provided                            N/A   O18 not applicable
Development with the potential to generate                                                                        The subject development is not considered to be of
significant traffic and parking impacts gives                                                                     a use and size which would generate significant
appropriate consideration to transport and                                                                        traffic and parking impacts relative to those
land use issues2.                                                                                                 generated by the broader Noosa Business Centre in
                                                                                                                  which it is located.




2
    PSP 1 details information Council may request, including a detailed Traffic Impact Assessment Report.

Page 27

Motor Cycles & Motor Scooters                   S19.1                                       û     Does not comply with S19.1
O19                                             For Commercial businesses,                        The subject development provides sufficient parking
Designated Motor cycle or motor scooter         Entertainment & dining business,                  to accommodate peak demands regardless of
parking spaces reduce the reliance on cars.     Industrial business Types 1 and 2,                vehicle type. Consequently, any staff or customers
                                                Retail business Types 2, 4, 5, 6 and              travelling to/from the site on a motorcycle or scooter
                                                7, Education Types 1 and 2, Open                  could make use of any of the available car parking
                                                Space, Wellbeing Uses and                         spaces in lieu of providing dedicated motorcycle
                                                Transport Types 1, 2, 3 and 4 motor               parking.
                                                cycle parking spaces accord with
                                                Planning Scheme Policy PSP26 Motor
                                                Cycle & Motor Scooter Parking.

O20                                             S20.1                                       N/A   S20.1 not applicable
Carparks are designed to ensure run-off is      Grease and oil arrestors or stormwater            Stormwater quality considerations are beyond the
treated to remove pollutants prior to leaving   quality improvement devices are                   scope of this traffic assessment.
the premises.                                   incorporated into the design to treat
                                                run-off prior to it leaving the premises.

O21 Carparking areas are designed to            No solution provided                        N/A   O21 not applicable
ensure drainage without the use of pumps                                                          Drainage considerations are beyond the scope of
or other electrical apparatus.                                                                    this traffic assessment.



O22 Site layout and building design             S22.1                                       N/A   S22.1 not applicable
provides for soft landscaping to be             Below ground components of                        Basement footprint and landscaping considerations
established.                                    buildings, including car parks, do not            are beyond the scope of this traffic assessment.
                                                extend beyond the above ground
                                                footprint to allow for the provision of
                                                landscaping, particularly within building
                                                setbacks.
Education Types 1, 2 or 3                       S23.1                                       ü     Complies with S23.1
O23 Carparking and setdown areas are            Paved setdown areas are provided                  While a dedicated setdown area is not provided as
designed and located to facilitate their safe   within the site;                                  part of the proposed development (and nor is one
and efficient use.                              AND                                               considered necessary or required by the provisions
                                                S23.2 For a minimum of 50% of               ü     of the planning scheme), all parking and vehicle
                                                carparking spaces, pedestrian access              manoeuvring areas are to be paved.

Page 28

to buildings is not across or through       Complies with O23
driveways, carparks,                        The provision of dedicated pedestrian pathways
setdown or manoeuvring areas;               within the basement carpark is not considered
AND                                         necessary and would result in significant additional
S23.3                                   ü   construction costs associated with the expansion of
Carparking and setdown areas are            the basement. It is instead noted that pedestrian
visible from off-site, or signed.           movements are acceptable within the basement
                                            carpark owing to low vehicle speeds and traffic
                                            volumes and the fact that drivers typically expect
                                            pedestrians to be circulating within a carpark
                                            environment.
                                            Complies with S23.3
                                            Signage is to be provided directing customers to the
                                            basement parking area. The ambulance bay is also
                                            to be signed accordingly to ensure it is reserved for
                                            the exclusive use of ambulances at all times.

Page 29

Division 18 – Transport, Roads and Drainage Code
Table 14-58 – Strategic transport network
Specific Outcomes                            Probable Solutions                             Compliance   Response
                                                                                              ü/û/NA
Strategic Transport Network
O1                                           S1.1                                               ü        Complies with O1
Traffic generation from the development is   Where the development leads to the                          The attached traffic assessment prepared by SLR
considered in a localised and a Shire wide   need to increase transport                                  Consulting suggests that the peak traffic generation
context to ensure that –                     infrastructure in the Shire, the                            potential of the subject development is expected to
 a) the transport network has the capacity   development contributes to the                              be immaterial relative to that generated by the
     to safely and efficiently accommodate   transport network in accordance with                        broader Noosa Business Centre. Consequently, no
                                             the requirements of the applicable
     projected movements; and/or                                                                         transport infrastructure upgrades are considered
                                             infrastructure charging instrument and
 b) the development includes measures to                                                                 necessary to support the subject development.
                                             the Priority Infrastructure Plan in
     upgrade the transport network to meet   accordance with legislation.
     the imposed demands
                                             Editor’s note
                                             Council may for some development require the
                                             preparation of a Transport Impact Assessment
                                             Report. Planning Scheme Policy PSP1 details
                                             matters to be addressed in the Report.

