Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118

of 80

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

                                                                                                                      Proposed Controls
       Activity                 Risk                                                                                                                                                                           Responsible Person




                                                Risk
                                                                                                                                                                                                    Risk




                                                             HOC




                                               Initial
                                               Rating
                                                                                           (1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)




                                                                                                                                                                                                  Residual
                       Fall from height       EXTREME    4         Compliant edge protection consisting of handrail at 900mm, mid-rail at 450mm and toe board 150 to 250mm must be                           Site Management
                                                                   in place for work 2m and above or via risk assessment if under 2m.
                                                                                                                                                                                                             Contract Partner
                                                                   A 2m exclusion zone to be established during works

                       Falling objects        EXTREME    4         Mesh guard to be installed if risk of falling objects could occur. Safe access to working platform must be in place                       Site Management
                                                                                                                                                                                                             Contract Partner

                       Plant colliding with   EXTREME    3         Plant movement paths and exclusion zones are to be established on and around walls that have been braced.                                 Site Management
                       temporary bracing
                                                                                                                                                                                                             Contract Partner

                       Hazardous              EXTREME    6         Mixing of cement should be done in well-ventilated area. Required PPE to be worn as per SDS (i.e., eye and hand                           Site Management
                       substances                                  protection).
                                                                                                                                                                                                             Contract Partner

                       Hazardous              EXTREME    5         Controls are to be implemented so workers are not exposed to RCS above the workplace exposure limit.                                      Site Management
                       substances
                                                                                                                                                                                                             Contract Partner

                       Manual handling        EXTREME    4         High risk manual tasks to be identified e.g., continuous heavy lifting, excessive pulling/ pushing movements – controls                   Site Management
                       injuries                                    implemented for high-risk manual tasks e.g., use trolleys to lift blocks from pallet, not pushing/ pulling loaded pallets
                                                                   onto or off of loading platforms, materials and tools not to be thrown from one level to another. Mechanical or other                     Contract Partner
                                                                   means to be used as required

                       Hazardous              EXTREME    5         Workers trained in hazardous substance use (hydrochloric acid). Hazardous chemicals safely stored when not in use;                        Site Management
                       substances                                  Hazardous chemicals not stored in drink containers
                                                                                                                                                                                                             Contract Partner

                       Falling objects        EXTREME    5         Loading of blocks on scaffolds bays or working decks not to overload SWL of the scaffold bay.                                             Site Management
                       Scaffold collapse                                                                                                                                                                     Contract Partner

Bracing and propping   Wall collapse          EXTREME    4         Wind loadings must also be considered when determining bracing requirements and wall heights. Bracing to be                               Site Management
                                                                   installed on both sides of masonry walls unless appropriate push/pull bracing is installed.
                                                                                                                                                                                                             Contract Partner

                       Injury                 EXTREME    4         Exclusion and No-Go zones to be established around all walls when high winds are expected.                                                Site Management
                                                                                                                                                                                                             Contract Partner




                                                                                                                                                    Project Hazard/Risk Assessment / Page 124 of 160

Used in these records

About this file

File size
836 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdf · 836 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.