Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118
Proposed Controls
Activity Risk Responsible Person
Risk
Risk
HOC
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)
Residual
Contract Partner Crane
Crew
Installation of PT Cable Injury to workers EXTREME 5 Cables will be bundled and capped prior to being tensioned. Contract Partner
Falling objects EXTREME 5 All cable offcuts are to be placed in rubbish bins; cable offcuts are not to be left on the scaffold. Contract Partner
Slips and trips
Fire MEDIUM 5 Obtain Hot Work Permit and conduct work in accordance with requirements, including the use of a fire extinguisher in Site Management
the work area.
Contract Partner
Cable rupturing EXTREME 5 Prior to the placement of concrete, the design engineer will verify that the placement of conduits, cables and Site Management
associated equipment meets the intended post tension design.
Contract Partner
Engineer
Tensioning of cables Cable rupturing EXTREME 5 Concrete MPA strength will be monitored, and the design engineer will verify cable length extensions during the cable Site Management
tensioning process.
Contract Partner
Engineer
Injury to workers HIGH 4 Erect flagging and signage around install area and coil to prevent access. Keep clear of cable as it is pulled from coil. Contract Partner
Cable over EXTREME 5 A copy of the current jack and gauge calibration certificate will always be kept with the jack and gauge on site. Site Management
tensioning
Contract Partner
Cable rupture Engineer
Cable rupturing EXTREME 4 PT Supervisor to communicate with other trades on site and restrict access to slab across full length of tendon/s. Site Management
Stressing area to be barricaded off using flagging/signage, etc. to restrict access.
Contract Partner
Exposure to HIGH 5 Cement based grout products to be used in accordance with manufacturer’s specs and SDS, including the use of PPE - Contract Partner
hazardous materials gloves, glasses, respiratory protection, etc.
Slips/trips HIGH 3 All grout tubes are filled, and the rendering of cable heads will be completed by the Contract Partner in a floor-by- Contract Partner
floor sequence.
Injury to workers
Project Hazard/Risk Assessment / Page 127 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 836 KB (small file)
- File type
No other editions are linked here.