O2                                           S2.1                                               ü        Complies with S2.1
The street network has high street           Road planning and development design                        The design of the subject development prioritises
connectivity, both within the development    facilitates as many pedestrian and                          pedestrian and cycle movements by providing
and to the surrounding local area.           cycle movements as possible and                             convenient pedestrian connections to the existing
                                             provides for future connectivity and                        pathway network whilst also locating bicycle parking
                                             integration with adjoining sites;                           in convenient and amenable location.
                                             AND
                                             S2.2                                              N/A       S2.2 not applicable
                                             Arterial and sub-arterial roads are                         The subject development does not include the
                                             designed so they can operate with                           provision or upgrading of arterial or sub-arterial
                                             acceptable volumes of traffic during                        roads.
                                             peak times;
                                             AND

Page 30

S2.3                                         N/A   S2.3 not applicable
Collector and local streets are provided           The subject development does not include the
to support short trips for local traffic           provision or upgrading of public collector and local
moving in and between                              streets.
neighbourhoods. Local traffic is
channelled towards collector streets to
ensure that traffic volumes on local
street are kept low;
AND
S2.4                                         N/A   S2.4 not applicable
Collector and local streets are designed           The subject development does not include the
to discourage through traffic;                     provision or upgrading of public collector and local
AND                                                streets.
S2.5                                         N/A   S2.5 not applicable
A collector street is provided parallel to         The subject development does not include the
arterials particularly where they pass             provision or upgrading of public collector streets.
through town centres;
AND
S2.6                                         N/A   S2.6 not applicable
Appropriate width of road and verge is             The subject development does not include the
provided to allow streets to perform               provision of new public roads.
their designated functions in the street
network;
AND
S2.7                                         N/A   S2.7 not applicable
A network of local streets focused                 The subject development does not include the
towards an activity centre or school is            provision of new public roads.
provided for safe and efficient
pedestrian and bike access to the
school, safe conditions for school
buses, setdown facilities, with on-site
parking where practical;
AND
S2.8                                         N/A   S2.8 not applicable
Passive surveillance is maximised by               The subject development does not include the
designing streets to enable                        provision of new public roads.

Page 31

development to front all streets and
roads, including arterials;
AND

S2.9                                       N/A   S2.9 not applicable
Streets near Public Passenger                    The subject development does not include the
Transport facilities are orientated to           provision of new public roads.
optimise the walkable catchments
within 800 metres walking distance;
AND

S2.10                                      N/A   S2.10 not applicable
The street network has no more than              The subject development does not include the
15 percent of lots fronting cul-de-sacs.         provision of a new public road network.
The maximum cul-de-sac length is 120
metres;
AND
S2.11                                      N/A   S2.11 not applicable
Street stubs to adjacent future                  The subject development does not include the
development areas are provided at                provision of a new public road network and does not
spacings of 200 m or closer to enable            abut future development areas.
future street connections to be made;
AND
S2.12                                      N/A   S2.12 not applicable
Street block lengths are not more than           The subject development does not include the
240 m long, and predominantly around             provision of a new public road network.
150-180 m long. Street block lengths
are generally shorter closer to town and
neighbourhood centres;
AND
S2.13                                      ü     Complies with S2.13
Direct, safe and attractive pedestrian           The subject development proposes numerous direct
and cycle routes are provided within             connections to the surrounding pathway
and through the development and                  infrastructure network to accommodate active
connect to bus stops.                            transport demands.

