2019-05-07 Services & Organisation Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
SERVICES & ORGANISATION COMMITTEE MEETING AGENDA 7 MAY 2019
1. OPERATIONAL PLAN UPDATE
Only the major initiatives are included in the Operational Plan with day to day “business as usual”
activities included in Branch Plans.
The Branch Plans are being used by Managers to manage day to day activities. They are an
effective tool for ensuring that all of the “business as usual” activities are undertaken and that any
minor projects are followed through. They are reported to Council by Directors on a quarterly
basis and those reports are on this round of Council meetings.
Details of each Operational Plan project is set out in Attachment 1 with an assessment of
whether the issue is completed, on track or behind schedule. Comments are also provided for
the information of Councillors about the status of each issue. It is important to note that this is
“as at 31 March” i.e. the end of the third quarter and in some instances, the actions have been
advanced further since that time.
There are 28 initiatives in the 2018/19 Operational Plan. The current status of those projects is:
Status Quarter 1 Quarter 2 Quarter 3
(July – Sept 2018) (Oct – Dec 2018) (Jan – Mar 2019)
Not started 3 2 0
Behind Schedule 3 3 5
On Track 22 20 20
Completed 0 3 3
The table below highlights some specific Operational Plan issues that may be of interest to
Council.
Initiatives Comment
Environment Strategy A draft Environment Strategy is currently out for community consultation.
Yurol and Ringtail Forest The Joint Transition Committee has met three times to manage the day-
Project to-day transition process. The first tranche of the transfer of State
Forest to National Park (approximately 340 ha) is almost complete.
Noosaville Library This project was completed and officially opened on 30 November 2018
refurbishment and the new refurbished library is operating well.
New Planning Scheme The draft planning scheme is currently open for community consultation
until 20 May 2019. A comprehensive community engagement process
has been underway since the draft scheme was adopted for the purpose
of community consultation.
Noosa Transport Strategy Council adopted a series of actions to alleviate the transport congestion
over the Christmas and Easter periods. Those actions were
implemented successfully over those periods and the results will be
reported to Council in due course.
Asset Management Plans The Stormwater Asset Management Plan was adopted in February
2019.
Noosa North Shore This project was delayed as a result of native title issues associated with
Campground the land swap but the project is proceeding for the areas not affected by
that issue. A tender for project work closed in December 2018 and we
are also awaiting the result of a State infrastructure grant application.
Page 11 of 71
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.