Project Hazard / Risk Assessment Ozcare Noosa RACF 23/04/2024 [OCR of page images] woollam CONSTRUCTIONS Project Hazard / Risk Assessment Ozcare Noosa RACF 23/04/2024 F/ WORKING TOGETHER TO BUILD LEGACIES
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of pages 2 to 56 (of 80)
Page 2
Contents
1. Introduction ........................................................................................................................................... 6
1.1 Project Information .......................................................................................................................... 6
1.2 Revision History................................................................................................................................ 7
1.3 Site Specific Hazard/Risk Register Approval..................................................................................... 7
1.4 Definitions ........................................................................................................................................ 8
1.1 Risk Matrix...................................................................................................................................... 11
2. Safety in Design Residual Risks ............................................................................................................ 13
2.1 Design and Construct Project ......................................................................................................... 14
3. Working in a Client’s Workplace .......................................................................................................... 15
3.1 Refurbishment works in a live environment .................................................................................. 15
3.2 Use of client safety systems ........................................................................................................... 15
3.3 Stakeholder required exclusion zones ........................................................................................... 16
3.4 Access ............................................................................................................................................. 16
4. Environmental Assessment ................................................................................................................. 17
5. Public Protection Controls and Traffic Management .......................................................................... 20
5.1 Traffic Management ....................................................................................................................... 21
6. Site Facilities ........................................................................................................................................ 24
6.1 Site Requirements .......................................................................................................................... 24
7. Work Environment Hazards ................................................................................................................. 27
7.1 Hazardous Manual Tasks................................................................................................................ 27
7.2 Pandemic ........................................................................................................................................ 27
7.3 Noise, Dust and Heat...................................................................................................................... 28
7.4 Confined Spaces ............................................................................................................................. 30
7.5 Hot Work ........................................................................................................................................ 32
7.6 Works in Isolated Conditions ......................................................................................................... 33
7.7 Portable Power Tools ..................................................................................................................... 34
7.8 Explosive Power Tools .................................................................................................................... 34
7.9 Biological Hazards .......................................................................................................................... 35
7.10 Fumes, gas, vapour hazards ........................................................................................................... 37
8. Hazardous Substances ......................................................................................................................... 46
Page 3
8.1 Asbestos Removal .......................................................................................................................... 46
8.2 Lead Process ................................................................................................................................... 48
8.3 Respirable Crystalline Silica Dust (RCS) .......................................................................................... 49
8.4 Medium Density Fibreboard (MDF) ............................................................................................... 52
8.5 Hazardous Chemicals (as defined under Schedule 14 WHS Reg 2011) .......................................... 53
9. Electrical .............................................................................................................................................. 56
9.1 Temporary Power........................................................................................................................... 56
9.2 Works around overhead and underground electrical installations ............................................... 59
9.3 Electrical equipment ...................................................................................................................... 60
9.4 Lighting ........................................................................................................................................... 62
9.5 Commissioning and energisation works ........................................................................................ 64
10. Fire Protection on Site ......................................................................................................................... 65
11. Demolition ........................................................................................................................................... 68
12. Earthworks ........................................................................................................................................... 72
12.1 Excavation, trenching and ground penetration ............................................................................. 72
12.2 Anchoring ....................................................................................................................................... 74
12.3 Piling Activities ............................................................................................................................... 76
13. Mobile Plant......................................................................................................................................... 78
13.1 Elevated Work Platforms (EWP)..................................................................................................... 82
13.2 Mobile Crane .................................................................................................................................. 84
13.3 Workbox / man box / flying loading bay ........................................................................................ 87
13.4 Suspended Swing Stage.................................................................................................................. 88
14. Temporary Fixed Plant ......................................................................................................................... 92
14.1 Gantry ............................................................................................................................................ 92
14.2 Scaffold........................................................................................................................................... 92
14.3 Tower Crane ................................................................................................................................... 97
14.4 Loading Bays................................................................................................................................... 99
14.5 Hoists............................................................................................................................................ 100
14.6 Mast Climber ................................................................................................................................ 101
15. Managing the Risk of Falls ................................................................................................................. 103
15.1 Penetrations and Openings .......................................................................................................... 103
15.2 Work at Heights ........................................................................................................................... 104
16. Temporary Support Structures .......................................................................................................... 109
16.1 Formwork ..................................................................................................................................... 109
Page 4
17. Concrete Structures ........................................................................................................................... 115 17.1 Concrete Pumping ........................................................................................................................ 115 17.2 Concrete Placement ..................................................................................................................... 118 17.3 Precast Panels .............................................................................................................................. 119 17.4 Tilt Up Panels ............................................................................................................................... 121 17.5 Masonry ....................................................................................................................................... 123 17.6 Post Tensioning ............................................................................................................................ 126 18. Structural Steel .................................................................................................................................. 129 18.1 Structural Steel Erection .............................................................................................................. 129 19. Emergency Response Scenarios ........................................................................................................ 130 19.1 Arrested Fall in a Harness............................................................................................................. 130 19.2 Asbestos Containing Material Discovery / Exposure.................................................................... 131 19.3 Biological Hazard Exposure .......................................................................................................... 132 19.4 Bomb Threat ................................................................................................................................ 133 19.5 Chemical Spill ............................................................................................................................... 134 19.6 Confined Space Rescue ................................................................................................................ 135 19.7 Contact with or Arching from Overhead Powerlines ................................................................... 137 19.8 Contact with Underground Services ............................................................................................ 138 19.9 Cyclone and High Winds............................................................................................................... 139 19.10 Electrical Incident ........................................................................................................................ 140 19.11 Elevating Work Platform Rescue ................................................................................................. 142 19.12 Explosion ..................................................................................................................................... 142 19.13 Fall from Heights ......................................................................................................................... 143 19.14 Fire .............................................................................................................................................. 144 19.15 Heat Related Illness ..................................................................................................................... 145 19.16 Lift Rescue ................................................................................................................................... 146 19.17 Medical Emergency ..................................................................................................................... 147 19.18 Plant Rollover and Collision......................................................................................................... 148 19.19 Power Loss .................................................................................................................................. 149 19.20 Roof Rescue ................................................................................................................................. 150 19.21 Site Evacuation ............................................................................................................................ 151 19.22 Structural Damage....................................................................................................................... 153 19.23 Temporary Support Collapse....................................................................................................... 154 19.24 Tilt-up or Precast Panel Event ..................................................................................................... 155
Page 5
19.25 Tower Crane Rescue .................................................................................................................... 156 19.26 Trench or Excavation Collapse .................................................................................................... 157 19.27 Wet Weather and Flooding ......................................................................................................... 158 19.28 Work Box Rescue......................................................................................................................... 159
Page 6
1. Introduction
1.1 Project Information
Project Details
Project Name: Ozcare Noosa RACF
Project Address 80 Cooyar Street, Noosa Heads, QLD, 4567
Project Number: TBA
Building Construction External Walls Material: Block, Metal Frame, Cladding
Internal Walls Material: Metal Frame, Plasterboard
Floors Material: Concrete, Ceramic Tile, Vinyl, Carpet
Ceilings Material: Plasterboard
Floor Areas Basement: N/A
Ground: 4560m2
Level 1: 2580m2
Neighbouring Facilities N/A
Remote / Isolated Project No
Start Date Approx. 06/2024
Completion Date -
Expected Completion Date Approx. 08/2027
Hours of Operation The construction works would generally be undertaken during standard
construction hours, being:
7:00 am to 6:30 pm Monday to Friday
7:00 am to 2:00 pm Saturdays
Non works on Sunday or Public Holidays
After hours contact details will be displayed on the Woollam site entry
banner located adjacent to the vehicle and/or pedestrian site access
point.
Project Hazard/Risk Assessment / Page 6 of 160
Page 7
1.2 Revision History
Amendments to the Project Hazard/Risk Register, including all relevant details will be recorded in the table
below.
Revision Date Amendments Reviewed By
001 07/03/2024 Document created. Cameron Stewart
(HSEQT Manager)
P1 23/04/24 Initial Draft Bryan Ward - PM
1.3 Site Specific Hazard/Risk Register Approval
This Project Hazard/Risk Register will be reviewed and approved by the Project Manager, Site Manager, Site
HSE Adviser, Regional HSE Coordinator and HSEQT Manager before it can be implemented.
Role Name Signature Date
HSEQT Manager: Cameron Stewart
Project Manager: Bryan Ward
Site Manager: TBA
Site HSE Adviser TBA
Regional HSE TBA
Coordinator:
Project Hazard/Risk Assessment / Page 7 of 160
Page 8
1.4 Definitions
Term Definition
Accident An unfortunate incident that happens unexpectedly and unintentionally, typically resulting
in damage or injury.
Dangerous Electrical The Electrical Safety Act QLD 2002 defines a Dangerous Electrical Event as:
Event
• whenever a person, for any reason, is electrically unsafe around high voltage
electrical equipment, even if the person does not receive an electric shock or
injury.
• significant property damage caused by electricity or something originating from
electricity (e.g., electrical fire).
• unlicensed electrical work.
• unsafe electrical work.
• unsafe electrical equipment or electrical equipment that does not have electrical
equipment safety system approval markings.
Emergency Any unplanned and unwanted event generated internally or externally, which has caused
or has the potential to cause significant harm to people, public or significant damage to
product, property, plant, equipment, the environment and / or the business and requires
an immediate response.
Emergency Assembly A place of safety outside of the building where persons evacuating the building, or the part
Point are expected to assemble under the building’s Emergency Preparedness and Response
Plan. This area is established to check that persons are accounted for (roll call), brief
persons evacuated on future action and to prevent re-entry.
Emergency Control A structured organization of persons to organize and supervise the safe movement of
Organization (ECO) personnel from the location in an emergency.
Emergency A document outlining the general procedures for preparing for potential emergency events
Preparedness and and initiating an emergency response.
Response Plan (EPARP)
Emergency Services The public organisations that respond to and deal with emergencies when they occur (i.e.
ambulance service, the police, and the fire brigade).
Evacuation Plan A plan developed and prominently displayed throughout the location indicating the
access/egress, and the main and alternative routes to the Emergency Assembly Point in
the event of an evacuation. The plan will also indicate the locations of the First Aid
Facilities and Fire Fighting Equipment.
Evacuation Route The designated route to the final place of safety. To always be maintained clear.
First Aid Officer The person responsible for attending to the medical needs of the injured person.
Incident An unplanned event related to a person resulting in or potential for injury/ill health or
other loss.
Rehabilitation The action of restoring someone to health or normal life through training and therapy
following injury or illness.
Project Hazard/Risk Assessment / Page 8 of 160
Page 9
Serious Electrical The Electrical Safety Act 2002 defines a Serious Electrical Incident as:
Incident
• is killed by electricity.
• receives a shock or injury from electricity and is treated for the shock or injury by
or under the supervision of a doctor.
• receives a shock or injury from electricity at high voltage, whether or not the
person is treated for the shock or injury by or under the supervision of a doctor.
Suitable Duties Plan Work duties for which a worker is suited, having regard to the nature of the worker's
incapacity and pre-injury employment according to relevant medical information.
Traffic Controller When assigned, is the person responsible for ensuring clear access to site for the
Emergency Services, meeting the Emergency Services at the nominated entry gate and
directing them to the emergency scene.
Competent Person Is a person that demonstrates an understanding of:
(Formwork) o the relevant Australian Standards, relevant codes of practice and other
relevant legislation,
o ability to read and interpret drawings under supervision.
o have general knowledge of the company risk management process for the
erecting, altering and dismantling of formwork, including: - hazard
identification and risk assessment - measures to control exposure to risks -
safe work practices and procedures - how to plan and prepare formwork.
A competent form worker needs to be under supervision from an appropriately
experienced Formwork supervisor as defined below
Competent Person workers who have completed the relevant module shown above will be permitted to
(Asbestos Removal) remove or supervise the removal of asbestos.
o CPCCDE3014A Remove non-friable asbestos.
o CPCCDE3015A Remove friable asbestos.
o CPCCBC4051A Supervise asbestos removal.
Competent Supervisor having a sound knowledge of relevant Australian Standards, relevant codes of practice and
(Formwork) other relevant legislation, ability to read and interpret drawings, sound knowledge of, and
competence in, the risk management process for the erecting, altering and dismantling of
formwork, including: - hazard identification and risk assessment - measures to control
exposure to risks - safe work practices and procedures - how to plan and prepare
formwork
RTO Registered Training Organization. Registered training organisations (RTOs) are providers
and assessors of nationally recognised training that have been registered by the Australian
Skills Quality Authority (ASQA)
Duty of Care (DOC) A statutory obligation. To ensure (as far reasonably practicable) the health and safety of
workers and all other persons; while the workers are at work in the business.
Code of Practice (COP) / Codes of Practice set out industry standards of conduct. They are guidelines for managing
Compliance Code exposure to risk and provide practice directions for a safe working environment.