Page 32

O3                                          S3.1                                        N/A   S3.1 not applicable
Development is designed –                   Higher     density    development      is         The subject development does not propose varying
a) To encourage travel by community         concentrated along public transport               densities of development and is not traversed by
    transport, walking and cycling rather   Routes;                                           public transport routes.
    than by private car; and                AND
b) To maximise accessibility via existing   S3.2                                        N/A   S3.2 not applicable
    and planned community transport         There is provision for bus routes                 The subject development is not of a scale which
    facilities                              through development sites;                        would support internal bus routes.
                                            AND
                                            S3.3                                        N/A   S3.3 not applicable
                                            Bus routes are located to maximise                The subject development is not of a scale which
                                            patronage catchment and to consider               would support internal bus routes.
                                            personal safety, lighting and traffic
                                            management;
                                            AND
                                            S3.4                                        N/A   S3.4 not applicable
                                            At least 90 percent of all residents are          The subject development does not propose any
                                            located within 400 metres of an                   residential land uses.
                                            existing or
                                            planned bus route;
                                            AND
                                            S3.5                                        ü     Complies with S3.5
                                            Pedestrian and cycle movement is                  The subject development does not compromise and
                                            provided within local streets to and              is not expected to have any material impact on
                                            through development;                              existing cycle routes, whether they are on-road or
                                            AND                                               accommodated by dedicated infrastructure.
                                            S3.6                                        N/A   S3.6 not applicable
                                            Attractive and safe pedestrian and                Landscaping are urban design considerations are
                                            cycle connections are provided with               beyond the scope of this traffic assessment.
                                            shade trees, graded walking and cycle
                                            paths and lighting;
                                            AND
                                            S3.7                                        N/A   S3.7 not applicable
                                            Buildings and pedestrian entrances                Architectural considerations are beyond the scope of
                                            are oriented to the street;                       this traffic assessment.
                                            AND

Page 33

S3.8                                        ü     Complies with S3.8
Pathways have ramps at all kerb                   The subject development proposes to integrate with
corners for wheelchair and pram                   surrounding pathway infrastructure which makes use
access;                                           of kerb ramps at crossing locations.
AND
S3.9                                        ü     Complies with S3.9
Every development has convenient and              The subject development proposed direct and short
prominent pedestrian entrances that               pedestrian connections to the fronting pathways of
cater for all pedestrians including older         adequate width to accommodate mobility impaired
people, children and the mobility and             persons. While not shown on the proposed plans,
vision impaired;                                  the topography of the site is conducive to these
                                                  connections not having an excessive grade.
S3.10                                       N/A   S3.10 not applicable
Expanses of ground level blank walls              Architectural considerations are beyond the scope of
along street frontages, and large                 this traffic assessment.
driveways and entrances to carparks
are avoided;
AND
S3.11                                       N/A   S3.11 not applicable
Bus routes are not be located away                The subject development is not of a scale which
from activity centres; and                        would support internal bus routes.
AND
S3.12                                       N/A   S3.12 not applicable
Facilities for boarding and exiting               The subject development does not include the
community transport facilities are                provision of public transport infrastructure.
incorporated into developments;
AND
S3.13                                       N/A   S3.13 not applicable
Pedestrian and cycle routes within or             Architectural considerations are beyond the scope of
adjacent to the development are                   this traffic assessment.
overlooked by adjoining buildings,
make use of views and attractive
sights, have lighting and are
signposted;
AND

Page 34

S3.14                                       ü     Complies with S3.14
Suitable car restraint measures are               Basement carparks as proposed as part of the
adopted within the development such               subject development are inherently low speed
as lower speed limits or traffic calming          environments. Adequate bicycle parking facilities are
measures to support greater pedestrian            also provided to accommodate and encourage the
and cycle movement;                               use of active transport modes, with the facilities
AND
                                                  located to maximise security and convenience as
                                                  discussed within Section 4.4 of the attached traffic
                                                  assessment.
S3.15                                       N/A   S3.15 not applicable
Traffic management devices on                     The subject development is not of a scale which
potential bus routes are provided in              would support internal bus routes.
accordance with the accepted
development subject to requirements
code for undertaking road works on
local government roads, under the
Transport Planning and Coordination
Regulation 2005;
AND
S3.16                                       N/A   S3.15 not applicable
Streets identified as potential bus               The subject development is not of a scale which
routes are—                                       would support internal bus routes or an internal
a)    collector streets and sub-                  street network.
      arterial/arterial roads which
      provide highly accessible and
      relatively direct routes wherever
      practical;
b)    those that provide for the shortest
      and most direct route for an
      efficient public transport service;
      and
c)    those that can efficiently service
      adjoining development areas.

