SITE-SPECIFIC APPROVALS
Works are to be performed in accordance with the relevant project approvals and permits. A copy of all relevant
permits is to be available on site and onboard any vessels throughout the works.
Table 2: Relevant Approvals
Permit Type Permit Number
Operational Works Permit TBA
Environmental Authority TBA
SCOPE OF CONCEPT DREDGE MANAGEMENT PLAN
The purpose of this Concept Dredge Management Plan is to document a structured program that:
• Sets the environmental objectives or standards to be achieved;
• Identifies the potential environmental harm which may occur from routine operations and establishes, and
documents measures to avoid this harm as far as practicable;
• Identifies extraordinary factors (i.e. abnormal operation, emergencies) that may cause environmental
harm and establishes and documents contingency plans to deal with these;
• Ensures all persons carrying out the activity are aware of the environmental risks, and are trained in the
measures and contingency plans to deal with them;
• Implements monitoring of environmental performance to ensure the effectiveness of the measures and
contingency plans;
• Assists the communication of environmental information throughout the organisation and to the
administering authority; and
• Provides for continual improvement.
A Site-Specific Environment Management Plan is to be developed and implemented by the Contractor and is to
be consistent with:
• Relevant permit conditions.
• Relevant legislation requirements.
• Concept Dredge Management Plan (this document).
• Contract documentation.
This Site-Specific Environment Management Plan is to be reviewed and accepted by the approval holder
(Principal) prior to the works being undertaken.
To achieve the intended outcomes, including enhancing the environmental performance, the dredging contractor
is to establish, implement, maintain and continually improve the plant and vessel specific Safety Management
Systems and this Site-Specific Environmental Management Plan, including the processes needed and their
interactions.
6
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.