Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118

of 80

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                                                                                 Proposed Controls                                                                             Responsible
Activity       Hazards




                                 Risk
                                                                                                                                                                                                      Risk




                                          HOC




                                Initial
                                Rating
                                                                                    (1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)                                              Person


                                                                                                                                                                                                    Residual
           Falls from         EXTREME     5     Formwork contractor will ensure that their work method complies with the COP for formwork 2016 with work at the leading edge always                               Site
           height                               being protected by at least 1.8m of false work (catch deck) in all directions.                                                                                 Management
                                                All timbers or proprietary systems must be laid from below to remove work at height risks.

           Collapse of        EXTREME     5     Formwork that is a “basic formwork system” will be designed by a formwork designer or professional RPEQ engineer.                                                 Site
           formwork                                                                                                                                                                                            Management
                                                                                                                                                                                                                Contract
                                                                                                                                                                                                                 Partner
           Collapse of        EXTREME     5     Formwork that is not a “basic formwork system” will be designed by a professional RPEQ engineer.                                                                   Site
           formwork                                                                                                                                                                                            Management
                                                                                                                                                                                                                Contract
                                                                                                                                                                                                                 Partner
           Collapse of        EXTREME     5     Prior to any concrete pour, a qualified formwork engineer nominated by the form worker will inspect the formwork and back propping                                Site
           formwork                             design to certify (through a signed inspection sheet) that the formwork is as per the certified design and AS 3610 and is ready for concrete                   Management
                                                pouring.                                                                                                                                                        Contract
                                                                                                                                                                                                                 Partner
           Collapse of        EXTREME     4     Back propping will be required and designed by a professional engineer.                                                                                           Site
           formwork                                                                                                                                                                                            Management
                                                A copy of the back propping plan will be available on site to both Woollam and the Formwork Contractor.                                                         Contract
                                                                                                                                                                                                                 Partner
           Collapse of        EXTREME     5     A formwork assembly check and monitoring will be undertaken by the formwork contractor during the concrete pour, with hazards identified                          Site
           formwork                             to be rectified or if necessary, the pour diverted or stopped to ensure the safe progression of the pour.                                                      Management
                                                                                                                                                                                                                Contract
                                                                                                                                                                                                                 Partner
           Falls from         EXTREME     5     Fall from heights controls as required by the project risk assessment will be implemented as required for formwork tasks.                                         Site
           height                                                                                                                                                                                              Management
                                                                                                                                                                                                                Contract
                                                                                                                                                                                                                 Partner
           Fall from height   EXTREME     3     External perimeter screens with mesh with openings of no more than 50mm x 25mm with 2.5mm diameter steel (or 50 x 50mm with                                        Site
                                                approved lining) will be erected to the full height of the building where formwork is erected, and the screens will extend at least one (1)                    Management
                                                metre above the formwork prior to erection.                                                                                                                     Contract
                                                                                                                                                                                                                 Partner
           Falls from         EXTREME     5     Any formwork such as wall or column forms to be lifted by a crane will have an engineer’s certificate certifying the lifting points and lifting                   Site
           height                               method.                                                                                                                                                        Management
                                                                                                                                                                                                                Contract
                                                                                                                                                                                                                 Partner
           Collapse of        EXTREME     5     Slip and jump form will include additional details to address compliance with the Formwork COP requirements.                                                      Site
           formwork                                                                                                                                                                                            Management
                                                a. Provision of safe access to all working areas                                                                                                                Contract
           falling objects                                                                                                                                                                                       Partner
                                                b. Control of risks associated with working at height.
           noise and dust
                                                c. Provision of sufficient working space and head room
           manual tasks

                                                                                                                                                 Project Hazard/Risk Assessment / Page 112 of 160

Used in these records

About this file

File size
836 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdf · 836 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.