Page 35

O4                                              No solution provided.                    ü     Complies with O4
Development access does not                                                                    The subject development makes use of existing road
compromise the functions of particular roads                                                   accesses and therefore does not impact on the
as indicated in the road hierarchy, and does                                                   function of any public roads.
not adversely impact on the safety, capacity
and operations of the road system.
O5 Pedestrian and cycle path infrastructure     S5.1                                     ü     Complies with S5.1
is provided –                                   Consideration is given to existing and         The subject development includes provision of direct
 a) to form an integrated component of          future pathway linkages and pathways           pathway connections to the site’s road frontages.
       the movement network and the             link to the Local and Regional Cycle
       open space system;                       Network and to the Priority
 b) to encourage walking and cycling;           Infrastructure Plan in Part 15.
 c) to add variety and visual interest;
 d) to conserve street trees, vegetation        S5.2                                     ü     Complies with S5.2
       and other significant features;          Direct and accessible linkages are             The subject development includes provision of direct
 e) to allow equitable access to public         provided into the site.                        pathway connections to the site’s road frontages.
       areas and community facilities;
 f) with adequate lighting where subject to     S5.3                                     ü     Complies with S5.3
       high night time usage;                   Pathway and landscape works are                All pathways are to be designed and constructed in
 g) in locations where there is casual          provided to a high standard to Council         accordance with relevant standards.
       surveillance;                            specifications and assessed for
 h) or widened at potential conflict            compliance with local government
       points;                                  cycling facility design standards.
 i) to incorporate—
    i.    street tree planting to enhance the   S5.4                                     N/A   S5.4 not applicable
          streetscape;                          Pathways are provided to cater for             The subject development is not of a scale which
directional signage that is visible under all   shared use and cater for both                  would justify the provision of dedicated shared paths.
conditions.                                     commuting and recreational usage
                                                and exceed minimum standards.

Page 36

O6      Pedestrian and cycle path                S6.1 Pedestrian and cycle path                      N/A   S6.1 not applicable
infrastructure is designed and constructed       infrastructure is designed and                            The subject development is not of a scale which
to –                                             constructed –                                             would justify the provision of dedicated shared paths.
a)    provide a stable, smooth surface,          a)     in accordance with
      including across driveways, sections              AUSTROADS;
      and joins;                                 b)     to comply with local government
b)    be easily maintained;                             design standards;
c)    a width and longitudinal gradient to       c)     to have navigational signs in
      cater for projected usage, including              accordance with Council
      nearby—                                           ‘Wayfinding’ signage
       i)        high activity                          specifications; and
       nodes; ii)                                d)     to incorporate –
        public transport; iii)                         i) kerb ramps at all
        centres;                                            intersections and designated
d)    provide clear sight-lines for safe use;               crossings;
      and                                              ii) refuge islands on all roads
e)    be free of any obstructions such as                   with median strips; and
      fences, signage and bollards.                    iii) holding rails for cyclists at the
                                                            intersection of trunk collector,
                                                            subarterial and arterial roads
                                                            that are positioned in
                                                            accordance with –
                                                            A. Australian Standard
                                                                1742.9: 2000 - Manual of
                                                                Uniform Traffic Control
                                                                Devices - Bicycle
                                                                Facilities; and
                                                            B. AUSTROADS Part 14 -
                                                                Bicycles - Section 9; and
                                                            C. AUSTROADS Part 13 –
                                                                Pedestrians.
                                                Editor’s note:
                                                All pathways are considered shared use
                                                pathways, which Cyclists can legally use, unless
                                                bicycles are specifically prohibited through signs
                                                or markings (such as in town centres).

Page 37

Table 14-59 – Roads and drainage
Specific Outcomes                                Probable Solutions                            Compliance   Response
                                                                                                 ü/û/NA
Road and drainage design and construction
O7                                                  S7.1                                          N/A       S7.1 not applicable
Roads and pedestrian and cycle paths are            Road planning and design supports the                   The subject development does not propose the
planned and designed to support the                 hierarchy and functional aspects                        planning or construction of new or upgraded road
hierarchy and functional aspects identified in identified in Sections 2 and 3 of PSP5                       infrastructure.
Sections 2 and 3 of PSP5 Engineering                Engineering Design Standards –
Design Standards – Roads, Drainage and              Roads, Drainage and Earthworks;
Earthworks and to ensure that –                     AND
 a) design and alignment of the roads,
        intersections and all associated
        works—                                      S7.2                                          N/A       S7.2 not applicable
      i.     provides a safe environment for        Road and pathway planning and design                    The subject development does not propose the
             all users;                             is in accordance with, in order of                      planning or construction of new or upgraded road or
     ii.     is adequate for the design speed       precedence—                                             public pathway infrastructure.
             environment;                           a) Noosa Integrated Local Transport
    iii.     is adequate for predicted traffic            Plan;
             volumes; and                           b)    Queensland Transport’s Shaping
   iv.       maintains the safe and efficient             Up;
             functioning of the road network        c)    Queensland Design Code for
             without the use of traffic signals;          Residential Streets;
     v.      is compatible with existing roads; vi. d)    AUSTROADS      Guide to Traffic
             is easily maintained by Council              Engineering  Practice;
             equipment; and                         e)      Sections 2 and 3 of PSP5
   vi.       where appropriate, has the ability to        Engineering   Design Standards –
             accommodate public transport                 Roads,   Drainage  and Earthworks;
             services;                                    or
 b) road pavement surfaces—                         f) the Noosa Cycling and Walking
     i.      are durable enough to carry                  Network Development Plan;
             estimated wheel loads of travelling OR
             and parked vehicles;                   g) A combination of the principles in
   ii.       provide for the safe passage of              these documents.
             vehicles, pedestrians, cyclists, and
                                                    AND

