18. Structural Steel
Proposed Controls Responsible
HC
Activity Hazard
Risk
Risk
Initial
Rating
(1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE) Person
Residual
18.1 Structural Steel Erection
Planning for the Activity planning, HIGH 5 Woollam Erecting Structural Steel Checklist on Procore is to be completed prior to work starting on Procore Site Management
installation of structural hazard Contract Partner
steel identification,
resourcing and
implementation of
controls
Activity planning and HIGH 5 All tasks involving structural steel erection / installation will have an approved SWMS in place including prior to the
hazard identification commencement of work
Structural collapse EXTREME Installation of structural steel members to be in accordance with engineers approved sequencing / methodology. Site Management
Contract Partner
Falls HIGH 5 Suitable methods to protect workers from fall from heights hazards during steel erection activities are to be detailed in Site Management
SWMS and implemented. Such methods may include the use of perimeter guardrails, scaffolding, etc. Contract Partner
Methods to reduce the need for personnel to work at heights during steel erection activities are to be considered
Workers not HIGH 5 Workers required to undertake any rigging / dogging activities are to hold a current licence/certification. The Site Management
correctly licenced licence/certification will be sighted and copied (where there is a facility to do so) at induction. Contract Partner
for the activity
Collapse HIGH 5 The erection of any component is to only commence when the necessary equipment to ensure stability of the structure Site Management
(i.e. temporary guys or bracing) is available and stability of the structure can be maintained at all times. Contract Partner
Steel installation Incorrect crane set EXTREME 5 Where a mobile crane is required to be used for installation process, set up and location will be completed in accordance Site Management
up. with the Mobile Crane Section.
Project Hazard/Risk Assessment / Page 129 of 160
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdfRelated documentApplication case desk ↗
About this file
- File size
- 836 KB (small file)
- File type
No other editions are linked here.