High Risk Construction Defined in legislation as the following activities all require an accompanying safe work
Work (HRCW) method statement:
• Involves a risk of a person falling more than 2m.
• Is carried out on a telecommunication tower.
• Involves demolition of an element of a structure that is load bearing.
• Involves demolition of an element of a structure that is related to the physical
integrity of the structure.
• Involves, or is likely to involve, disturbing asbestos.
Project Hazard/Risk Assessment / Page 9 of 160
Page 10
• Involves structural alteration or repair that requires temporary support to prevent
collapse.
• Is carried out in or near a confined space.
• Is carried out in or near a shaft or trench deeper than 1.5 m or a tunnel.
• Involves the use of explosives.
• Is carried out on or near pressurised gas mains or piping.
• Is carried out on or near chemical, fuel or refrigerant lines.
• Is carried out on or near energised electrical installations or services.
• Is carried out in an area that may have a contaminated or flammable atmosphere.
• Involves tilt-up or precast concrete.
• Is carried out on, in or adjacent to a road, railway, shipping lane or other traffic
corridor in use by traffic other than pedestrians.
• Is carried out in an area of a workplace where there is any movement of powered
mobile plant.
• Is carried out in areas with artificial extremes of temperature.
• Is carried out in or near water or other liquid that involves a risk of drowning.
• Involves diving work
A 'person conducting a A legal term under harmonised WHS laws for individuals, businesses or organisations that
business or are conducting business. A person who performs work for a PCBU is considered a worker.
undertaking' (PCBU)
Personal Protective Clothing or equipment which, when used correctly, protects part or all of the body from
Equipment (PPE) identified risks of injury or disease in the workplace.
Safe Work Method A study carried out to ensure that hazards are identified, analysed, and properly controlled
Statement (SWMS) to minimise, or, if practicable, eliminate risks. High risk construction work SWMS must be
available at the point of use (either in hard copy or electronically) and approved by
Woollam before the commencement of high risk works.
Safety Data Sheet (SDS) Safety Data Sheets are documented information which clearly identifies a hazardous
substance and states the precautions to be taken for the safe use, storage and disposal of
the substance along with the health hazards and toxicity associated with the substance.
Must be available at the point of use (either in hard copy or electronically).
Corrective Action The action taken to remedy a non-conformance.
Consignee/s For the purpose of this plan, the term is used to describe the party responsible for the hire
of plant.
Non-Conformance Deviation from an approved procedure, legislated requirement or site rule.
Risk Potential event(s) resulting in an unintended outcome.
Code of Practice (COP) / Codes of Practice set out industry standards of conduct. They are guidelines for managing
Compliance Code exposure to risk and provide practice directions for a safe working environment.
Dangerous Occurrence A ‘Dangerous Occurrence’, often called a ‘near miss’, is an incident where no person is
injured, but which had the potential to cause serious injury, incapacity or death.
Duty of Care (DOC) A statutory obligation. To ensure (as far reasonably practicable) the health and safety of
workers and all other persons; while the workers are at work in the business.
Project Hazard/Risk Assessment / Page 10 of 160
Page 11
Effectiveness The extent to which planned activities are realised and planned results are achieved.
Contract Partner Subcontractor hired by the Principal Contractor Woollam
RPEQ Engineer Registered Professional Engineer of Queensland
Scaffolder A person who holds one of the following qualifications
• CPCCLSF2001 – Basic Scaffold
• CPCCLSF3001 – Intermediate Scaffold
• CPCCLSF4001 – Advanced Scaffold
Occupation Hygienist An occupational Hygienist that has completed required tertiary education and is a member
of AIOH (Australian Institute of Occupational Hygienists).
Operator protective A roll-over protective structure (ROPS), falling object protective structure (FOPS), operator
device restraining device or seat belt.
A competent person must be able to -
Competent Person
(Excavations)
• Ensure proposed excavation(s) has been marked for underground utility locating
and contact utility locating service.
• Know and understand utility locating services and their markings.
• Classifying the soil type
• Prescribe and ensure proper installation of protective system(s)
• Identify and correct all hazards, including those associated with confined spaces.
• Ensure employees are protected from the spoils, surface encumbrances, and all
other potential hazards surrounding the excavation.
• Ensure adequate access and egress.
• Ensure excavation is properly barricaded and protected from public.
• Ensure atmospheric monitoring is performed when necessary.
Geotechnical engineer Geotechnical engineer an engineer whose qualifications are acceptable for membership of
the Institution of Engineers Australia and who has qualifications and experience in soil
stability and mechanics and excavation work.
1.1 Risk Matrix
CONSEQUENCE LIKELIHOOD
The event Not expected
The event will The event is
may occur however the The event
probably expected to
Health & Safety Environment Quality Severity only in event may could occur
occur in most occur or has
exceptional occur at at some point
circumstances occurred
circumstances some point
Project Hazard/Risk Assessment / Page 11 of 160
Page 12
Almost
Rare Unlikely Possible Likely
Certain
Severe
Serious and damage to
Fatality irreversible Woollam
environmental reputation
Permanent harm with
Catastrophic Medium High High Extreme Extreme
Total Disability costs greater Loss greater
than $50,000 than
$200,000
Considerable
Significant /
damage to
extensive
Extensive Woollam
injury or illness
environmental reputation High Medium Medium High High Extreme
Permanent damage Loss of
Partial
$50,000 –
Disability
$199,999
Woollam
Serious injury brand
Minor
or illness reputation
resulting in
environmental Moderate Low Medium Medium High High
damage Loss of $5,001
lost time injury
– $49,999
Injury or Minor impact
illness to Woollam
Environmental reputation
requiring
nuisance
Low Low Low Medium Medium High
medical Loss of $501 –
treatment $5,000
Injury or No effect on
illness No Woollam
requiring environmental reputation Insignificant Low Low Low Medium Medium
minor first aid damage Loss less than
treatment $500
Risk Risk
Actions
Rating Tolerance
Unacceptable Controls are inadequate, task not to commence or continue until risk is reduced by changes to methodology and or
Extreme
Risk additional control measures have been approved by the operations support teams.
Unacceptable Controls may be inadequate, task not to commence or continue until risk is reduced by changes to methodology and or
High
Risk additional control measures agreed by Project Manager in consultation with Construction Team management.
Tolerable Existing controls are monitored for effectiveness and where additional controls to reduce risk are identified controls are
Medium
Risk to be implemented.
Accepted
Low Undertake the activity with existing controls and monitor effectiveness.
Risk
Project Hazard/Risk Assessment / Page 12 of 160
Page 13
2. Safety in Design Residual Risks
Summary of the key buildability risks identified in the design risk assessment/s that require consideration in the Risk Assessment, or link to the referenced
constructability risks to ensure risks adequately captured in this Project Risk Assessment.
Date of Reference of the SiD Document Summary of Risks to be assessed in this assessmen
Review
TBA – Awaiting SiD Registers from Consultants
Select the contract type for this project: Design & Construct
Refurbishment
Project Hazard/Ri
Page 14
2.1 Design and Construct Project
Proposed Controls
Hazard Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Worker health and HIGH 5 Consultation with all designers and consultants to ensure they are made aware that their design is to meet. Project Manager and
safety during the: • all legislative requirements and Designers and
• Construction • incorporate control measures to remove or reduce health and safety implications to an acceptable level. Consultants
• Use Design briefs need to consider the health and safety of persons.
• Maintenance and • during construction of the structure/equipment
• In the vicinity • when the structure /equipment has been constructed and is used by the end user.
Regular meetings are to be scheduled with designers/consultants to review and where possible close out actions/issues raised in the design
risk assessment.
Architects, designers, engineers, and those consultants responsible for design elements must provide the project team with a documented
design risk assessment addressing the issues described above.
Residual constructability risks to be outlined in the above table.
Where there are design changes the site team is to undertake a preliminary assessment and.
• Record yes or no on the project variation register to identify if the changes may impact on the site health and safety that involve
change in.
• New construction materials
• Construction processes
• Construction techniques previously used.
• Introduction of new hazardous materials
Amend or develop a new work method statement for the change being made.
Where YES has been recorded on the variation register the site team is to undertake a design changes assessment
Results of the design change risk assessment are to be communicated to the relevant Contract Partner’s or employees and involve a toolbox
talk to inform the relevant workers
Project Hazard/Risk Assessment / Page 14 of 160
Page 15
3. Working in a Client’s Workplace
Adjust this section to suit your project and the client requirements for the below – all left intentionally blank to incorporate the project specific requirements where they exist.
Hazard Proposed Controls Responsible Person
Risk
Risk
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
HOC
Residual
3.1 Refurbishment works in a live environment
Add project specific requirements associated with the isolation and impairment of client’s fire protection systems during
construction
Striking live services (gas, HIGH 5 Identification of service isolation points prior to commencement of works and communicated to the project. Site Management
electrical etc.) Live service isolation points to be identified and communicated. Contract Partner’s
Task specific controls to be established in the relevant SWMS
Coordination of site works HIGH 5 Emergency Preparedness and Response Plan to be collated to address: Project Manager
with other contractors, client Site Manager
• Access and egress
contractors or the clients’
operations. • Evacuation processes
• Communication protocols
Failure to understand project HIGH 5 Consultation will be undertaken with the client with the objective of identifying specific hazards and issues relating to the Project Manager
hazards project which the client is aware of. Site Manager
3.2Use of client safety systems
Controls required ** information requested prior to commencement on site // clients permit systems to be established prior
to commencement on site // our permit clients permit to isolate.
Client required induction processes.
e.g. communications and time restrictions on noisy work requirements
Incorrect use of client MEDIUM 5 • Implementation of client systems requirements on the project include: Site Management
required systems
• Inductions
• Specific site rules
• Emergency procedures
• Additional personal protective equipment
• Client Permits to work process will be implemented as agreed the requirements for use communicated to all personnel
and complied with (as applicable).
Project Hazard/Risk Assessment / Page 15 of 160
Page 16
Hazard Proposed Controls Responsible Person
Risk
Risk
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
HOC
Residual
• Fire Impairment Notices
3.3Stakeholder required exclusion zones
Control required: e.g. rail corridor – 10m from outside of track etc. CASA flight restrictions
3.4 Access
e.g. Shared access requirements / Restricted access/delivery times
Slips, trips, falls HIGH 4 Public areas will be kept clear of any debris, trip or slip hazards and protected from any projectiles, dust etc. that may be Project Manager
released as a product of work undertaken. Site Manager
Project Hazard/Risk Assessment / Page 16 of 160
Page 17
4. Environmental Assessment
Proposed Controls
Risk
Risk
HOC
Aspect Risk Responsible Person
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Environmental Harm HIGH 5 Erosion and Sediment Control Plan (ESCP) to be designed by suitably qualified person. M Site Management
☑ Natural form sediment in Installation and maintenance of ESCP devices as per plan to be implemented and monitored as per
waterways, waterways instruction from suitably qualified person.
stormwater, or
overland flow Complete regular inspections on sediment and erosion plan and in consultation with the plan owner to
adjust the sediment and erosion controls as the site changes
Failure to implement HIGH 3 Implementation of required controls on site with monitoring of implementation completed through the M Site Management
adequate controls Weekly Inspection or as required in the engineer notes.
Sediment tracked off HIGH 5 • Vehicles to be inspected prior to leaving site for excessive soil/mud on tyres. M Site Management
site Contract Partner’s
• Sediment traps to be installed on stormwater inlets. Stockpiles need to be managed to ensure run
off does not leave site and enter stormwater and stockpiles need to be located away from land
overflow paths
Sediment tracked off HIGH 4 All road/ kerb and channel environmental devices to be maintained and cleaned during construction. If M Site Management
site required street sweeper to clean roads of sediment from travel paths of trucks and vehicles Contract Partner
Contamination of EXTREME 4 Separate washout areas for: M Site Management
waterways by • Paint Project Management
incorrect site washout
facilities • Plaster
• Concrete
• General
Contamination of EXTREME 1 Washout for paint and plaster are not to be connected to sewer or disposed of in stormwater. L Site Management
waterways by Paint and plaster wash out to be maintained to ensure effective containment.
incorrect site washout
facilities
Protected flora and HIGH 5 Prior to commencement of works all protection zones to be identified and established as per the DA M Site Management
☑ Work in fauna adversely requirements. Where required monitoring of flora / fauna is to occur, and records maintained.
environmentally impacted Any observed native animals or pest on site are to be managed by a licenced animal catcher
sensitive areas
Pollution of HIGH 5 Where practical, waste to be segregated into recycling materials and bins clearly mark to identify each M Site Management
☑ Waste surrounding areas bin type. Project Management
Management Plan
Waste tracking certificates for traceable waste to be completed by licence contractors
Project Hazard/Risk Assessment / Page 17 of 160
Page 18
Proposed Controls
Risk
Risk
HOC
Aspect Risk Responsible Person
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Nuisance dust HIGH 3 Work areas and trafficable areas are to be dampened down for dust suppression. L Site Management
☑ Dust controls
Water to be used with plant and equipment generating dust Contract Partner
Nuisance dust HIGH 3 Vacuums to be used with equipment in alignment with relevant safe work method statements L Site Management
Contract Partner’s
Nuisance dust HIGH 5 Limit dust generating activities during high winds where possible L Site Management
Contract Partner
Non-compliance with HIGH 5 • Site operations between 7:00am and 6:30pm Monday to Saturday (or as per DA/BA requirements) L Site Management
☑ Noise DA conditions
management • Where out of hours works are required application and approval from local council to be obtained.
