Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy · OPW24/0118

of 80

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

   19.             Emergency Response Scenarios
                                                                                                                    Proposed Controls                                                                             Responsible
                                                                                                                                                                                                                    Person




                                                    HC
    Activity           Hazard




                                       Risk
                                                                                                                                                                                                       Risk




                                      Initial
                                      Rating
                                                                                         (1/Elimination 2/Substitution 3/Isolation 4/Engineering 5/Administration 6/PPE)                             Residual



    19.1           Arrested Fall in a Harness
                                                                                                                                                                                                                Site
Planning for an    Activity          HIGH       5        Woollam Emergency Control Organisation established. Each member shall complete the applicable training modules in ELMO.                                Management
arrested fall in   planning,
harness rescue.    hazard
                   identification,
                   resourcing, and                                                                                                                                                                              Site
                                     HIGH       5        Project specific Emergency Preparedness and Response Plan completed prior to work commencing on the project.                                           Management
                   implementation
                   of controls

                                                                                                                                                                                                                Site
                                     HIGH       5        Work at Heights Permit completed, reviewed, and authorised prior to the work activity commencing.                                                      Management
                                                                                                                                                                                                                Contract Partner

                                     HIGH       5        The SWMS submitted by the Contract Partner shall outline their rescue procedure for this activity and their workers have been                          Contract Partner
                                                         trained to perform a rescue

                                     HIGH       5        Workers involved in the rescue can provide evidence of a current Safe Work at Heights qualification - RIIWHS204E - Work safely at                      Contract Partner
                                                         heights

                                                                                                                                                                                                                Site
Use of Specific    Rescue            EXTREME    3        Rescue equipment items identified in the Emergency Preparedness and Response Plan are readily available and in serviceable                             Management
Equipment          equipment -                           condition.
                   Fall arrest /
                   restraint
                   system items      EXTREME    3        The worker to use the fall arrest / restraint equipment shall inspect each item prior to commencing the activity. Any item found to                    Contract Partner
                   defective,                            be defective, faulty, or damaged shall be immediately removed form service.
                   faulty, or
                   damaged.
                                     EXTREME    3        Each item of fall arrest / restraint equipment shall be inspected every 6 months by a Rigger or qualified height safety inspector.                     Contract Partner
                                                         Items that exceed the life span of 10 years from date of manufacture shall be removed from service and destroyed.

                                                                                                                                                                                                                Site
                   Rescue EWP not    EXTREME    3        An EWP with the applicable height capacity shall be readily available.                                                                                 Management
                   available and /
                   or licensed                                                                                                                                                                                  Contract Partner



                                                                                                                                                  Project Hazard/Risk Assessment / Page 130 of 160

Used in these records

About this file

File size
836 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Project Hazard_Risk Assessment Ozcare Noosa RACF 23-042024 STP24-0253 Application for Operational Works Fire Trail - 80 Cooyar Street Noosa Heads - Copy.pdf · 836 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.