MCU STA - 132 Solar Road - Planning Report
PO4 AO4.3
Visitor accommodation is located such that it Accommodation
preserves the safety of guests and does not a) within a designated transport noise
impact on the function of infrastructure corridor; or
including: b) within 100 metres of an existing
a) the major road network; electricity substation—
b) the North Coast railway line; i. incorporates noise attenuation
c) existing and future electricity supply measures to mitigate noise
infrastructure; and impacts and;
d) water supply and waste water ii. guests are not accommodated in
treatment. lightweight shelters (such as tents,
yurts, recreational vehicles, or
relocatable dwellings).
Complies
The subject site is not located:
Applicant’s Response
• Within a designated transport noise corridor, or
• Within 100 metres of an existing electricity substation.
PO4 AO4.4
Visitor accommodation is located such that it Accommodation within a water catchment
preserves the safety of guests and does not area relies on minimal clearing of natural
impact on the function of infrastructure vegetation, earthworks, and movement of
including: sediments or nutrients from the site and any
a) the major road network; on-site disposal of effluent is to a secondary
b) the North Coast railway line; treatment standard.
c) existing and future electricity supply
infrastructure; and
d) water supply and waste water
treatment.
Complies
The subject site is located within a Water Resource Catchment area.
Applicant’s Response However, the applicant proposes to utilise the existing two storey
detached residential dwelling for Short-term Accommodation, and
no changes are proposed to the existing dwelling or land.
No further clearing of natural vegetation or earthworks are proposed.
PO4 AO4.5
Visitor accommodation is located such that it Accommodation does not occur within 400
preserves the safety of guests and does not metres of a sewerage treatment plant.
impact on the function of infrastructure
including:
e) the major road network;
f) the North Coast railway line;
g) existing and future electricity supply
infrastructure; and
water supply and waste water treatment.
Complies
Applicant’s Response The subject site is not located within 400 metres of a sewerage
treatment plant.
RG Strategic Town Planning Report – Short-term Accommodation 18