Skip to the record
The gold standard in government transparency.

Council archive · source document

Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118

of 80

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

    2.1 Design and Construct Project


                                                                                                        Proposed Controls
       Hazard                                                                                                                                                                                              Responsible Person




                        Risk
                                                                                                                                                                                                  Risk




                                 HOC




                       Initial
                       Rating
                                                                           (1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)



                                                                                                                                                                                                Residual
Worker health and      HIGH      5     Consultation with all designers and consultants to ensure they are made aware that their design is to meet.                                                         Project Manager and
safety during the:                      •    all legislative requirements and                                                                                                                              Designers and
•    Construction                       •    incorporate control measures to remove or reduce health and safety implications to an acceptable level.                                                       Consultants
•    Use                               Design briefs need to consider the health and safety of persons.
•    Maintenance and                    •    during construction of the structure/equipment
•    In the vicinity                    •    when the structure /equipment has been constructed and is used by the end user.
                                       Regular meetings are to be scheduled with designers/consultants to review and where possible close out actions/issues raised in the design
                                       risk assessment.
                                       Architects, designers, engineers, and those consultants responsible for design elements must provide the project team with a documented
                                       design risk assessment addressing the issues described above.
                                       Residual constructability risks to be outlined in the above table.
                                       Where there are design changes the site team is to undertake a preliminary assessment and.
                                        •    Record yes or no on the project variation register to identify if the changes may impact on the site health and safety that involve
                                             change in.
                                        •    New construction materials
                                        •    Construction processes
                                        •    Construction techniques previously used.
                                        •    Introduction of new hazardous materials
                                       Amend or develop a new work method statement for the change being made.
                                       Where YES has been recorded on the variation register the site team is to undertake a design changes assessment
                                       Results of the design change risk assessment are to be communicated to the relevant Contract Partner’s or employees and involve a toolbox
                                       talk to inform the relevant workers




                                                                                                                                                     Project Hazard/Risk Assessment / Page 14 of 160

Used in these records

About this file

File size
836 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdf · 836 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.