Page 38

             discharge of stormwater run-off        S7.3                                       N/A   S7.3 not applicable
             from contributing catchments and       On-road cycling treatment is utilised to         The subject development does not propose the
             the preservation of all weather        provide safe and continuous movement             planning or construction of new or upgraded road
             access;                                of cyclists along a roadway, such as—            infrastructure.
c) kerb and channel—                                a) sealed shoulders;
   i.      controls vehicle movement by             b) wide kerbside lane;
           delineating the carriageway for all      c) exclusive or peak
           users;                                        period bicycle lane;
  ii.      conveys road pavement run-off to         d) advisory treatments
           stormwater drainage in a manner               such as Bicycle
                                                         Awareness Zone;
           that allows the road to be trafficable
                                                    e) shared parking / bicycle
           in Q100 ARI local rainfall events;            lane;
           and                                      f)   contra flow bicycle
d) verges and footpaths provide—                         lane; and
      i. safe access for pedestrians and            g) bus/bicycle lane.
           cyclists clear of obstructions;
      ii. an access area for vehicles onto          S7.4                                       N/A   S7.4 not applicable
           properties;                              The provision of bicycle lanes at                The subject development does not propose the
      iii. a corridor allocated for services and    intersections is generally in                    planning or construction of new or upgraded road
           utilities; and                           accordance with AUSTROADS Part                   infrastructure.
      iv. additional amenity for minor roads.       14, section 5 and the Manual of Urban
                                                    Traffic Control Devices (MUTCD) Part
                                                    9.
O8                                                  S8.1                                       N/A   S8.1 not applicable
Stormwater drainage infrastructure is               Stormwater drainage planning, design             Stormwater considerations are beyond the scope of
planned, designed and constructed to—               and construction is in accordance with           this traffic assessment.
a)   be accessible, cost effective and              Section 4 of PSP5 Engineering Design
     easily maintainable;                           Standards – Roads, Drainage and
b)   protect downstream capacity;                   Earthworks;
c)   protect downstream water quality;              AND

Page 39

 d)   maximise on-site stormwater             S8.2                                    N/A   S8.2 not applicable
      retention and retardation; and          As Constructed data is submitted in           Stormwater considerations are beyond the scope of
 convey run-off to stormwater drainage in a   accordance with Section 6 of PSP5             this traffic assessment.
 manner that allows roads to be trafficable   Engineering Design Standards –
 in Q100 ARI local rainfall events            Roads, Drainage and Earthworks; AND




                                              S8.3 Stormwater drainage planning,      N/A   S8.3 not applicable
                                              design and construction is in                 Stormwater considerations are beyond the scope of
                                              accordance with the Queensland Urban          this traffic assessment.
                                              Drainage Design Manual

O9       Roads and stormwater drainage        S9.1                                    N/A   S9.1 not applicable
infrastructure is constructed—                Roads and stormwater drainage                 Stormwater considerations are beyond the scope of
a)    in accordance with appropriate          infrastructure is constructed in              this traffic assessment.
      engineering standards; and              accordance with—                              The subject development also does not propose the
to minimise adverse environmental impacts,    a) Sections 2, 3 and 4 of PSP5                planning or construction of new or upgraded road
including from run-off and erosion.                Engineering Design Standards –           infrastructure.
                                                   Roads, Drainage and Earthworks;
                                              b) Queensland Design Code for
                                                   Residential Streets;
                                              c) AUSTROADS; or
                                              d) A combination of the principles in
                                                   these documents;
                                              AND

Page 40

                                               S9.2                                       N/A   S9.2 not applicable
                                               Erosion and sediment control measures            Erosion and sediment control considerations are
                                               are designed and implemented in                  beyond the scope of this traffic assessment.
                                               accordance with the Institution of
                                               Engineers Australia (Queensland
                                               Division) Soil Erosion and Sediment
                                               Control - Guidelines for Queensland
                                               Construction Sites.

