Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
Proposed Controls
Activity Risk Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Activity planning HIGH 5 All tasks involving concrete pumping will have an approved SWMS in place including prior to the commencement of Site Management
and hazard work.
identification Contract Partner
Impact of pipelines HIGH 3 When the pump be set up in the street, then safe and unobstructed access for the public-to-public areas in the vicinity Site Management
and boom with of the pumping unit and the delivery trucks will be maintained and clearly identified. Controls to protect the public
structure, scaffold, from concrete pumping activities will be implemented:
and personnel
Protective screens fitted around the pump area.
Close fitting mesh or shade cloth screen around the pump reservoir
Sign posting “concrete pump being used” / “Concrete pump in operation”.
Provide an access ramp for the public which is stable and sold, doesn’t create a trip hazard, has a height to length ratio
of no more than 1:12 from the highest point to the end of the ramp, is easily negotiable by wheelchair, has a non-slip
surface at all times, extends the width of the footpath, has handrails and toe boards, has adequate lighting and has
pump pipes that are removable for inspection and cleaning.
Pump set up Overhead services HIGH 5 The boom pumps will be set up with regard to the minimum distance requirements to power lines, wind conditions Site Management
and obstacles and the presumption that all power lines etc. are live unless they are positively identified to be isolated, and a
certificate has been issued stating the same.
Rollover of concrete HIGH 5 Underground services, unstable ground, and other excavations in the vicinity will be identified and details given to the Site Management
truck Contract Partner prior to setup and commencement of work.
Other workers or HIGH 5 Concrete pump areas will be sign posted “Danger – Concrete Pumping Area – Authorised Persons Only”. Site Management
visitors in the
concrete pumping Exclusion zone established and unauthorised people are not present in concrete pumping exclusion zone.
zone All persons other than operators of the pump are to stay clear of the pump and associated pipes / accessories.
Exposure to fumes HIGH 5 Precautions will be taken to prevent the build-up of exhaust gases in work areas. Site Management
from exhaust
Contract Partner
Slips, trips and HIGH 5 Clear access to the pump unit for concrete trucks to be maintained. Site Management
injury to pump
operators
Project Hazard/Risk Assessment / Page 116 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 836 KB (small file)
- File type
No other editions are linked here.