• Noise Management Plan implemented as required.
• Site planning and positioning of noisy plant and equipment to be considered prior to
commencement on site (including but not limited to crane selection).
• Planning of the works with potential to create excessive noise/vibration.
• Reduced hours for rock breaking activities to reduce impact to neighbours.
• Place machinery away from noise sensitive areas where possible
Environmental harm N/A 5 Implementation of Acid Sulphate Management Plan with required controls. N/A Project Management
☒ Acid Sulphate Soils from run off or Site Management
Per initial
incorrect disposal of
Geotech
spoil
Damage to property HIGH 5 Vibration management process to be implemented in areas with a high risk of damage to surrounding M Site Management
☑ Works near other during earthworks buildings. Vibration monitoring devices to be installed where possible issues are identified. Contract Partner
buildings or historical
buildings Damage to property EXTREME 3 • Screening installed in accordance with demolition/staging plans. M Site Management
during demolition Contract Partner
• Initial hand demolition to assist in some areas where stages are too close to each other for machine
demolition.
Introduction of fire EXTREME 5 Project is not located in a Fire Ant Zone L Site Management
☒ Fire ant zone ants into new areas Imported fill to be from within local area HSE Advisor with
Implementation of Fire Ant Environmental Work Method statement and required controls. BSBWHS414 OHS Cert
4 / Manager
Failure to identify fire N/A 5 1 x member of the Site Management Team to complete Fire Ant Awareness Training and display the N/A Site Management
ants and respond certificate in the site office
Project Hazard/Risk Assessment / Page 18 of 160
Page 19
Proposed Controls
Risk
Risk
HOC
Aspect Risk Responsible Person
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Non-compliance with N/A 5 Identify if any part of the works involves aspects which are heritage listed. (Researching of cultural N/A Project Management
☒ Cultural / Heritage DA conditions and/or heritage items should be conducted a tender stage). Ensure all necessary approvals and/or
considerations (DA Nil on site.
permits are in place before any construction work begins.
requirements)
Incorrect storage of HIGH 3 Sewerage generated from site to be connected to sewer or sewer tank. M Site Management
☑ Land liquid waste Sewer tank to be disposed of by licenced contractor. HSE Advisor with
Contamination
BSBWHS414 OHS Cert
4
Contract Partner
Injury / damage to HIGH 3 Injured native Fauna shell be taken to the nearest native animal hospital / refuge. A specialist animal M Site Management
☑ Habitats flora / fauna handling group such as WIRES should be called if difficult to handle or dangerous animals are HSE Advisor with
(Protected Flora / encountered. BSBWHS414 OHS Cert
Fauna)
4
HIGH 3 Workers to be instructed not to disturb or injure any native Fauna which may be present onsite M Site Management
HSE Advisor with
BSBWHS414 OHS Cert
4
Contract Partner
HIGH 3 Minimise removal of vegetation L Site Management
HSE Advisor with
BSBWHS414 OHS Cert
4
Contract Partner
HIGH 3 Vehicles and equipment where there is a risk of pest infestation should be cleared prior to M Site Management
entering/exiting site. HSE Advisor with
BSBWHS414 OHS Cert
4
HIGH 3 Re-instate the work area to its previous condition including the laying of turf or grass seeding as L Site Management
required. HSE Advisor with
BSBWHS414 OHS Cert
4
Review / Monitoring HIGH 5 Safety Interactions, Task Observations, Weekly HSE Inspection, Monthly Auditing in line with Procore M Site Management
Inspection Matrix
Project Hazard/Risk Assessment / Page 19 of 160
Page 20
5. Public Protection Controls and Traffic Management
Proposed Controls
Activity Hazard Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Implementation Unauthorised access HIGH 1 • Temporary fencing will be erected as per manufacturers / suppliers’ specifications. M Site Management
• Gates to be locked at all times after hours.
• Site amenities (Site Office and Lunchroom) are locked each day.
• All building entry point to be secured and locked at the conclusion of each day.
Unauthorised road / HIGH 5 Written approval will be obtained from the relevant authority to close adjoining areas when excluding members L Site Management
footpath closures of the public.
Any controls imposed by the authority will be fully implemented and monitored during the project.
Injuries to the public HIGH 3 Hoardings erected on site will: M Project Management
• be able to withstand a horizontal force of- Site Management
2 2
– 500 N/m applied over 1m at the top of the hoarding midway between any two posts without
deforming permanently &
– 950 N/m2 applied over 1500mm2 at any point on the hoarding without fully penetrating the hoarding.
• only have small gaps that are necessary to minimize wind resistance; and
• extend to the gantry’s overhead platform (if it is part of a gantry).
Injuries to the public HIGH 5 During installation, extension or reduction of catch platforms or screening, appropriate measures (i.e. such as M Site Management
closing the adjoining area) will be taken to ensure that a falling object cannot injure a member of the public in Contract Partner
the adjoining area.
Falling objects HIGH 3 For QLD Around the perimeter of the site based on the angle made between: M Project Management
• the horizontal and Site Management
• an imaginary line drawn between the closest point where the public have access, to the highest point on HSE Advisor with
the building/structure where work is to be done: BSBWHS414 OHS Cert
4
The fencing will be:
• (< 15o) ☐ barricade or hoarding at least 900mm high.
• (15o – 30o) ☐ A hoarding at least 1800mm high.
• (30o – 75o) ☐ a hoarding at least 1800mm high that is fully sheeted with timber, plywood, metal, or
sturdy synthetic sheets.
• (75o or more) ☐ a hoarding at least 1800mm high that is fully sheeted with timber, plywood, metal, or
sturdy synthetic sheets, AND one of the following:
– a gantry (or overhead protective structure), (incorporating the hoarding), or
Project Hazard/Risk Assessment / Page 20 of 160
Page 21
Proposed Controls
Activity Hazard Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
– the adjoining area is closed to prevent Falling objects on or otherwise hitting members of the public in
that area; or
– a catch platform with vertical sheeting or perimeter containment sheeting is installed.
Falling objects N/A 3 For NSW Where work is carried out at a height exceeding 4m above the lowest ground level of the adjoining N/A Project Management
Is a public place the following will be implemented: Site Management
QLD • a hoarding at least 1800mm high that is fully sheeted with timber, plywood, metal or sturdy synthetic \ HSE Advisor with
project. sheets, AND one of the following controls: BSBWHS414 OHS Cert
• a gantry (or overhead protective structure), (incorporating the hoarding), or 4
• the adjoining area is closed to prevent falling objects on or otherwise hitting members of the public in that
area; or
• a catch platform with vertical sheeting or perimeter containment sheeting is installed.
Unless the ratio of the horizontal distance to the vertical height between the nearest boundary of the public
place and the where the work is carried out exceeds 2, in which case the requirements as per for QLD (above)
will be implemented.
Falling objects HIGH 4 Vertical containment sheeting and perimeter containment screening will be used and installed not more than M Site Management
1m below the height at which an object could fall from a surface or storey to an area below. The screens will be
capable of preventing an object that may reasonably be expected to hit it when falling from the level on which
work is being done.
Inadvertent access HIGH 5 “Construction Site – No Unauthorised Entry” signs will be used to clearly identify areas on and around the M Site Management
perimeter of sites as being a place of work.
Slips, trips and falls HIGH 5 Public areas will be kept clear of any debris, trip or slip hazards and protected from any projectiles, dust etc. that M Site Management
may be released as a product of work undertaken (e.g. shared footpaths etc).
5.1 Traffic Management
Planning Traffic management HIGH 5 Where work is undertaken that requires the closure of footpaths and roads, specific risk assessments, M Site Management
incorrectly employment of traffic controllers and the preparation of traffic management plans will be undertaken in HSE Advisor with
implemented accordance with statutory requirements and to suit the environment and method of work, which is required. BSBWHS414 OHS Cert
4
Interactions with HIGH 5 A traffic management plan / traffic guidance scheme will be developed by suitably qualified person as required M Site Management
members of the by legislation and include risk assessments, traffic controllers’ details and specific road barricading and signage Project Management
public will be prepared and implemented prior to work commencing on a road or footpath.
Where construction activities require that vehicular traffic be impeded, or footpath closures are required a
Traffic Management Plan will be developed by a qualified person in accordance with the Manual of Uniform
Traffic Control Devices.
Project Hazard/Risk Assessment / Page 21 of 160
Page 22
Proposed Controls
Activity Hazard Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Plant and people HIGH 5 The TMP/TGS will consider the co-ordination of site plant/pedestrians and members of the public. M Site Management
interactions Contract Partner
Activity planning and HIGH 5 All tasks involving Traffic & Roadway Management will have an approved SWMS in place. M Site Management
hazard identification Contract Partner
Training and HIGH 5 Suitably licenced Traffic Controllers to be engaged to perform traffic control tasks in alignment with Minimum M Site Management
licensing Licencing Guidelines. Licences are to be sighted and recorded at induction. Contract Partner
Construction works Vehicle interactions HIGH 5 Where the drivers of vehicles, trucks and plant are required to reverse into the site across public footpaths and M Site Management
with members of the walkways the following is to be implemented:
public - Erect a sign at the entry gates directing drivers to contact the Site Manager/Foreman before entering site –
provide phone numbers.
- Email suppliers and Contract Partners to advise them of the health and safety protocol to be followed for plant
& vehicle movements onto the site.
- Where there are members of the public using the footpath or walkways provide a spotter or mechanical aids to
control their movements during the reversing process.
- The reversing vehicle, plant, and trucks from the street to be controlled as per the traffic management plan for
the project
Interactions with HIGH 3 Where the altered roadway/path cannot be controlled using safety barriers and signage alone, traffic controllers M Site Management
members of the will be provided to direct vehicles and pedestrians. Contract Partner
public
Failure to correctly HIGH 5 Signs and devices will be erected and displayed before work commences. Signs and devices will be removed M Site Management
identify construction from a work site only after all work is completed and as soon as practicable after completion of the work each Contract Partner
work zones day.
Traffic devices not HIGH 5 A detailed daily diary/log will be maintained for all actions taken by a traffic controller on site which includes M Site Management
implemented during details of signage and traffic control setup daily and time of control set up, modifications or controls removal, Contract Partner
altered traffic hours of operation and surface condition of the road.
conditions Periodic inspection is completed to ensure devices are in place as per TGS and free of damage and vandalism.
Worker safety in low HIGH 6 Additional reflective helmet, vest, leggings, and light baton will be worn and used for night works as per MUTCD. M Site Management
light conditions Contract Partner
Worker safety in low HIGH 4 Night lighting will be provided for night works to ensure traffic controllers are visible to oncoming traffic. M Site Manager
light conditions
Road conditions HIGH 2 Consideration will be given to conducting work out of peak times. M Project Management
Site Management
Project Hazard/Risk Assessment / Page 22 of 160
Page 23
Proposed Controls
Activity Hazard Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Accurate recording HIGH 5 In the case of any incident, the type, size, location and arrangement of signs and devices, weather conditions M Site Management
of traffic related and conditions of travel path will be recorded and photographed.
incidents
Failure to comply HIGH 5 Traffic control PPE and vests to be as per relevant state/territories legislation. M Site Management
with legislative
requirements
Project Hazard/Risk Assessment / Page 23 of 160
Page 24
6. Site Facilities
6.1 Site Requirements
Project Stage Initial set up 3 months 6 months 9 months 12 months 15 months
Average number of workers on site 10 [XX] [XX] [XX] [XX] [XX]
Amenities Number of male toilets [XX] [XX] [XX] [XX] [XX] [XX]
- Closet pans 1 per 20
Number of urinals [XX] [XX] [XX] [XX] [XX] [XX]
- 1 urinal space per 25 workers
Number of female toilets and sanitary facilities [XX] [XX] [XX] [XX] [XX] [XX]
- Closet pans 1 per 15 workers with sanitary
provisions
Crib Room Floor space [XX] [XX] [XX] [XX] [XX] [XX]
- 1m2 per person
Tables [XX] [XX] [XX] [XX] [XX] [XX]
Chairs [XX] [XX] [XX] [XX] [XX] [XX]
Water bubblers [XX] [XX] [XX] [XX] [XX] [XX]
Water Bubblers
- IP33 rated coolers for outdoor locations
Proposed Controls
Activity Hazard Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Planning and site Inadequate first aid HIGH 5 Review the maximum number of workers to be working on site over an 8 -10 hour period and assess First Aid Kit L Site Management
establishment equipment / facilities requirements for construction work.