Environmental Protection                                                                  N/A   S10.1 not applicable
O10                                            S10.1                                            Stormwater considerations are beyond the scope of
Roads and stormwater drainage                  Roads and stormwater drainage follow             this traffic assessment.
infrastructure are located and aligned so as   the edge of existing disturbed areas, or         The subject development also does not propose the
to— a) minimise disturbance to native          alternatively, these works are co-               planning or construction of new or upgraded road
vegetation and/or other habitat areas;         located within                                   infrastructure.
b) protect and maintain wildlife corridor      a combined utility corridor;
     movements and the safety of native        AND
     fauna;
c) minimise changes to the hydrological        S10.2                                      N/A   S10.2 not applicable
     regime, including drainage patterns,      Roads avoid native vegetation and                The subject development does not propose the
     run-off and water quality;                provide for fauna underpasses and                planning or construction of new or upgraded road
d) avoid crossing watercourses, drainage       associated                                       infrastructure.
     lines and wetlands, but where such        fencing where appropriate;
     crossings are unavoidable, disturbed      AND
     areas are reinstated and revegetated
                                               S10.3                                      N/A   S10.3 not applicable
     on completion of works; and
                                               Road infrastructure within or adjacent           The subject development does not propose the
minimise bulk earthworks.
                                               to native habitat incorporates fences            planning or construction of new or upgraded road
                                               which allow for protected wildlife               infrastructure.
                                               movement and controls unrestricted
                                               access of domestic cats and dogs;
                                               AND

Page 41

                                                  S10.4                                       N/A   S10.4 not applicable
                                                  Native vegetation is protected from               Preservation of flora or fauna is beyond the scope of
                                                  clearing or construction activities by—           this traffic assessment.
                                                  a) clearly marking vegetation to be
                                                        retained with flagging tap;
                                                  b) installing protective fencing
                                                        around the dripline of vegetation;
                                                        and
                                                  c) ensuring stock piling, storage and
                                                        vehicle parking occur outside the
                                                        areas of vegetation to be retained;
                                                  AND

                                                  S10.5                                       N/A   S10.5 not applicable
                                                  Low impact construction techniques                Preservation of flora or fauna is beyond the scope of
                                                  are used around areas of vegetation to            this traffic assessment.
                                                  be retained to minimise interference
                                                  with the vegetation.
O11                                               No solution provided                        N/A   O11 not applicable
Roads and stormwater drainage                                                                       Stormwater considerations are beyond the scope of
infrastructure is proven to be suitable for its                                                     this traffic assessment.
use prior to Council accepting the dedicated                                                        The subject development also does not propose the
asset.                                                                                              planning or construction of new or upgraded road
                                                                                                    infrastructure.
O12                                               S12.1                                       N/A   S12.1 not applicable
Alignment of stormwater drainage                  The location, design and construction             Stormwater considerations are beyond the scope of
infrastructure is to allow for easy access for    of stormwater drainage structures is in           this traffic assessment.
the ongoing maintenance by Council.               accordance with Sections 4 and 5 of
                                                  PSP5, Engineering
                                                  Design Standards - Roads, Drainage
                                                  and Earthworks;
                                                  AND
                                                  S12.2                                       N/A   S12.2 not applicable
                                                  Where infrastructure is located on                Stormwater considerations are beyond the scope of
                                                  private land an easement is dedicated             this traffic assessment.
                                                  over the infrastructure in accordance
                                                  with Section 4 of PSP 5, Engineering

Page 42

                                          Design Standards – Roads, Drainage
                                          and Earthworks.
Frontage works
O13                                       S13.1                                       ü     Complies with S13.1
Development is provided with external     The following infrastructure                      The roads fronting the subject site are already of an
roadworks along the full extent of the    components already exist at the                   adequate standard and therefore no upgrades of the
frontage of the site to an appropriate    frontage of the site or are provided at           fronting roads are required or proposed.
standard having regard to the specified   the developer’s expense—
function of the road.                     a) full width sealed road;
                                          b) concrete kerb and channel where
                                              appropriate;
                                          c) forming and grading to footpaths;
                                          d) vehicular kerb and footpath
                                              crossings;
                                          e) a constructed bikeway;
                                          f) a constructed footpath;
                                          g) a constructed carriageway;
                                          h) required alterations to public utility
                                              mains, services or installations;
                                          i) construction of any required
                                              alterations to public utility mains,
                                              services or installations;
                                          j) stormwater drainage works; and
                                          k) installation of electrical conduits;
                                          AND
                                          S13.2                                       N/A   S13.2 not applicable
                                          Road and drainage design and                      Stormwater considerations are beyond the scope of
                                          construction is in accordance with                this traffic assessment.
                                          Sections 3 and 4 of PSP5 Engineering              The subject development also does not propose the
                                          Design Standards – Roads, Drainage                planning or construction of new or upgraded road
                                          and Earth works.                                  infrastructure.

