13. All refrigeration plan, including motors, shall be situated within the building or suitably
provided with noise reduction and shall be located as to prevent disturbance beyond the
subject land.
14. Airconditioning units shall be located in a manner which prevents noise disturbance beyond
the subject land.
15. All reasonable precautions shall be taken to ensure that the proposed use does not interfere
with the amenity of the neighbourhood by reason of noise, vibration, smell, fumes, vapour,
steam, soot, ash, dust, waste water, waste products, grit, oil or otherwise.
Engineering
16. The developer must provide at least 22 off-street car parking spaces, comprising 8 covered
spaces and 14 uncovered spaces, and access thereto which are to be provided with a sealed
pavement.
17. The developer is to abide by the Department of Main Roads requirements in that all vehicular
access is to be taken from Elisabeth Street.
18. All separate, adjoining lots the from part of this application are to be amalgamated into one
undivided lot in accordance with Section 5.11 of the Local Government (Planning and
Environment) Act, Prior to the issue of a Building Approval.
19. The developer shall bear the cost of alteration of by public utility or other facilities
necessitated by the development of the land or associated construction works external to the
site.
20. Connection to Council’s existing water supply and sewerage reticulation systems at the
developer’s expense to the standards and requirements for Council’s Shire Engineer.
21. The developer shall pay contributions in accordance with Council’s Policy on Water Supply
Headworks Contributions and Sewerage Headworks Contributions. An estimate only of the
charges as at July 1998, under the current policy is as follows:-
Water Supply $13,009
Sewerage $15,135
TOTAL: $28,144
Please note that the headworks charges will alter in accordance with Price Index variations
or if any amendment is made to Council’s policy.
Headworks contributions shall be calculated and paid in accordance with either of the
following alternatives:-
21.1. Payment to be made prior to the issue of a Development Permit for building works in
the amount calculated under the Policy at the date; or
21.2. Payment may be deferred to a date:-
21.2.1. prior to Council sealing plans of the development for titling purposes;
21.2.2. prior to the issue of a Certificate of Classification for any building works; or
21.2.3. prior to commencement of the approved use at the relevant premises;
whichever is sooner. Payment of deferred headworks contributions shall also be subject to
the following requirements:-
21.2.4. payment of a bonding fee in the amount of $150 and submission of a
trading bank guarantee to the value of the headworks assessed at the time
of submission, plus 20%, prior to the issue of a Development Permit for
building works;
Page 3 of 7
Document Set ID: 22711656
Version: 3, Version Date: 01/12/2023
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Minor Change - 51997 2399 02 [As Published].pdfRelated documentApplication case desk ↗
About this file
- File size
- 156 KB (small file)
- File type
No other editions are linked here.