More than 25 up to 50 persons at the workplace – 1 x Main Kit
Project Hazard/Risk Assessment / Page 24 of 160
Page 25
Proposed Controls
Activity Hazard Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
More than 50 up to 150 persons at the workplace – 1 x High Risk First Aid Kit and 1x Transportable High Risk First Aid
Kit
More than 150 up to 200 persons at the workplace – 2 x High Risk First Aid Kit A and 2 x Transportable High Risk First
Aid Kit
The first aid kit will be stocked appropriately for the number of workers onsite and the type of work being undertaken on
a weekly basis as per Woollam Weekly Inspection Checklist.
All first aid equipment will be maintained in a hygienic, safe, and serviceable condition
Inadequate first aid HIGH 5 A first aid room will be provided where it is assessed that the treatment for workplace injuries or illness would be more M Site Management
equipment / facilities effective with the provision of a first aid room, and in alignment with the relevant state / territory regulations and COP.
- ☐ QLD / NSW / NT / TAS - construction sites >100 workers or as the project requires
- ☐ VIC
- ☐ ACT – Construction site with > 25 employees
- ☐ Other:
Incorrect number of HIGH 5 First aid officers will be trained with a minimum First Aid qualifications and current CPR certifications relevant to the M Site Management
trained first aiders on jurisdiction of the workplace – Refer Minimum Licencing Guidelines.
site A minimum of one First Aid Officer will always be available onsite.
First aid certifications to be accessible and or displayed on the project.
Contract Partners are required to provide workers with necessary first aid qualifications to ensure adequate number of
first aid trained personnel are available on the project
Significant distance HIGH 5 Remote workplaces with limited access to emergency services (Hospitals / Medical Centres / Ambulance) will: L Site Management
from medical centres/ - Provide 1 x First Aid trained person in remote Situations: and
hospitals / ambulance
services - Provide 1 x First Aid person for every additional 25 workers.
- Have Contract Partner’s provide workers with First Aid certifications to ensure adequate number of First Aid trained
personnel are available on the project
First aid facilities not HIGH 5 First aid signs will be displayed on the outside wall/door of a site shed or room containing a first aid kit, erected at least L Site Management
identifiable 2m above the floor.
Workers not aware of HIGH 5 Emergency contact names, numbers, and address of the nearest medical centre (including a sketch-map of its location) L Site Management
who is a trained first aid will be displayed onsite and form part of the workplace specific induction.
officer - In site office
- In lunchroom
- In First Aid Room
- The First Aid Officer will have their identity displayed at the workplace and referred to during workplace specific
inductions.
Project Hazard/Risk Assessment / Page 25 of 160
Page 26
Activity Hazards Proposed Controls Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Planning for works Activity planning HIGH 5 Prior to the commencement of works that generate or agitate Respirable or Crystalline Silica Dust (RCS), an approved Site Management Contract
involving RCS and hazard SWMS with suitable controls is to be provided to the site team. Partner
identification HSE Advisor
Worker exposure HIGH 5 RCS work processes should be done outdoors away from other workers where possible. Site Management Contract
Partner
Indoors, separate the RCS work processes from other work activities where possible. HSE Advisor
Worker and visitor HIGH 4 Dedicated areas with barricades and signage are to be established where cutting, drilling, grinding, mixing and scraping Site Management Contract
exposure RCS is likely to be generated or agitated. Partner
These dedicated areas are to be:
- Segregated from other work areas & amenities.
- Mechanical ventilation and approved filtration
- With a bin near to dispose of waste
Worker Exposure HIGH 4 - Plan PPE as per MPF requirements identified in RCS COP.
Project Hazard/Risk Assessment / Page 50 of 160
Page 27
Activity Hazards Proposed Controls Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Drilling, grinding, Worker and visitor HIGH 3 Where practical an engineered control is to be implemented to reduce or eliminate as far as reasonably practicable Site Management Contract
grinding, mixing, exposure RCS dust exposure to the acceptable national exposure limit. These controls include: Partner
scraping of RCS - Extraction / vacuums
materials
- Tool attachments (shrouds / drill pieces etc.)
- Misting / water application
- Prefabrication / modifications off site
- Cast in components or block outs to reduce agitation of RCS.
- Accurate site measures to eliminate the requirement for cuts or alterations.
Worker exposure EXTREME 6 Those personnel involved in cutting, drilling, grinding, mixing, scraping where an exposure to dust exists must wear Site Management Contract
to RCS suitable Respiratory Protective Equipment for the task and receive adequate training in its use and application. Partner
Worker exposure EXTREME 2 Alternative materials with no or reduce silica amounts to be used. Site Management Contract
to RCS Partner
General cleaning Worker and visitor EXTREME General Cleaning activities that may expose a worker to RCS Avoid blowing, areas: Site Management Contract
exposure Partner
- suitable vacuum / extraction method to be utilised where practical.
- dust to be bagged in vacuum cleaner.
- When emptying vacuum ensure contents are not emptied from the bag directly into the bin
- Misting/water application when emptying site bins.
NOTE – suitable Respiratory Protective Equipment is still required to be worn when vacuuming.
- If vacuum is not practical, then another means of dust suppression (e.g. water) is to be applied to the area.
- Dust cleaned up and stockpiled for removal is to be enclosed in sealed plastic prior to placing in bin
RCS levels EXTREME 5 The workplace exposure limit shall be in accordance with the national exposure guidelines for RCS. Site Management Contract
exceeding national Partner
exposure
guidelines
Worker exposure EXTREME 5 General Dust management refer to Environmental Management Plan Site Management Contract
to RCS Partner
- Prior to overturning bins to empty, apply a light mist over the contents to reduce the risk of agitation.
- No bins are to be overturned in enclosed areas
Health monitoring Health impacts EXTREME 5 Where Woollam direct employees are undertaking activities exposing them to hazardous substances health Site Management Contract
surveillance / monitoring as required by relevant legislation will be undertaken, or those identified as significant risk to Partner
a worker’s health through the Hazardous Substance Risk Assessment. Procedure is outlined in the Woollam Health HSE Advisor with
Monitoring Program. BSBWHS414 OHS Cert 4
Occupation Hygienist.
Project Hazard/Risk Assessment / Page 51 of 160
Page 28
Activity Hazards Proposed Controls Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Health impacts EXTREME 5 Health surveillance / monitoring information / reports will be provided to workers. Site Management Contract
Partner
HSE Advisor with
BSBWHS414 OHS Cert 4
Occupation Hygienist.
Health impacts EXTREME 5 Actions will be taken based on the results of the health surveillance / monitoring. And the recommendation of a Site Management Contract
medical professional and or Occupation Hygienist. Partner
HSE Advisor with
BSBWHS414 OHS Cert 4
Occupation Hygienist.
Health impacts Extreme 5 RPE Usage Record to be completed prior to any work possibly exposing a worker to RCS any more than 30 days with Site Management Contract
365 days recorded will trigger health monitoring. Partner
HSE Advisor with
BSBWHS414 OHS Cert 4
8.4 Medium Density Fibreboard (MDF)
Planning works Dust exposure. EXTREME 2 Use alternative material in place of MDF. Site Management Contract
Partner
Health impacts
Dust exposure. EXTREME 1 Where an alternative is not available, cut MDF offsite. Site Management Contract
Partner
Health impacts
Dust exposure. EXTREME 5 Prior to works that generate MDF dust airborne dust an approved SWMS with suitable controls is to be in place and Site Management Contract
communicated to all workers involved with the task generating MDF dust. Partner
Health impacts
Dust exposure. EXTREME 5 Identify materials to be installed with MDF. Where a task has been identified with MDF with a risk to exposure of Site Management Contract
airborne MDF dust, all PCBU are to review their relevant SWMS and ensure all controls are in place. Partner
Health impacts
Works with MDF Dust exposure. EXTREME 4 Cut, drill, or agitate MDF in dedicated cutting room where airborne MDF is generated or agitated. Site Management Contract
Partner
Health impacts The dedicated cutting room is to be:
- Excluded from other workers not involved in the task and communicated to all workers.
- Signage for the exclusion zone.
- Be completely sealed with no openings.
- Door on entrance which remains closed.
Project Hazard/Risk Assessment / Page 52 of 160
Page 29
Activity Hazards Proposed Controls Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Dust exposure. EXTREME 3 Where practical an engineered control is to be implemented to reduce or eliminate as far as reasonably practicable MDF Site Management Contract
dust exposure to the acceptable national exposure limit. These controls include: Partner
Health impacts
- Extraction / vacuums
- Tool attachments (shrouds / drill pieces etc.)
- Air scrubbers/mechanical extraction.
Dust exposure. EXTREME 6 Those personnel involved in cutting, drilling, planning where an exposure to dust exists must wear suitable respiratory Site Management Contract
protective equipment for the task and receive adequate training in its use and application. Partner
Health impacts
All Personnel are to wear eye protection PPE.
Dust exposure. EXTREME 5 Cutting room cleaning activities that may expose a worker: Site Management Contract
Partner
Health impacts - Avoid blowing, areas.
- Suitable vacuum/extraction method to be utilised.
- Room to be cleaned regularly daily.
- Room to be cleaned prior to other workers entering the room.
- Disposal of dust to be bagged.
- Promote good personnel hygiene.
Dust exposure. EXTREME 5 Predrill holes in MDF material in cutting room. Site Management Contract
Partner
Health impacts
Dust exposure. EXTREME 5 All personnel are to be managed to ensure no personnel exceed national exposure limit for formaldehyde. Site Management Contract
Partner
Health impacts
8.5 Hazardous Chemicals (as defined under Schedule 14 WHS Reg 2011)
Planning and training Activity planning MEDIUM 5 All tasks involving Hazardous Substances / Dangerous Goods will have an approved SWMS in place which addresses the Site Management Contract
and hazard activity and task hazards. Partner
identification
Project Hazard/Risk Assessment / Page 53 of 160
Page 30
Activity Hazards Proposed Controls Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Failure to identify MEDIUM 5 A register and SDS’s of hazardous materials to be used on site will be in a readily accessible position to any worker on Site Management Contract
chemical site. Partner
information SDS dated within the last five (5) years will be provided as part of SWMS and a copy kept with the product on site.
Hazardous Chemicals as Defined under Schedule 14 WHS Reg 2011 -
o Acrylonitrile
o Arsenic
o Asbestos
o Benzene
o Cadmium
o Chromium
o Creosote
o Crystalline Silica
o Isocyanates
o Lead
o Mercury
o MOCA
o Organophosphate pesticides
o Pentachlorophenol (PCP)
o Polycyclic aromatic hydrocarbons (PAH)
o Thallium
o Vinyl Chloride
Failure to identify MEDIUM 5 Risk assessments for each substance (and its uses) will be carried out prior to the hazardous substances / dangerous Site Management Contract
chemical goods being brought/used onto site. Partner
information
Workers not MEDIUM 5 Personnel will be trained in the hazards associated with the hazardous substances / dangerous goods, the risk Site Management Contract
trained / licenced assessment and the correct use and maintenance of PPE. A signed training record will be recorded on Woollam Connect Partner
in the activity
Workers not MEDIUM 5 Details of instruction, training, and supervisory requirements for the use of the hazardous substances / dangerous goods Site Management Contract
trained / licenced may form part of SWMS. Training is also provided on Woollam Connect Partner
in the activity
Use Compatible MEDIUM 5 All containers and storage areas in which hazardous substances / dangerous goods are stored will be appropriately Site Management Contract
storage labelled. Partner
Explosion
Absorption or MEDIUM 6 Employers shall ensure necessary personal protective equipment (PPE) will be provided for use with the hazardous Site Management Contract
contact with substances / dangerous goods in accordance with the SDS and SWMS. Partner
products
Project Hazard/Risk Assessment / Page 54 of 160
Page 31
Activity Hazards Proposed Controls Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Explosion MEDIUM 5 A fire extinguisher provided to any area where a hazardous substance / dangerous goods shows a significant fire risk Site Management Contract
whilst stored or in use. Partner
Responding to an Inadequate MEDIUM 5 An emergency plan developed for any significant risks associated with any hazardous substances / dangerous goods to Site Management Contract
emergency emergency be incorporated in the site Emergency Preparedness and Response Plan. Partner
response
Storage Compatible MEDIUM 3 All hazardous substances and dangerous goods will be safely stored in accordance with SWMS Hazardous chemicals and Site Management Contract
storage dangerous goods. Partner
Environmental MEDIUM 5 Controls will be implemented to prevent contamination of the workplace and amenities – hazardous substance or Site Management Contract
contamination Dangerous goods are not to be stored within these areas Partner
Health monitoring Health impacts EXTREME 5 Where Woollam direct employees are undertaking activities exposing them to hazardous substances health surveillance Site Management Contract
/ monitoring as required by relevant legislation will be undertaken, or those identified as significant risk to a worker’s Partner
health through the Hazardous Substance Risk Assessment. Procedure is outlined in the Woollam 0011- Health HSE Advisor with
Monitoring Program. BSBWHS414 OHS Cert 4
Occupation Hygienist.