Road and rail corridors

Page 43

O14 Noise sensitive uses including           S14.1                                    N/A   S14.1 not applicable
residential uses are not subjected to high   Noise sensitive uses including                 Acoustic considerations are beyond the scope of this
traffic noise levels from the major road     residential uses are separated by a            traffic assessment.
network or rail corridors.                   minimum of—
                                             a) 40m from the property boundary
                                                  of roads within the major road
                                                  network; and
                                             b) 80m from the property boundary
                                                  of rail corridors;
                                             OR

                                             S14.2                                    N/A   S14.2 not applicable
                                             Development in the vicinity of road            Acoustic considerations are beyond the scope of this
                                             corridors meets the following external         traffic assessment.
                                             design criteria for roads in the major
                                             road network— a)           54dB(A)L10
                                             (18hours) based on predicted traffic
                                             volumes ten years hence;
                                             AND

                                             S14.3                                    N/A   S14.3 not applicable
                                             Development in the vicinity of rail            Acoustic considerations are beyond the scope of this
                                             corridors meets the following external         traffic assessment. The subject site is also not
                                             design level noise criteria—                   located in the vicinity of a rail corridor.
                                             a)     65dB(a), assessed as the
                                                    24hour average equivalent
                                                    continuous Aweighted sound
                                                    pressure level; and
                                                    b)        87dB(A), assessed as
                                                    a single event maximum sound
                                                    pressure level.
Staged development
O15                                          No solution provided.                    N/A   O15 not applicable
Staged development is planned, designed                                                     Construction of the subject development will not be
and constructed to ensure that—                                                             staged.
a)   each stage of the development can be
     constructed without interruption to

Page 44

     services and utilities provided to the
     previous stages;
b)   the infrastructure provided is capable
     of servicing the entire development;
     and
c)   the materials used are consistent
     throughout the development.

Alterations to services and utilities
O16 Any alterations or repairs to               S16.1 Any alterations or repair to   N/A   S16.1 not applicable
infrastructure as a result of the development   infrastructure as a result of the          Consideration of services is beyond the scope of this
are made at no cost to Council.                 development are completed at the           traffic assessment.
                                                developer’s expense.

Page 45

Division 19 – Waste Management Code
Table 14-60

Specific Outcomes                             Probable Solutions                          Compliance   Response
                                                                                            ü/û/NA
Waste separation                                                                             N/A       S1.1 not applicable
O1                                            S1.1                                                     Construction, operational and demolition works
Development that generates several classes    Construction, operational and                            considerations are beyond the scope of this traffic
of waste is designed so waste is collected,   demolition works are planned and                         assessment.
stored and disposed of in a safe and          managed in accordance PSP11
ecologically sustainable manner3.             AND
                                              S1.2                                            ü        Complies with S1.2
                                              Adequate area is provided for on-site                    The subject development includes the provision of a
                                              for the collection and separate storage                  dedicated bin storage area capable of
                                              of recyclable, non-recyclable,                           accommodating up to two 1,100L bulk bins, which is
                                              vegetative and hazardous materials in                    considered adequate given the proposed land use is
                                              their specific waste streams during                      expected to have a low waste generation potential.
                                              construction, operational and
                                                                                                       The disposal of medical waste is to be arranged by
                                              demolition works;
                                                                                                       individual tenants as required.
                                              AND
O2                                            S2.1                                            ü        Complies with S2.1
Waste storage areas provide for adequate      Waste storage areas allow for the                        The subject development does not preclude the
separation of all recyclable and non-         separate storage of different waste                      storage of a recycling bin alongside a general waste
recyclable materials.                         materials for reuse or recycling by—                     bin in the bin storage area. Signage would be
                                              a)     providing sufficient area to store                resolved as part of the detailed design process.
                                                     all recyclable material and
                                                     recycling containers required; and
                                              b)      sign posting the types of waste
                                                     stored.
Design and location of waste storage                                                          ü        Complies with S3.1
areas                                         S3.1                                                     The design of the proposed waste storage area is to
O3                                            Waste storage areas are designed and                     be resolved as part of the detailed design process;
Waste storage areas are located so that       maintained in accordance with PSP 9;                     however the subject development does not preclude
they are convenient and safe to use and       AND

