Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
12. Earthworks
Proposed Controls Responsible
Activity Hazards
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
12.1 Excavation, trenching and ground penetration
Planning for excavation works Contact with EXTREME 5 Prior to any excavation activity site management shall. Site
underground Management
- Utilise the detailed underground services plan, where available, that has been to manage the risk Contract Partner
services associated with working in the vicinity of underground services.
- Where such a plan is not available, undertake a detailed survey and positive location of all underground
services in the affected area and develop a detailed underground services plan that provides concise
information as to the nature and location of all underground services.
- Services such as ‘Dial Before You Dig;’ electromagnetic or other suitable scanning processes, and non-
destructive potholing are required to positively identify underground services prior to commencement
of works.
- Make available all information related to the nature and location of underground services to any party
engaged by Woollam to work in the vicinity of underground services.
Activity planning and EXTREME 5 All tasks involving excavations or trenching to have an approved SWMS in place which details controls for Site
hazard identification excavation activities. Management
Contract Partner
Failure to assess task EXTREME 5 0586–03 Excavation Permit shall be implemented prior to the start of any excavation works Site
specific risks. Management
The information related to about underground services will be kept onsite until the end of the project, or Contract Partner
Contact with for two years hence in the case where a notifiable incident has occurred in relation to the excavation
underground works.
services
Collapse of EXTREME 1 Unsafe excavations will be isolated by rigid barriers and shall not be entered by any persons unless written Site
excavation or approval by way of the appropriate 0586–03 Excavation Permit has been issued and all conditions have Management
trench been met. Contract Partner
Persons falling
Operation by EXTREME 1 Excavation plant (e.g., excavators, backhoes, etc.) will not be operated by persons who do not have the Site
unlicenced or appropriate licencing, training verifications or VOC’s. Management
inadequate trained Contract Partner
Plant operator’s competency to be verified at the site induction re: statement of attainment by RTO or
operators valid license.
Excavation and trenching activities Excavation collapse EXTREME 1 Materials will not be placed, stacked, or moved near the edge of the excavation in such a way as to cause a Site
collapse of the work or endanger a person below. Management
Contract Partner
Project Hazard/Risk Assessment / Page 72 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 836 KB (small file)
- File type
No other editions are linked here.