Health impacts EXTREME 5 Health surveillance / monitoring information / reports will be provided to workers. Site Management Contract
Partner
HSE Advisor with
BSBWHS414 OHS Cert 4
Occupation Hygienist.
Health impacts EXTREME 5 Actions will be taken based on the results of the health surveillance / monitoring. And the recommendation of a medical Site Management Contract
professional and or Occupation Hygienist. Partner
HSE Advisor with
BSBWHS414 OHS Cert 4
Occupation Hygienist.
Reference WHS Act 2011 Schedule 14, Managing Hazardous Substances COP, Managing RCS Code of Practice.
Review / Monitoring Safety Interactions, Task Observations, SWMS Review Weekly HSE Inspection as per Procore Inspection Matrix
Project Hazard/Risk Assessment / Page 55 of 160
Page 32
9. Electrical
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Planning Unlicenced electrical work EXTREME 5 Only suitably licenced electrical contractors to undertake electrical work. Site Management
Electrical Contractor
Electrical licences to be checked at induction and copies of electrical licences retained Procore.
9.1 Temporary Power
Planning Inadequate planning HIGH 5 A plan/register of distribution board location and supply requirements are to be retained in the project site office and Site Management
with the electrical contractor. Electrical Contractor
Inability to identify the board HIGH 5 Where there is more than one switch board on site, marking shall be provided, by means of numbers, letters, or both, Electrical Contractor
for isolation purposes to identify each individual switchboard.
Inability to isolate the board EXTREME 5 Every switchboard or part of a switchboard that is supplied form a separate source of supply is to be clearly marked to Site Management
identify the source form which the supply originates. Electrical Contractor
Suitable access to power HIGH 5 Switchboards will have at least 1m clearance provided in front of the switchboard. Site Management
boards Electrical Contractor
Incorrect use of electrical EXTREME 4 In multi-level buildings distribution boards will be positioned in a manner which eliminates the need for electrical leads Site Management
equipment to be run between levels or in accordance with Table 1 in section 2.6.7 AS/NZS 3012 - Electrical Installations - Contract Partner
Construction
Damage to electrical EXTREME 4 Wiring and electricals circuits (including overhead installations) will be positioned to avoid crossing roadways or access Site Management
installations resulting in power ways where cranes, high loads or heavy machinery may travel. Electrical Contractor
loss or injury.
Damage to electrical EXTREME 5 Risk assessment should be undertaken prior to the installation of cables or whenever a change occurs, as to the Site Management
installations resulting in power likelihood of the cables being exposed to mechanical damage – as per AS 3012 – 2.5.2 protection against mechanical Electrical Contractor
loss or injury. damage
Inadequate planning EXTREME 5 Power points installed inside relocatable premises will only be used to supply power to electrical equipment and Site Management
lighting within that relocatable premise.
Workers electrocuted / EXTREME 4 All generators connected as site supply to the main switchboard of a construction site are to be installed in accordance Site Management
shocked with AS 3010 and the manufacturers requirements with Records of all testing to be retained on site and provided to Electrical Contract
Woollam. Partner
Workers electrocuted / EXTREME 4 Portable generators supplying electrical equipment by plug and socket outlet on the generator set is not required to Site Management
shocked have an earth electrode connected as per AS/NZS 3012 Contract Partner
Non-compliant installation EXTREME 5 A contract partner supplied Temporary Electrical Board Checklist to be completed prior to handover and submitted to Site Management
Woollam. Records of all testing to be retained on site and provided to Woollam. Contract Partner
Project Hazard/Risk Assessment / Page 56 of 160
Page 33
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Installation of Faulty wiring EXTREME 5 All temporary construction electrical installations will be installed and maintained in accordance with AS/NZS 3012 Site Management
temporary Electrical Contractor
electrical circuits Faulty electrical installations EXTREME 4 RCDs will be supplied to all circuits in switchboards and will be tested monthly by a push button test and every 3 Site Management
months by a person holding an Electrical Practitioner Licence. Records of all testing to be retained on site and provided Electrical Contractor
to Woollam.
Faulty electrical equipment HIGH 3 Daily RCD push button test by user is to be completed for all PSOA (portable socket outlet assemblies) on site. User
Workers electrocuted / EXTREME 4 Construction wiring will not be tied, bundled or grouped with permanent wiring. Site Management
shocked. Contract Partner
It will be readily distinguishable from permanent wiring by using cable of a different colour (except green), or by
Faulty installation attaching iridescent yellow tape at intervals of not more than five (5) metres and stamped with the words
“Construction Wiring.”
Faulty installation EXTREME 5 Switchboards must be: Site Management
Contract Partner
- readily accessible, protected from damage and located within the site perimeter; and
- singularly identifiable through either numbering, lettering, or a combination of the two.
Project Hazard/Risk Assessment / Page 57 of 160
Page 34
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Workers electrocuted / EXTREME 5 Switchboards must be constructed to comply with the following requirements: Site Management
shocked. Electrical Contractor
- Be connected to incoming supply by a direct method (e.g., wired to terminals)
Faulty installation - Be of robust construction
- Have a door or lid which:
• is fixed so they are kept closed (except for access) and require a tool to remove.
• is lockable,
• be attached so as not to damage cables / extension cords etc.; and
• has a means of keeping the door open when required for electrical work.
- Be positioned so that an appropriate flexible extension cord of suitable length can be used.
- Be securely attached to the floor, a pole, post, wall.
- Have at least one (1) 10amp power point and where required (1) 15amp point.
- Have a means of supporting electrical leads off the floor, i.e. lead stand, cross arm.
- Isolating switch i.e. “main switch”, “distribution board isolation switch.” “Isolating switch after-hours supply-do not
switch off”, must be marked as required by AS/NZS 3000 in letters 6mm high in contrasting colour to background
material.
- Additional switches clearly identified for final sub circuits intended to operate after hours, and emergency systems.
- Isolating switches provided with isolating device for securing in the open position.
- Lockable covers (made from non-conductive materials) provided over circuit breakers and RCD associated with
outgoing circuits, but which do not prevent access to isolating switches (unless the installation comprises of only one
final sub-circuit or includes or incorporates a combined mains circuit breaker / RCD as the main switch, in which case
the fitting of the lockable cover is not required).
- On the cover of the RCD’s and circuit breakers marked “In the event of an RCD or circuit-breaker operating, the cause
of any fault should be assessed by a competent person”.
- Fix a caution or danger safety sign to advise of electrical hazard.
- Have live parts protected to prevent contact by anyone connecting or disconnecting plugs.
- Have an insulated anchorage tie bar provided if there are power points on the board to prevent straining on the
cable going into the power supply.
- Have an insulated slot in the base for leads to go through and a sign fitted to it stating, “keep closed – run all leads
through bottom.”
Use of electrical Workers electrocuted / EXTREME 5 Portable RCDs will be tested by the user before each use daily and undergo an operating time at tripping current test Site Management
circuits shocked. using an RCD tester carried out by a licenced electrician every 3 months. Contract Partner
Faulty wiring
Electricity MEDIUM 4 Domestic power boards are not permitted on site. All power boards to comply with AS/NZS 3012 and be RCD protected. Site management
Contract Partner
Project Hazard/Risk Assessment / Page 58 of 160
Page 35
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Workers electrocuted / EXTREME 5 All isolations of live electrical circuits will involve placing a physical lock and attachment of a danger tag with relevant Site Management
shocked details associated with the isolation (including the name of the electrician who has undertaken the isolation) to prevent Contract Partner
unauthorised access. Energy circuits under the control of clients/service/asset owners shall have a visual verification of
isolation and lock out.
Full details of the Isolation & Lock out procedure will be detailed within the electrical Contract Partner ’s Safety Plan /
SWMS. Woollam Isolation & Lock Out Permit must be completed prior to commencement of work.
Refer Woollam procedure SP:03 Isolation & Lock Out for other isolation details.
Maintenance of Workers electrocuted / EXTREME 5 All wiring (including switchboards) will be inspected and tested by a licenced electrician after completion of the wiring and Site Management
electrical circuits shocked. prior to connection for normal use and at 6 monthly intervals. Records of all testing and verification to be retained on site Electrical Contract
and provided to Woollam. Partner
Faulty installation
Workers electrocuted / EXTREME 5 Construction wiring will be visually inspected to verify the integrity of the installation every six (6) months, with records of Site Management
shocked. inspections maintained on site. Contract Partner
Faulty installation
Workers electrocuted / EXTREME 5 All inspections, tests and maintenance carried out on electrical installations and plant & equipment will be recorded and Site Management
shocked. kept onsite. Compliant equipment to be fitted with a durable tag with the name of person conducting the test, and the Contract Partner
Faulty installation test and retest dates.
Construction wiring and electrical equipment shall be verified as follows:
- New equipment prior to introduction into service
- Repaired or serviced equipment prior to returning into service after a repair or service.
- Hire equipment inspected prior to each hire and at testing intervals as per Table 6 in AS/NZS 3012
- All equipment as per table 6 in AS/NZS 3012 and in accordance with relevant state/territories legislation.
Workers electrocuted / EXTREME 5 Fixed RCDs will be tested by a licenced electrician every month by the operation of the pushbutton and undergo an Site Management
shocked. operating time at tripping current test using an RCD tester carried out by a licenced electrician every 6 months from the Contract Partner
Faulty wiring time of installation.
References AS/NZ 3012 Electrical Installations – Construction
AS/NZS 3000 Wiring
AS 3010 – Electrical installations – Generating sets
Review / Safety Interactions, Task Observations, SWMS Review, Weekly HSE Inspection, Monthly Audit as per Procore Inspection matrix
Monitoring
9.2Works around overhead and underground electrical installations
Project Hazard/Risk Assessment / Page 59 of 160
Page 36
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Planning works Contact with overhead power EXTREME 5 Safe approach distances will be determined by plant operators and/or the Site Supervisor using the relevant state Site Management
around overhead lines legislation, COP and Australian Standards prior to any work commencing near overhead power lines. Contract Partner
powerlines Site Management
Contact with overhead power EXTREME 5 Consultation with the utility entity shall occur to inform of work activities when near assets and identify any specific
lines. controls that may be required. Contract Partner
Contact with covered / All work occurring near network assets must adhere to any requirements of an electricity entity responsible for the line.
underground services
Contact with overhead power EXTREME 5 No worker, equipment, loads being moved, crane or plant will be required to enter the exclusion zone around power Site Management
lines lines. Contract Partner
Contact with overhead power EXTREME 5 An electrical safety observer will work with the operator of any plant and equipment, which could enter the exclusion Site Management
lines zone. The electrical safety observer will have no other duty and will only observe one crane or piece of plant at a time. Contract Partner
Workers electrocuted / EXTREME 5 Work on site will be undertaken within the safe approach distances (i.e. exclusion zones) and special provisions will be Site Management
shocked made including: Contract Partner
- To notify and obtain written permission from the power authority before commencing work.
- Not to commence work until a pre-start site meeting, a risk assessment detailing the necessary controls to be
implemented and training has been completed.
Plan for working Striking underground services EXTREME Assessment of underground services completed prior to the commencement of works including: Site Management
around - DBYD
underground
power - Service location (i.e., scanning etc.)
- Potholing (positive identification of service location)
Planning for Inadvertent contact with EXTREME Assessment of live buildings to identify services remaining live during construction: Site Management
working around live electrical services Electrical contractor
If live permanent wiring is located where construction activity is occurring it, or its location shall be marked with the
electrical circuit words ‘LIVE WIRING’ at intervals not exceeding 5m.
Live permanent wiring shall be readily distinguishable from construction.
References AS/NZ 3012 Electrical Installations – Construction
AS/NZS 3000 Wiring
AS 3010 – Electrical installations – Generating sets
Review / Safety Interactions, Task Observations, SWMS Review Weekly HSE Inspection, Monthly Audit as per Procore Inspection Matrix
Monitoring
9.3Electrical equipment
Planning Electrocution HIGH 5 Contract Partner’s will supply an electrical register to demonstrate compliance with the above requirements Site Management
Contract Partner
Project Hazard/Risk Assessment / Page 60 of 160
Page 37
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Use of electrical Injury HIGH 5 All tools will be used in accordance with the manufacturer’s specifications. Site Management
equipment Contract Partner
Electrocution HIGH 5 All electrical equipment including power tools will be tagged and tested every three (3) months (unless relevant Site Management
jurisdiction legislation requires a short testing time frame) and will be fitted with a durable tag identifying the person Contract Partner
conducting the test, date of the test and next inspection.
