               46.    Prior to any works commencing on site or prior to the issue of the building permit, a bank
                      guarantee or a bond of $5,000 must be lodged as security for the protection of the trees
                      identified for retention identified on the approved tree retention plan. The bond:
                      a.       may be drawn upon by Council in its entirety if any one tree identified for retention is
                               damaged to the point where the tree cannot be saved (as confirmed by the project
                               arborist and agreed in writing by Council)
                      b.       will be returned upon practical completion of all the operational works relating to this
                               development.


                OPW22/0140 - DEVELOPMENT PERMIT FOR OPERATIONAL WORKS (DRAINAGE WORK,
                                LANDSCAPING, STORMWATER & EARTHWORKS)
               ENGINEERING
                      APPROVED PLANS
               47.    Development authorised by this approval must be undertaken generally in accordance with
                      the Approved Plans listed in the tables below. The plans must be amended to incorporate
                      the amendments listed within the table below and resubmitted to Council prior a prestart
                      meeting being held.

                           Plan No.     Rev. Plan/Document Name                                      Date

                           C30          D     Bulk Earthworks       Plan   prepared    by   Recor 15 March 2023
                                              Consulting

                           C31          D     Bulk Earthworks Sections prepared by Recor 15 March 2023
                                              Consulting

                           C40          D     Roads & Drainage Layout Plan prepared by Recor 15 March 2023
                                              Consulting

                           C41          D     Roads & Drainage Details prepared by Recor 15 March 2023
                                              Consulting

                           C42          D     Stormwater Drainage Sections prepared by Recor 15 March 2023
                                              Consulting

                           C43          D     Driveway Longsection         prepared    by   Recor 15 March 2023
                                              Consulting

                           CD-001       A     Specification Notes, prepared by, Project Urban        24/11/2022

                           CD-102       A     Landscape Plan – Second Floor, prepared by, 27/02/2023
                                              Project Urban

                           CD-103       A     Landscape Plan – Second Floor, prepared by, 24/11/2022
                                              Project Urban

                           CD-600       B     Tree Retention and Removal Plan, prepared by, 24/11/2022
                                              Project Urban

                           CD-900       B     Construction Details, prepared by, Project Urban       28/02/2023

                           -            1     Arboricultural Impact Assessment, prepared by, 30/11/2022
                                              Consult Arborist

                                                                                                        Page 29 of 42

Document Set ID: 22374890
Version: 10, Version Date: 06/08/2023
Log in to download the original file

Delegated Report - Code - Planning MCU22 0087 [As Published].pdf · 11.9 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.