Skip to the record
NoosaWatch™: The source of truth.

Original source · versioned page text

6. Noosa River DMP Ver0 (Combined)

of 392

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file (18.5 MB): the original may take a few minutes to open or download. The page text below is quick to read.

Original PDF page 8, section 1. The text section number identifies this passage in the reader.

               SITE-SPECIFIC APPROVALS
Works are to be performed in accordance with the relevant project approvals and permits. A copy of all relevant
permits is to be available on site and onboard any vessels throughout the works.

Table 2: Relevant Approvals

    Permit Type                                  Permit Number
    Operational Works Permit                          TBA
    Environmental Authority                           TBA




               SCOPE OF CONCEPT DREDGE MANAGEMENT PLAN
The purpose of this Concept Dredge Management Plan is to document a structured program that:
       •    Sets the environmental objectives or standards to be achieved;
       •    Identifies the potential environmental harm which may occur from routine operations and establishes, and
            documents measures to avoid this harm as far as practicable;
       •    Identifies extraordinary factors (i.e. abnormal operation, emergencies) that may cause environmental
            harm and establishes and documents contingency plans to deal with these;
       •    Ensures all persons carrying out the activity are aware of the environmental risks, and are trained in the
            measures and contingency plans to deal with them;
       •    Implements monitoring of environmental performance to ensure the effectiveness of the measures and
            contingency plans;
       •    Assists the communication of environmental information throughout the organisation and to the
            administering authority; and
       •    Provides for continual improvement.


A Site-Specific Environment Management Plan is to be developed and implemented by the Contractor and is to
be consistent with:
       •    Relevant permit conditions.
       •    Relevant legislation requirements.
       •    Concept Dredge Management Plan (this document).
       •    Contract documentation.
This Site-Specific Environment Management Plan is to be reviewed and accepted by the approval holder
(Principal) prior to the works being undertaken.
To achieve the intended outcomes, including enhancing the environmental performance, the dredging contractor
is to establish, implement, maintain and continually improve the plant and vessel specific Safety Management
Systems and this Site-Specific Environmental Management Plan, including the processes needed and their
interactions.




6
Log in to download the original file

6. Noosa River DMP Ver0 (Combined).pdf · 18.5 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.