Workers electrocuted / EXTREME 4 Flexible cords used in extension leads will be heavy duty sheathed, have a minimum 10amp rating and a minimum cable Site Management
shocked. size of. Contract Partner
Faulty installation - 1mm2 for a maximum cable length of 25m.
- 1.5mm2 for a maximum cable length of 30m.
- 2.5mm2 for a maximum cable length of 60m – 10amp rating
Flexible cords will comply with requirements for maximum length / current rating / conductor size applicable as per
AS/NZ 3012.
Workers electrocuted / EXTREME 5 Leads will not be joined such that the total length of any such combination exceed the relevant maximum length specified Site Management
shocked in section 2.6.7 in AS/NZS 3012 Electrical Installations - Construction Contract Partner
Workers electrocuted / EXTREME 4 All electrical leads will be protected from mechanical damage, heat sources and not to positioned in water or moist areas. Site Management
shocked Contract Partner
Metal structures energised. EXTREME 4 Where extension leads are run on insulated stands, hangers or clip brackets, clearances of at least 2m will be maintained Site Management
in work areas and higher clearances where vehicles operate. Contract Partner
Trips and falls
Metal structures energised EXTREME 4 Extension leads are not to be wrapped or slung off metal piping, lift cages, scaffolding or any other non-insulated bracket Site Management
or fixing – an insulated type of hanger or stand must be used. Contract Partner
Electrocution HIGH 1 Leads with piggyback plugs, leads with multiple plugs or double adaptors will not be used on site. Site Management
Contract Partner
Fire HIGH 3 Portable electrical equipment generating heated material (i.e., sparks, hot metal etc.) will not be used in the vicinity of Site Management
flammable or combustible materials. Contract Partner
Trips and falls. HIGH 5 Plugs will comply with AS/NZS 3112 – Approval and test specification – Plugs and sockets & extension sockets will comply Site Management
with AS/NZS 3120 -– Approval and test specification – Cord extension sockets. Contract Partner
Manual handling task
Electrocution HIGH 4 Leads will not be used in a coiled or reeled configuration. Site Management
Contract Partner
Injury to worker HIGH 3 Electrical leads and equipment will be electrically isolated or disconnected prior to changing blades, discs, bits, etc. or Site Management
undertaking other maintenance procedures and in advance of pack up of equipment. Contract Partner
Electrocution HIGH 5 Tools that are damp or wet or have been exposed to the rain will not be used unless they have been examined by an Site Management
electrician and cleared for safe use. Contract Partner
Project Hazard/Risk Assessment / Page 61 of 160
Page 38
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Contact with or impact from – HIGH 5 Only manufacturer’s recommended components will be fitted, including blades, discs, etc. and they will be checked prior Site Management
flying particles and moving to starting the equipment. Contract Partner
objects
Incorrect use resulting in HIGH 5 All tolls to have OEM guards and handles attached and the tool will be inspected prior to use to ensure it can be used Site Management
injury safely. Contract Partner
Electricity HIGH 4 Tools classed as DIY use only are not permitted on site. Site Management
Contract Partner
Falling objects HIGH 5 If using portable electrical equipment at heights, measures will be taken to ensure that tools cannot be dropped onto Site Management
workers below. Contract Partner
Injury
Maintenance of Workers electrocuted / EXTREME 5 Any worker that identifies damaged wiring, the damage is to be report to Site Management Team that part of the Site Management
electrical shocked installation is to be isolated repaired or replaced then tested prior to putting back into service. Contract Partner
equipment Any visual inspection by an electrician that identifies damage or non-compliant wiring, that part of the installation is to be
isolated repaired or replace then tested prior to putting back into service.
Workers electrocuted / EXTREME 5 Any non-compliant electrical equipment is to be removed from service immediately and have an out of service tag Site Management
shocked attached. The electrical equipment is to be repaired or replaced and tested by a qualified person. Contract Partner
Electrocution HIGH 5 Portable socket outlets shall comply with the relevant requirements of AS/NZS 3190 - Approval and test specification – Site Management
Residual current devices Contract Partner
Reference AS/NZS 3190 - Approval and test specification – Residual current devices
AS/NZS 3112 – Approval and test specification – Plugs
AS/NZS 3120 -– Approval and test specification – Cord extension sockets
Review / Safety Interactions, Task Observations, SWMS Review, Weekly HSE Inspection, Monthly Audit as per Procore Inspection matrix
Monitoring
9.4 Lighting
Planning Workers electrocuted / EXTREME 4 All lights will be supplied from a final sub-circuit of the construction wiring and be provided with residual current Site Management
shocked protection to a maximum rated residual current of 30mA. Electrical Contractor
Workers electrocuted / EXTREME 4 All lights in the construction area will be protected against mechanical damage, with mechanical guard for lamps and Site Management
shocked adequate stability as per AS/NZS 3012 Electrical Contractor
Inability to see site hazards. MEDIUM 4 Lighting will be provided on site sufficient and suitable for the illumination of all common areas including stairways, Site Manager
Slips, trips and falls corridors, and passageways where persons must frequent, pass or use.
Project Hazard/Risk Assessment / Page 62 of 160
Page 39
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Inadequate temporary or EXTREME 4 Emergency lighting will be in accordance with AS/NZS 3012 requiring a minimum of 20 lux. Site Management
emergency light levels Electrical Contractor
Sufficient battery powered lighting (minimum 1 hour capacity) will be installed in stairways, passageways and adjacent to
Trips and Fall switchboards to allow safe access to and egress from the area if there is insufficient natural “lighting” for the case of
emergency.
Emergency Lighting shall be verified by measurement using an appropriate light level meter with records of the test
provided to Woollam.
Emergency Lighting is to be provided in designated access and egress paths and directly above and in front of
switchboards where natural lighting requirements cannot be met using natural lighting.
Inability to see site hazards. MEDIUM Site Management
Emergency Lights in the required areas be one of the following: Electrical Contractor
Slips, trips and falls.
a) Provide an average of 20lux at 900mm above floor level along the centre line of the corridor containing the
Emergency response process
emergency lights; or
b) Be installed using luminaires complying with the luminaire classification, mounting height, and spacing specified
in table 2,3,4 or 5 in AS/NZS 3012 or
c) Be installed based on calculations of luminance complying with the requirements of AS 2293 and using a
minimum horizontal luminance of 3 lux.
Inadequate temporary or MEDIUM 5 Emergency lighting design or paperwork verifying the emergency lux levels to be on site and available to Woollam. Electrical Contractor
emergency light levels
Commissioning of Faulty electrical installations HIGH 5 Records of all testing and verification to be retained on site and provided to Woollam. Site Management
lighting Electrical Contractor
installations
Use Unable to evacuate in MEDIUM 4 Lighting levels will be in accordance with AS/NZS 3012 as follows: Site Management
emergency. Electrical Contractor
- Emergency min: 20 lux,
Slips, trips and falls. - Designated access and egress paths: min 40 lux,
Ergonomic issues - General work areas: min 160 lux
Slips, trips and falls MEDIUM 5 Contract Partner’s will be required to provide suitable and sufficient task lighting for all work areas and workplaces Site Management
requiring a greater luminance to perform their specific activities in a safe manner. Contract Partner
Slips, trips and falls MEDIUM 5 Relocatable lighting will not be placed in a position where it presents a trip hazard. Site Management
Contract Partner
Maintenance and Slips, trips and falls MEDIUM 5 Emergency lighting will be verified and tested at intervals not exceeding 6 monthly and recorded. The testing documents Site Management
testing are to be retained on the project. Electrical Contractor
References AS/NZS 3012 Electrical Installations – Construction
AS 2293-Emergency lighting and exit signs for buildings
Project Hazard/Risk Assessment / Page 63 of 160
Page 40
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Review and Safety Interactions, Task Observations, Weekly HSE Inspection, Monthly Audit as per Procore Inspection matrix
Monitoring
9.5Commissioning and energisation works
Planning for Electrocution EXTREME 5 Planning of works to be conducted with the site team and Contract Partner’s to apply for Permit to Energise Project Team
energisation works Contract Partner
Site disruptions Permit to identify any site impacts and communication requirements to the remainder of the project.
Inadvertent livening of parts Permit to energise will ensure communication and consultation with all involved trades and the Project Team.
Planning for Electrocution EXTREME 5 Commissioning process is to be coordinated with the site management team in alignment with AS 3760. Site Management
commissioning Electrical Contractor
Site disruptions
works
Inadvertent livening of parts
Commissioning Electrocution EXTREME 3 Tools, testing equipment and PPE are to be suitable for the task and align with the Safe Work Method Statement and Electrical Contractor
AS/NZS 3760
Electrocution EXTREME 5 Emergency Plan (for commissioning and energisation / electrocution) to be supplied by the Contract Partner prior to Electrical Contractor
works commencing (may be contained in the SWMS).
Works on Electrocution EXTREME 6 LV rescue kit to be on standby during commissioning works on/in switchboards. Electrical Contractor
switchboards
Completion of Inadvertent energisation of EXTREME 5 Licenced electrical to provide commissioning / testing records following completion of energisation works to verify Electrical Contractor
commissioning or electrical equipment and compliant electrical work has been handed over and is compliant and is carried out in accordance with AS 3000 and the
energisation works circuits applicable Australian standard.
Workers electrocuted / EXTREME 5 Where distribution boards are decommissioned, and GPOs are utilised during the handover stage of a project the Site Manager
shocked electrical contractor is to provide a test and compliance certificate and clearly communicate those circuits that are Contract Partner
operational off the mains board. Emergency shutdown processes for the board are to be briefed with the site
management team.
References AS 3760 Inservice safety, inspection, and testing of electrical equipment.
AS/NZS 3012 Electrical Installations – Construction
Review and Safety Interactions, Task Observations, Weekly HSE Inspection, Monthly Audit as per Procore Inspection matrix
Monitoring
Project Hazard/Risk Assessment / Page 64 of 160
Page 41
10. Fire Protection on Site
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Planning Safe evacuation path MEDIUM 3 Fire Emergency Exits / evacuations ways: Site
Management
- to be assessed to be clear of operational activities that could have a major impact on safe movement of
workers.
- be a minimum of 1200mm wide.
- be the quickest route to identified exit internal stairs and scaffold stairs.
- be uncluttered and kept clear for the entire route to the exit stairs and down to the building exit.
- be uncluttered from the building exit to the assembly areas.
- have adequate lighting to ensure safe visual travel – refer Lighting section to be maintained on a daily
basis and assessed on the Weekly HSE Inspection on Procore
Incorrect signage MEDIUM 3 Fire Emergency Exit / Access Signage Site
Management
- “Exit” signs to be positioned at all exit points from floor levels to exit stairs.
- “Evacuation Route” signs to be positioned along areas where Exit Signs can’t be quickly identified due to
building structure changes.
- exit signs to be positioned at a height of 2m and at various locations along the access way to adequately
inform workers of the safe exit route to take.
- be positioned at a height minimum of 2m above the floor adjacent to the exit openings.
be illuminated adjacent to internal stair wells – refer Lighting section to be maintained on a daily basis and
assessed on Weekly HSE Inspection on Procore
Fire control equipment MEDIUM 4 Fire Extinguisher: Site
Management
- Not less than one fire extinguisher to suit Class A, B and C fires and fires involving electrical equipment
will be always provided on each storey adjacent to each required exit or temporary stair or exit.
- Fire extinguishers to be installed with mounting bracket, (1200mm above floor level) and signage (2m
above floor) to prevent possible dislodgement and damage.
- to be maintained daily and assessed on Weekly Inspection Checklist
- To be tested and tagged at intervals not exceeding 6 months
Construction phase Fire control equipment MEDIUM 4 After the building has reached an effective height of 12m: Site
Management
- The required hydrants and hose reels for the building will be operational in at least every storey that is
covered by the roof or the floor structure above, except the 2 uppermost storeys: and
- Any required booster connections are to be installed.
- Hose reels are to be always rolled onto drum.
- The area in front of all hose reels is to be kept clear and uncluttered.
Project Hazard/Risk Assessment / Page 65 of 160
Page 42
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
- Water is to be always charged in reels.
a. All of the above is to be maintained current and assessed using the Weekly HSE Inspection on
Procore
No knowledge of safe procedures MEDIUM 5 Fire evacuation procedures including an evacuation path diagram will be developed and included in the Site
Emergency Response and Preparedness Plan. Management
No knowledge of safe procedures MEDIUM 5 Workers will be trained in evacuation procedures at site specific induction and will be involved in refresher Site
training throughout the construction process at planned intervals; as per trial evacuations. Management
Workers
No knowledge of safe procedures MEDIUM 5 Trial evacuation/s will be carried out on site and evaluation of the evacuation plan will be conducted by the Site
site management team following each trial evacuation – depending on the site drills may be: Management
- after 3 months of commencement
- when formwork or scaffolding has reached at least 4 levels.
- simulated medical emergency.