Page 46

provide for convenient and safe collection by S3.2                                           the provision of waste storage facilities in
service vehicles;                             Waste storage areas are designed and           accordance with Council requirements.
                                              located so they—                               Complies with S3.2
                                              a)    are easily accessed and                  The location of the waste storage area has been
                                                    convenient to use;                       chosen based on easy and convenient access by
                                              b)    have unobstructed access for the         waste collection contractors whilst still allowing
                                                    collection of the waste by service       sufficient space for necessary service vehicle
                                                    vehicles;                                manoeuvres. The proposed waste storage
                                              c)    provide for sufficient space for         arrangements are also generally consistent with the
                                                    safe entry and exit and servicing        current function of the service road which circulates
                                                    by Council’s contractor without
                                                                                             behind the Showroom Emporium tenancies.
                                                    the need for manual handling;
                                                                                             It is also noted that the site would sit within the
                                              d)    are clear of carparking bays,
                                                                                             Waste Management Plan (WMP) currently in place
                                                    loading bays and similar areas;
                                                                                             for the Noosa Business Centre, with waste to be
                                              e)    are clear of footpaths and
                                                                                             collected by the centre’s existing third-party
                                                    pedestrian access;
                                              f)    are capable of being serviced by         contractor.
                                                    the collection vehicle without
                                                    impeding traffic flow; and
                                              g)    have a level area provided for the
                                                    storage of waste and recyclable
                                                    materials in
                                                    standard waste containers;
                                                    AND
                                              S3.3                                       ü   Complies with S3.3
                                              For uses that do not comprise a                The proposed waste storage area has been located
                                              caretaker’s residence or central               to minimise the distance needed to transfer waste to
                                              management, the maximum distance               vehicles and is therefore well within Council’s
                                              between waste storage areas and the            requirements.
                                              kerbside is—
                                              a) for Multiple housing Type 3 –
                                                   40m; or
                                              b) for other uses – 70m; and

Page 47

                                             S3.4                                      ü     Complies with S3.4
                                             Pathways used to transport bins—                Waste collection contractors are not required to
                                             a) have a maximum grade of 1:15;                travel along pathways to transport waste to their
                                                 and                                         vehicles. The travel path does not contain steep
                                             b) are free of steps, stairs or other           grades or obstructions such as steps.
                                                 impediments;


O4      The location and methods of waste    S4.1                                      N/A   S4.1 not applicable
storage minimises any adverse impacts on     Waste storage areas are—                        Architectural aspects of waste storage are beyond
adjoining or nearby properties;              a)    integrated with the building              the scope of this traffic assessment.
                                                   design, where possible;
                                             b)    setback a minimum of 2m from
                                                   side and rear property
                                                   boundaries;
                                             c)    screened so that bins are not
                                                   visible from neighbouring
                                                   properties or passing vehicular
                                                   and pedestrian traffic; and
                                             d)    not located directly adjacent to
                                                   dwelling units on the site on
                                                   neighbouring
                                                   properties;
                                              AND
O5                                           S5.1                                      N/A   S5.1 not applicable
 Waste storage areas are designed for ease   Waste storage areas are constructed of          Architectural aspects of waste storage are beyond
of maintenance and ease of access for        impermeable, durable and non textured           the scope of this traffic assessment.
cleaning;                                    materials and surfaces so that they are
                                             easily cleaned;
                                             AND
                                             S5.2                                      ü     Complies with S5.2
                                             A minimum distance of 0.5m2 distance            The proposed location of the bin store provides
                                             is provided between and around waste            some flexibility with the provision of space for
                                             storage bins to allow for manoeuvring           manoeuvring and washing of bins.
                                             and washing of bins.

Page 48

O6                                               S6.1                                       N/A   O6 not applicable
Waste storage areas provide a safe and           No solution provided.                            The considerations are beyond the scope of this
secure environment for users through–                                                             traffic assessment.
 a) appropriate siting and access;
 b) the provision of lighting; and
 c) restricting access to the general public
     by making the area clearly identifiable
     as private space (eg. through
     landscaping, change of paving material
     or fencing, rather than locking the area.
Water management for waste storage                                                          N/A   S7.1 not applicable
areas                                            S7.1                                             Water management considerations are beyond the
O7                                               The waste storage area —                         scope of this traffic assessment.
Waste storage areas are designed to              a) is bunded and graded so that
contain and appropriately dispose of                 washwater and bin leakage are
leakage from bins and wastewater from bin            drained to the sewer or an on-site
washing.                                             effluent disposal system via a gully
                                                     within the storage area;
                                                 b) has a bund wall with a maximum
                                                     height of
                                                     100mm;
                                                 c) is serviced by a conveniently
                                                     located hosecock and backflow
                                                     prevention device, and connected
                                                     to a water supply; and
                                                 d) is roofed or otherwise covered if
                                                     the storage area is—
                                                     i more than 1m2; or
                                                     ii storing wet waste; or
                                                     iii storing other waste with a
                                                         high potential to cause
                                                         pollution if washed or
                                                         leaked from the bins,
                                                         including waste oil or
                                                         putrescibles.

Used in these records

About this file

File size
3.3 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Appendix E Traffic Impact Assessment Report.pdf · 3.3 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.