Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
Proposed Controls
Activity Hazard Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Plant and people HIGH 5 The TMP/TGS will consider the co-ordination of site plant/pedestrians and members of the public. M Site Management
interactions Contract Partner
Activity planning and HIGH 5 All tasks involving Traffic & Roadway Management will have an approved SWMS in place. M Site Management
hazard identification Contract Partner
Training and HIGH 5 Suitably licenced Traffic Controllers to be engaged to perform traffic control tasks in alignment with Minimum M Site Management
licensing Licencing Guidelines. Licences are to be sighted and recorded at induction. Contract Partner
Construction works Vehicle interactions HIGH 5 Where the drivers of vehicles, trucks and plant are required to reverse into the site across public footpaths and M Site Management
with members of the walkways the following is to be implemented:
public - Erect a sign at the entry gates directing drivers to contact the Site Manager/Foreman before entering site –
provide phone numbers.
- Email suppliers and Contract Partners to advise them of the health and safety protocol to be followed for plant
& vehicle movements onto the site.
- Where there are members of the public using the footpath or walkways provide a spotter or mechanical aids to
control their movements during the reversing process.
- The reversing vehicle, plant, and trucks from the street to be controlled as per the traffic management plan for
the project
Interactions with HIGH 3 Where the altered roadway/path cannot be controlled using safety barriers and signage alone, traffic controllers M Site Management
members of the will be provided to direct vehicles and pedestrians. Contract Partner
public
Failure to correctly HIGH 5 Signs and devices will be erected and displayed before work commences. Signs and devices will be removed M Site Management
identify construction from a work site only after all work is completed and as soon as practicable after completion of the work each Contract Partner
work zones day.
Traffic devices not HIGH 5 A detailed daily diary/log will be maintained for all actions taken by a traffic controller on site which includes M Site Management
implemented during details of signage and traffic control setup daily and time of control set up, modifications or controls removal, Contract Partner
altered traffic hours of operation and surface condition of the road.
conditions Periodic inspection is completed to ensure devices are in place as per TGS and free of damage and vandalism.
Worker safety in low HIGH 6 Additional reflective helmet, vest, leggings, and light baton will be worn and used for night works as per MUTCD. M Site Management
light conditions Contract Partner
Worker safety in low HIGH 4 Night lighting will be provided for night works to ensure traffic controllers are visible to oncoming traffic. M Site Manager
light conditions
Road conditions HIGH 2 Consideration will be given to conducting work out of peak times. M Project Management
Site Management
Project Hazard/Risk Assessment / Page 22 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 836 KB (small file)
- File type
No other editions are linked here.