- site evacuation scenarios
- at intervals not greater than 6 monthly thereafter
- ad identified in the EPARP
No knowledge of safe procedures MEDIUM 5 Following any change to the site emergency plans, full communication of the changes to all personnel Site
working onsite will occur via the safety committee, toolbox talks and practice drills. Management
Explosion MEDIUM 5 Combustible materials (including waste materials and dust) will not be permitted to accumulate to constitute All Personnel
a fire hazard and the burning of materials will not be permitted on site.
Explosion MEDIUM 5 Flammable materials will be stored on site and handled in a manner that minimises the risk of fire, that is: Site Manager
Foreman
- Away from other combustible materials.
- Flammable signs erected adjacent to the storage area. HSE Advisor
- Fire extinguisher with sign erected adjacent to the storage area.
- Extinguisher tested and tagged every 6 months; and
- All of the above to be maintained on a daily basis and assessed on during the Weekly HSE Inspection in
Procore
Fire control equipment MEDIUM 4 Fire prevention and suppression equipment for the completed workplace/building will be made operational Site
as soon as possible. This may include heat and smoke detectors, etc. Management
Fire control equipment MEDIUM 4 All sub-contractors will provide a fire extinguisher within valid test date of the appropriate type in the Site
immediate area where hot works are taking place or a risk of fire on site. Management
Explosion MEDIUM 5 Warning signs will be displayed wherever a person could encounter materials that are highly flammable or Site
could cause an explosion. Management
Project Hazard/Risk Assessment / Page 66 of 160
Page 43
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Fire MEDIUM 1 Activities that generate flammable or explosive atmospheres will be eliminated. Site
Management
Fire MEDIUM 5 Appropriate controls will be implemented to minimise the risk from flammable or explosive atmospheres. Site
Management
Fire MEDIUM 5 Flammable substances will be properly stored, transported and disposed of to minimise fire / explosion risks. Site
Management
Fire MEDIUM 5 All Flammable materials boxes, wastepaper, scrap timber etc. to be removed from buildings and work areas Site
as soon as is reasonably practicable to remove ignition sources. Management
Contract
partners
Fire Medium 5 Eliminate smoking within / around buildings and work areas and provide designated smoking areas if location Site
permits. When working within health facilities, government buildings or schools full smoking bans to be Management
implemented. Contract
partners
Review and Safety Interactions, Task Observations, Weekly HSE Inspection, Monthly Audit as per Procore Inspection matrix
Monitoring
Project Hazard/Risk Assessment / Page 67 of 160
Page 44
11.Demolition
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Planning for Collapse of structures EXTREME 5 Woollam’ Demolition Work of Structures Checklist is to be completed prior to work starting. Site
demolition works / buildings Management
Demolition
Contract Partner
Compliance with EXTREME 5 The regulator is required to be notified of the following types of demolition work 5 business days prior to the commencement Project
regulatory of work: Management
requirements Site
- of a structure or part of a structure that is load bearing or otherwise related to the physical integrity of the structure Management
(only if six metres or higher in height) Demolition
- involving load shifting machinery on a suspended floor Contract Partner
- involving explosives
- Copies of notifications and permits will be obtained and retained on file
Exposure to hazardous EXTREME 5 Asbestos report from client or an appropriately qualified person who has examined the building or structure for the presence Project
materials of asbestos. Management
Site
Management
Exposure to hazardous EXTREME 1 All hazardous substances, lead and asbestos will be removed prior to demolition. Site
materials Management
Asbestos / Lead
Removalist
Compliance with EXTREME 5 Copies of business certificate for demolition and where applicable asbestos removal certificates for the Contract Partner will Site
regulatory be obtained. Management
requirements Demolition
Contract Partner
Inadequate EXTREME 5 Name and details of competent person to supervise demolition activities are to be obtained. Site
supervision Management
Contract Partner
Collapse of structures EXTREME 5 A Demolition Work Plan which considers the requirements of AS 2601 The demolition of structures and the relevant state Demolition
/ buildings code of practice will be provided for all demolition activities including: Contract Partner
Injury to workers a) location of the site on which the structure to be demolished stands
b) The overall height of the structure above ground level and the least distance from the structure to each boundary (all to
nearest 0.5m)
c) A brief description of the type of building (occupancy class), its structural support system and principal materials of
construction.
Project Hazard/Risk Assessment / Page 68 of 160
Page 45
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
d) Brief description of the methods of demolition proposed (including type of major equipment required and method of
moving between floors)
e) Methods for handling and disposing of demolition materials including hazardous waste.
f) Sequence of activities with the expected time to complete (in days) each stage of work.
g) Details of protective measures
h) Exclusion zones
i) And other plans related to items d) and g) including temporary engineering requirements.
j) Traffic management plan requirements
k) all relevant SWMS.
l) Noise, dust and environmental controls are to be identified and documented.
The Demolition Work Plan will include details of results of investigations as required by AS 2601 The demolition of structures
Demolition Collapse of structures EXTREME 5 If mechanical means are used to carry out the demolition work, the work is to be carried out sequentially in accordance with Site
activities / buildings approved Demolition Work Plan. Management
Demolition
Contract Partner
Collapse of structures EXTREME 5 Demolition work involving pulling with ropes or chains or similar means will only be carried out if the building being Demolition
/ buildings demolished is not more than 4 metres in height and the work is carried out sequentially. Contract Partner
Collapse of structures EXTREME 5 The demolition of chimney stacks will be in accordance with the relevant state legislation. Demolition
/ buildings Contract Partner
Collapse of structures EXTREME 3 Persons will not be permitted to work in or below a building being demolished Site
/ buildings Management
Demolition
Contract Partner
Collapse of EXTREME 5 Engineer’s investigation and certificate to support demolition machinery on structure. Site
structures/buildings Management
Demolition
Contract Partner
Exposure to hazardous EXTREME 5 Where demolition is performed by Woollam, and asbestos is identified on site work is to cease immediately (refer to Site
materials Hazardous Materials, Substances or Chemicals section) Management
Demolition
Contract Partner
Exposure to live EXTREME 5 Details (prescribed information) about underground services are recorded in writing and given to each person who is to do Site
services (gas, demolition work. Management
electrical, sewerage,
refrigerant gases etc.)
Project Hazard/Risk Assessment / Page 69 of 160
Page 46
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Exposure to live EXTREME 5 A copy of certification of the disconnection of services from the relevant authority is retained on site. Site
services (gas, Management
electrical, sewerage, Demolition
refrigerant gases etc.) Contract Partner
Flying particles / EXTREME 3 Controls will be in place to prevent falling objects hitting the public in adjoining areas by: Site
materials / falling Management
- Closing adjoining areas (to exclude all persons) to the extent necessary to prevent objects contacting persons. Demolition
objects
- Erecting perimeter containment screening along each part of the structure from which an object could fall. Contract Partner
- Another control measure to stop objects from falling on or hitting persons
Flying particles / EXTREME 4 Where overhead protective structures are provided over public walkways (between a public place and the building being Site
materials / falling demolished) the structures shall consist of a horizontal platform of solid construction with vertical supports and the Management
objects platform shall: Demolition
Contract Partner
- Extend from the common boundary to the edge of the carriageway for the full length of the boundary,
- Have a clear height above the footpath of not less than 2.1m,
- Terminate at the edge of the carriageway with a continuous solid up stand projecting not less than 0.5m above the
platform surface and
- Together with its supports, be designed for a uniformly distributed live load of not less than 7kPa.
Flying particles / EXTREME 5 Where the demolition is adjacent to another building controls will be implemented to protect: Site
materials / falling Management
- the other building; and Demolition
objects
- any person entering/leaving the other building; and Contract Partner
- any person who is on top of the other building (as applicable).
Flying particles / EXTREME 4 Where perimeter containment screening is erected or altered controls will be implemented to prevent any part of the Site
materials / falling screening falling on a person. Management
objects Demolition
Contract Partner
Flying particles / EXTREME 3 Where demolished materials are to be lowered onto / into a public place, the area will be properly barricaded to prevent Site
materials / falling members of the public entering. Management
objects Demolition
Contract Partner
Flying particles / EXTREME 4 Where scaffolding is provided it shall comply with AS 1576 Scaffolding (SET) and shall- Site
materials / falling Management
- be erected before the demolition work starts on the side of the building that is being demolished where it faces a public Demolition
objects place and may be kept erected until the work is finished; and Contract Partner
- be certified by an engineer; and
- be rated as heavy duty; and
Project Hazard/Risk Assessment / Page 70 of 160
Page 47
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
- have each platform extend the full width of the scaffold frame; about the building; and extend into any openings of the
building for a sufficient distance to catch any falling material.
- The above will occur in accordance with the relevant state legislation.
Flying particles / EXTREME 5 The demolition area will be defined, and non-essential personnel will be excluded from this area. Site
materials / falling Management
objects Demolition
Contract Partner
Flying particles / EXTREME 5 Signs stating “Danger! Demolition in Progress” or similar will be erected. Site
materials / falling Management
objects Demolition
Contract Partner
Emergency response EXTREME 5 At least two clearly marked, illuminated and unobstructed access and egress routes are provided as an emergency exit Site
processes connecting all un-demolished floors to the nearest street. Management
Demolition
Contract Partner
Falling objects EXTREME 3 Penetrations will be covered in alignment with Penetrations section Site
Management
Demolition
Contract Partner
References AS 2601 The demolition of structures
AS 1576 Scaffolding (SET)
Review and Safety Interactions, Task Observations, Weekly HSE Inspection, Monthly Audit as per Procore Inspection matrix
Monitoring
Project Hazard/Risk Assessment / Page 71 of 160
Page 48
12. Earthworks
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
12.1 Excavation, trenching and ground penetration
Planning for excavation works Contact with EXTREME 5 Prior to any excavation activity site management shall. Site
underground Management
- Utilise the detailed underground services plan, where available, that has been to manage the risk Contract Partner
services associated with working in the vicinity of underground services.
- Where such a plan is not available, undertake a detailed survey and positive location of all underground
services in the affected area and develop a detailed underground services plan that provides concise
information as to the nature and location of all underground services.
- Services such as ‘Dial Before You Dig;’ electromagnetic or other suitable scanning processes, and non-
destructive potholing are required to positively identify underground services prior to commencement
of works.
- Make available all information related to the nature and location of underground services to any party
engaged by Woollam to work in the vicinity of underground services.
Activity planning and EXTREME 5 All tasks involving excavations or trenching to have an approved SWMS in place which details controls for Site
hazard identification excavation activities. Management
Contract Partner
Failure to assess task EXTREME 5 0586–03 Excavation Permit shall be implemented prior to the start of any excavation works Site
specific risks. Management
The information related to about underground services will be kept onsite until the end of the project, or Contract Partner
Contact with for two years hence in the case where a notifiable incident has occurred in relation to the excavation
underground works.
services
Collapse of EXTREME 1 Unsafe excavations will be isolated by rigid barriers and shall not be entered by any persons unless written Site
excavation or approval by way of the appropriate 0586–03 Excavation Permit has been issued and all conditions have Management
trench been met. Contract Partner
Persons falling
Operation by EXTREME 1 Excavation plant (e.g., excavators, backhoes, etc.) will not be operated by persons who do not have the Site
unlicenced or appropriate licencing, training verifications or VOC’s. Management
inadequate trained Contract Partner
Plant operator’s competency to be verified at the site induction re: statement of attainment by RTO or
operators valid license.
Excavation and trenching activities Excavation collapse EXTREME 1 Materials will not be placed, stacked, or moved near the edge of the excavation in such a way as to cause a Site
collapse of the work or endanger a person below. Management
Contract Partner
Project Hazard/Risk Assessment / Page 72 of 160
Page 49
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Persons falling EXTREME 3 Any excavations 1m deep or more are barricaded (barricades at least 900mm high) to exclude entry and Site
protect persons from risk to health and safety from open excavations. Management
Contract Partner
Persons falling EXTREME 4 For trenches >1.5m deep where access is via steps or ladders, steps or ladders are: Site
Management
Falling objects - placed at 9m intervals in the part of the trench where a person will be. Contract Partner
- secured at the top and bottom against displacement.
- placed so the stiles of the ladder extend 1m beyond the landing place.
- placed so that there is a safe place to stand when leaving the ladder and
Not made of metal or with wire reinforcing where there’s a risk of contact with electricity.
Falling objects EXTREME 4 Shoring will be provided where there is a reasonable likelihood of a fall or dislodgement of earth, rock or Site
other material from a height of >1.5m that could harm a person. An adequate supply of shoring equipment Management
will be provided and used. Contract Partner
Collapse of EXTREME 4 Caissons and cofferdams will be of sound construction and secured into position to prevent movement. Contract Partner
excavation or trench
Collapse of EXTREME 4 All trenches over 1.5m deep will have at least one or a combination of the following controls to address each Site
excavation or side of the trench: Management
trench Contract Partner
1. Shoring (with commercially manufactured sheeting which has been designed by and engineer for its
Persons falling specific use and erected in accordance with the manufacturer / supplier’s instructions or sheeting /
timber where a competent person has inspected the trench and shoring and approved the use of the
timber / sheeting),
2. Benching (benches no higher than they are wide unless a geo-technical engineer has approved a greater
height in writing).
