Objective: To minimise impacts of the works on items of cultural or heritage significance.
Issues: No impacts expected.
Performance Criteria: No disturbance of cultural heritage items.
Control Measures:
Responsible
Control Measures
Party
1. If items are identified that potentially have cultural significance, immediately notify Traditional Owners and Contractor
seek advice.
2. Dredging and nourishment activities at Munna Point Caravan Park to be undertaken in a manner that Contractor
minimises impacts on visual and recreational aesthetics during the works.
3. Public access to be maintained to the foreshore during the works. Contractor
4. On completion, nourishment to form a natural profile and not present safety hazards to users. Contractor
Monitoring: Monitoring is to be undertaken in accordance with Table 4.
WASTE
Dredged sediments are not considered to be waste.
The dredging activity generates wastes, including general rubbish and hazardous wastes.
Objective: To minimise impact of waste generated by the dredging works.
Issues: Release of waste to receiving waters.
Performance Criteria: No loss of waste overboard. No unsuitable disposal of waste.
Control Measures:
Responsible
Control Measures
Party
1. No garbage to be thrown overboard or into the environment. Materials and equipment is to be secured to Contractor
prevent accidental loss overboard, particularly during inclement weather. If garbage accidently ends up in
the water, it is to be retrieved.
2. Waste bins are to have secure lids, be appropriately sized and be disposed of regularly to a suitable Contractor
facility onshore. Waste to be recycled where possible.
3. Hazardous wastes must be stored in an appropriate and secure manner with collection and transport by a Contractor
licenced Contractor.
4. On completion of the works, inspect and remove any waste generated as a result of the works. Contractor
25
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.