Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
Proposed Controls
Activity Risk Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Incomplete EXTREME 5 Documentation verifying the following is to be available on site: Site Management
documentation
The concrete specification of concrete supplied on site for use in panels. Contract Partner
The minimum final concrete strength (i.e. 28-day strength) of concrete delivered to the site.
The minimum concrete strength to be achieved prior to lifting of panels (information for the inserts should be
available that specifies the minimum concrete strength required for the insert.)
How many days are to elapse between casting and lifting of panels.
Results of a sampling program that demonstrates the concrete is of an appropriate strength.
The casting dates for each panel and earliest date when the panel can be lifted (each panel should be numbered, and
written records made)
Where dead men anchor points are used – Deadman drawings, and engineer sign off is required as per COP
Activity planning EXTREME 5 All tasks involving tilt up panel construction and erection will have an approved SWMS in place including prior to the Site Management
and hazard commencement of work
identification Contract Partner
Insufficient EXTREME 5 Concrete test reports for supporting concrete structures i.e., slab top and bottom, dead men – supplied by concrete Site Management
engineering supplier
resulting in Contract Partner
Structural collapse
Installing panels People interaction EXTREME 3 An exclusion zone will be established so that only those persons directly involved with the erection of panels are in Site Management
in installation area the area while lifting is taking place. The exclusion zone will be set up so that it includes an area where persons cannot
resulting in injury be struck either by: Contract Partner
The crane falling over,
The panel being lifted falling over (approx. 1.5 x height of largest panel), or
Another structural element failing and falling to the ground as a result of being struck by the crane or the panel being
lifted.
Consider neighbouring properties and public access ways – refer traffic management if closure required.
For vertical construction – exclusion of 1 floor below panel flight path.
Collapse of pre-cast EXTREME 3 A minimum of two braces will be secured to each panel unless specified by the engineer and indicated on the erection Site Management
concrete units drawings. Where only one brace is used there will be a minimum of two fixings at each end.
Contract Partner
Project Hazard/Risk Assessment / Page 122 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 836 KB (small file)
- File type
No other editions are linked here.