3. Battering (not be more than 45 degrees from the horizontal unless a geo-technical engineer has
approved the greater angle in writing), or
4. Geotechnical engineer’s certificate which approves in writing all sides of the trench as safe from
collapse, states in writing how long the approval lasts if there is no stated natural occurrence that could
affect adversely the stability of the trench and states in writing the natural occurrences that could
adversely affect the stability of the trench.
Collapse of EXTREME 5 Where a trench is not more than 1.5m deep and not shored, benched or battered and something happens Site
excavation or that could affect the stability of the trench or put someone at risk, work in the trench will be stopped Management
trench immediately and all persons will be excluded from the trench. Work will not re-start and persons will not be Contract Partner
Persons falling permitted to enter the trench until a geo-technical engineer inspects the trench and approves re-entry in
writing or all sides of the trench are shored, benched, battered or a combination of these controls.
Collapse of EXTREME 5 Trenches 1m deep or more will be inspected by a competent person at the intervals identified in the task Contract Partner
excavation or specific SWMS.
trench
Project Hazard/Risk Assessment / Page 73 of 160
Page 50
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Fall from heights EXTREME 4 Work at heights < 2m where a risk of injury could consider the use of edge protection, which includes handrails and mid- Site Management
rails. Contract Partner
Fall from heights EXTREME 4 Work at heights > 2m will require a minimum of one of the following control measures must be implemented (in order of Site Management
preference): Contract Partner
- the erection of physical barriers (such as guardrails or scaffolding)
- providing a personal fall protection system (in order of preference first a travel restraint system or second a fall-
arrest harness system)
- providing a catch system (catch net below a fall perimeter)
- erection of an exclusion zone (physical barrier minimum 2m back from the edge)
Use of edge Fall from heights EXTREME 4 Appropriate edge protection (consisting of the necessary handrails, mid-rails, toe-boards/kickboards and/or infill that Site Management
protection are adequate to provide support against workers and objects from falling from an edge or platform) will be erected and Contract Partner
maintained during the work activities on site.
Falling objects EXTREME 4 Where edge protection is selected as the work at heights control measures it must include top and mid rail, toe board, Site Management
mesh screen to prevent falling objects. Contract Partner
These shall comply with:
- Top rail – 900mm-1100 mm from ground
- Mid rail -
- Toe board – 150mm material placed hard down on the horizontal surface.
- Mesh 50mm x 50mm with an approved lining or mesh 25mm x 25mm mesh screening
Failure of equipment EXTREME 5 The use, installation, and maintenance of the work at heights system selected will be in accordance with the relevant Site Management
legislation, codes of practice and Australian Standards. Contract Partner
Works on roofs Fall from heights. EXTREME 4 Where the pitch of the roof is over 26º and a guard railing system is used, the guard railing will have a top rail, mid-rail, Site Management
toe board and an infill panel. Contract Partner
Falling objects
Fall from heights. EXTREME 4 Where the pitch of the roof is over 35º a platform will be constructed to minimise the likelihood of a person falling onto Site Management
the top rail or over the guard railing system. The platform will be at least 450mm wide with guardrails on the outside Contract Partner
Falling objects
perimeter and an infill panel on the outside perimeter and will not be used to stack materials or equipment.
Fall from heights. EXTREME 4 Where the pitch of the roof is over 45º additional safeguards will be provided as determined by a risk assessment: Site Management
Contract Partner
Falling objects - use of elevating work platforms
- higher guardrails
- perimeter scaffolding
- mesh infill panels.
- wider platforms
Project Hazard/Risk Assessment / Page 105 of 160
Page 51
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
- fall arrest systems
Use of fall Fall from heights EXTREME 5 Personal fall protection systems or catch systems used on site will be in accordance with AS 1891.4 and the Competent Person
protection systems manufacturer’s instructions must be employed wherever work is conducted near an unprotected edge. Sec3 WMSHP
Activity planning and EXTREME 5 Where fall arrest systems are used a SWMS for the activity is the address task hazards and controls. Site Management
hazard identification Contract Partner
Competent Person
Training and EXTREME 5 Competency requirements relating to the use, installation, inspection and testing facets of fall protection equipment is to Contract Partner
instruction align with the Site Management
All workers required to use personal fall protection equipment are to be competent in the inspection, use and
maintenance of such equipment – completed a Work at Height training course.
Failure of equipment EXTREME 5 Inspection Requirements for fall arrest equipment: Site Management
Contract Partner
Additional maintenance and testing requirements -
Application Activity
Personal equipment including harnesses, lanyard Inspection by operator before and after each use
assemblies, connectors and fall-arrest devises including
common use devices.
Fall arrest devices (external check only) 3 monthly inspections by a competent person
Belts, harnesses, lanyard assemblies and associated 6 monthly inspections by a competent person
personal equipment
- Permanently installed anchorages. 12 monthly inspection/ service by competent person.
- Fall-arrest devices (full service including dismantling
where indicated).
- Horizontal lifelines and rail, including integral
components and permanently installed mobile
attachment devices.
Fall from heights EXTREME 5 The following types of anchorage points are to be installed or verified for a fall arrest system: Site Management
Contract Partner
- engineer designed system.
- riggers pole attached to steel beam – installed by licensed rigger.
- anchor system or bracket that are designed by an engineer and installed by a suitable qualified person as per design.
- anchorage brackets attached to steel roofing material.
- anchorage bracket to framed steel structure.
- the above anchorage systems are installed by person that has completed a work safely at heights course
Project Hazard/Risk Assessment / Page 106 of 160
Page 52
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
Work at heights Fall from heights EXTREME 5 Lanyards, anchorage lines or restraint lines shall be able to be attached to anchorages before the operator moves into Site Management
position where there would be a risk of a fall, unless the operator is already protected by another fall-arrest system. Contract Partner
Competent Person
Incompatible systems EXTREME 5 The type of fall-arrest system attached to an anchorage point shall be compatible with the anchorage strength indicated Site Management
on any sign associated with the anchorage point. Contract Partner
Competent Person
Falling objects EXTREME 6 Wrist straps or rope lanyards will be used to secure tools to persons or work platforms to prevent falling objects. Site Management
Contract Partner
Failure of equipment EXTREME 5 Servicing schedules will be placed on the Woollam or equivalent prior to equipment being used on site. Site Management
Contract Partner
This register shows the service/ maintenance duration and date of the last service for each item.
Working on roofs Failure of roof EXTREME 4 Where workers are required to access or work on any part of a roof of a building or structure which comprises of or Site Management
materials resulting in a includes brittle or fragile roofing material the following will be action. Contract Partner
person or object falling Existing or New Roof Sheeting:
form heights
- assess the roof and provide a suitable walkway to where workers need to work – planks or sheets of ply laid on
Resulting in a person roof material for access way and work area.
or object falling from
heights - provide warning signage or exclusion zones outside of identified walkways and work areas.
Existing or New Roof Skylights:
- where workers are required to work within 2m of adjacent skylights - provide a suitable strength cover e.g., wire
mesh, metal or ply sheet coverings depending on the size of the skylight.
- where workers are required to work over 2m from skylights – provide a flag exclusion zone to identify the area.
A fall protection cover placed over holes and openings must be:
- able to withstand the impact of a fall onto it of any person who may reasonable be expected to fall onto it.
- be securely fixed in place to prevent it being moved or removed accidentally.
- if a cover is used as a control measure, it must be made of a material that is strong enough to prevent persons or
objects falling through.
References AS 1891.4 Industrial fall arrest systems and devices – Selection, use and maintenance.
Project Hazard/Risk Assessment / Page 107 of 160
Page 53
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
AS 1891.4 Industrial fall arrest systems and devices – Selection, use and maintenance (2.2.10 User Competency)
Review and Safety Interaction, Task Observation, Monthly Audit as per Procore Inspection Matrix.
Mentoring
Project Hazard/Risk Assessment / Page 108 of 160
Page 54
16. Temporary Support Structures
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Residual Person
16.1 Formwork
Planning Collapse of EXTREME 5 Formwork / Concrete Placement and Installation Checklist on Procore is to be completed prior to commencement of formwork and Site
formwork concrete placement. Management
Contract
Partner
Collapse of EXTREME 5 Formwork documentation will be provided prior to work being undertaken and available on site. This documentation shall contain a Site
formwork statement that the formwork design conforms with AS 3610 including the following information: Management
Formwork
a. A certification letter from the Professional Engineer or Formwork Designer listing the formwork drawings or all drawings signed and Contract
certified by the engineer or formwork designer. Partner
b. Formwork drawings
c. Where eccentric loading is to be applied to U-heads (i.e. single bearers are positioned to one side of the U-head), the formwork drawings
should state that this is permitted.
d. Details sufficient to fully describe important or unusual features of the design.
e. Reference to documentation for proprietary items.
f. Work method statements for the erection and stripping of the formwork assembly.
g. The areas of the form designed to carry stacked loads.
h. Acceptance criteria for single use formwork.
i. Requirements for the project documentation relating to formwork.
j. Method of provision for field adjustment of the forms prior to and during concrete placement.
k. Where required, location of weep holes, vibrator holes, clean-out holes and inspection openings.
l. Sequence of concrete placement, including direction of intended pour on ranking or sloping surfaces.
m. Wrecking strips and other details relating to stripping of other forms.
n. Design assumptions, including those related to strength, stability and stiffness.
o. Footing design assumptions, such as foundation material description, safe bearing value, limitations on settlement during erection of
formwork, placement of concrete and dismantling of formwork. Reference to information sources such as geotechnical reports should
also be included.
p. Preparation of the foundation, such as filling, compaction, and drainage.
q. Footing details, such as type and size of footings, level of soffit, concrete strength, reinforcement, specification and details of site filling
or compaction, and precautions against washouts.
Project Hazard/Risk Assessment / Page 109 of 160
Page 55
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
r. Professional engineer certification of non-proprietary equipment.
s. Evidence that the formally conforms to Australian Standards.
t. Vertical pour rates.
u. Methods of securing single or multiple props
Collapse of EXTREME 5 Formwork drawings must explain: Formwork
formwork Contract
- Plans, elevations, and sections to show the general arrangement of the formwork and to identify and locate all members and Partner/
components including bracing. Engineer
- Wall and column form details
- The maximum point loadings to be applied.
- The component types and spacings.
- The maximum jack extensions.
- The bearer and joint timber type, the dimensions and spacings.
- The prop sizes and maximum extensions.
- The method for tying the structure together and spacing between ties (if required); and
- The form ply size
Collapse or EXTREME 5 Formwork must be designed by a competent person or an RPEQ certified engineer as per the table below referenced from the Formwork
Formwork COP 2016.
Project Hazard/Risk Assessment / Page 110 of 160
Page 56
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
With a competent person defined as –
a person who has acquired, through training, qualifications or experience knowledge and skills, including:
• sound knowledge of relevant Australian Standards, relevant codes of practice and other relevant legislation,
• ability to read and interpret drawings
• sound knowledge of, and competence in, the risk management process for the erecting, altering and dismantling of formwork including:
- hazard identification and risk assessment - measures to control exposure to risks - safe work practices and procedures - how to
plan and prepare formwork.
Planning for Activity EXTREME 5 All tasks involving formwork will have an approved SWMS in place. The SWMS will address all high-risk activities including work at heights Site
formwork planning and for tasks that are undertaken where a worker could fall 2m or more and scaffold stripping activities along with formwork hazards and Management
installation hazard controls. Formwork
identification Contract
Partner
Falling objects EXTREME 3 Where works to erect or dismantle formwork are undertaken, the adjoining area will be closed to the public or perimeter containment Site
screening will be erected. Management
Where works to erect or dismantle formwork are undertaken, the area on site will be excluded to non-essential workers not involved in the
task.
Access and EXTREME 3 QLD – Site
egress Management
Stair tread access and egress is to be used as the primary source of access to a formwork deck unless it is not reasonably practicable to do
Slips trips. so.
Emergency Access requirements as per Formwork code of practice 2016 are to be applied:
retrieval
Access and EXTREME 4 NSW - Access to the live working deck will be through one of the following methods. Site
egress Management
- Extension Ladder – Tied top and bottom, at an angle of 4:1 and protrude at least 1 metre above the landing height.
Slips trips. - Hoist
Emergency - Internal stairs
retrieval
- Portable stairs
- Mobile scaffold stairs
- Perimeter scaffold stairs.
Project Hazard/Risk Assessment / Page 111 of 160
The text continues on page 57.
Used in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 836 KB (small file)
- File type
No other editions are linked here.