    18.               Structural Steel
                                                                                                                            Proposed Controls                                                                        Responsible




                                                                HC
         Activity                    Hazard




                                                       Risk
                                                                                                                                                                                                          Risk




                                                      Initial
                                                      Rating
                                                                                               (1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)                                         Person
                                                                                                                                                                                                        Residual

      18.1              Structural Steel Erection
Planning for the             Activity planning,       HIGH      5    Woollam Erecting Structural Steel Checklist on Procore is to be completed prior to work starting on Procore                                   Site Management
installation of structural   hazard                                                                                                                                                                                Contract Partner
steel                        identification,
                             resourcing and
                             implementation of
                             controls

                             Activity planning and    HIGH      5    All tasks involving structural steel erection / installation will have an approved SWMS in place including prior to the
                             hazard identification                   commencement of work

                             Structural collapse     EXTREME         Installation of structural steel members to be in accordance with engineers approved sequencing / methodology.                                Site Management
                                                                                                                                                                                                                   Contract Partner
                             Falls                    HIGH      5    Suitable methods to protect workers from fall from heights hazards during steel erection activities are to be detailed in                     Site Management
                                                                     SWMS and implemented. Such methods may include the use of perimeter guardrails, scaffolding, etc.                                             Contract Partner
                                                                     Methods to reduce the need for personnel to work at heights during steel erection activities are to be considered

                             Workers not              HIGH      5    Workers required to undertake any rigging / dogging activities are to hold a current licence/certification. The                               Site Management
                             correctly licenced                      licence/certification will be sighted and copied (where there is a facility to do so) at induction.                                           Contract Partner
                             for the activity

                             Collapse                 HIGH      5    The erection of any component is to only commence when the necessary equipment to ensure stability of the structure                           Site Management
                                                                     (i.e. temporary guys or bracing) is available and stability of the structure can be maintained at all times.                                  Contract Partner

Steel installation           Incorrect crane set     EXTREME    5    Where a mobile crane is required to be used for installation process, set up and location will be completed in accordance                     Site Management
                             up.                                     with the Mobile Crane Section.




                                                                                                                                                     Project Hazard/Risk Assessment / Page 129 of 160

Used in these records

About this file

File size
836 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdf · 836 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.