OPERATIONAL PLAN 2018-19 PROGRESS REPORT
LONG TERM PLANNING FOR NOOSA SHIRE
No. Project Responsibility Update Status
1 Complete State interest review and community Director Environment & Sustainable Community consultation is underway until 20 May 2019. A series of pop-ups On track @
consultation for draft new Noosa Planning Scheme Development across the Shire have occurred with hundreds of enquiries about the new
draft scheme occurring. Once public engagement finishes, submissions will
be reviewed and the scheme will be reviewed for any proposed changes prior
to coming back to Council. Further state sign off is required prior to final
adoption.
2 Progress remaining matters associated with the Property Manager The primary action plan for the Foreshore Plan comprised the 10 items in On track @
Noosaville Foreshore Land Use Master Plan Council’s resolution. All have been actioned, and those requiring
ownership/action by other Departments (Items E, F, G & H) have been
discussed with those Departments to progress.
3 Implementation of Noosa Transport Strategy priority Director Infrastructure Services Easter period transport trials underway. Evaluation of trial data to be reported On track @
actions to Council post-Easter.
4 Commence the Noosa North Shore Campground Property Manager Tender closed December 2018. Currently awaiting decision regarding Behind Schedule @
redevelopment potential Queensland government grant funding.
5 Complete detailed Asset Management Plans Asset Planning Manager Council adopted the Stormwater Asset Management Plan at the February Behind Schedule Oo
2019 Council meeting. Ongoing development of the Buildings and Facilities &
Parks and Playgrounds Asset Management Plans.
6 Finalise Climate Change Adaptation Plan and initiate Director Environment & Sustainable Updated modelling (i.e. additional scenarios) completed on schedule. Work On track @
implementation of actions Development on risk analysis delayed due to above but now progressing. Biodiversity
component being finalised. Submission of Coastal Hazard Adaptation Plan to
State still expected by end 2018/2019 Financial Year. The Climate Change
Adaption Plan (encompasses the whole of LGA) is partially delayed due to the
diversion of resources for draft planning scheme consultation.
Page 17 of 71See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.