Capital Program 2024/2025 Delivery Status · Attachment 1 - Capital Program Delivery Status

of 5

Text shows just the words. Original shows the document exactly as it was published.

Very large file (14.8 MB): the original may take a few minutes to open or download. The page text below is quick to read.

SERVICES & ORGANISATION COMMITTEE MEETING REPORT 12th August 2025



Attachment 1 - Projects completed during Q4 2024/25 financial year.
Sealed Roads Network


Sunrise Beach - David Low Way
– Retaining Wall Construct
A new three-metre-wide pathway
beside David Low Way at Sunrise
Beach intended to improve safety
for pedestrians, cyclists and
mobility scooter users is now
open. Retaining wall construction
completed ahead of schedule.




Noosaville, Seagull Park –
Pathway Renewal
Footpath renewal works
complete.




                                                                      Page 1 of 5
Full text of the other 4 pages

Page 2

SERVICES & ORGANISATION COMMITTEE MEETING REPORT 12th August 2025




Shire Wide Pathway Renewal
Footpath renewal works complete
at Gympie Terrace Noosaville
(pictured left) and Moorindil Street
Tewantin (pictured right).




Stormwater Drainage
Tewantin, 74 Goodchap Street
Upgraded stormwater network
complete. Works will eliminate a
frequent stormwater overflow
experienced during moderate to
severe rain events at 74
Goodchap Street.




                                                                Page 2 of 5

Page 3

SERVICES & ORGANISATION COMMITTEE MEETING REPORT 12th August 2025




Environmental Assets, Bushland, Tracks and Trails



  Kin Kin – Wahpunga (Trail 4)
  & Woondum (Trail 3) - Trail
  Renewal
  Project update for Q4


  Shelters at McKanes Memorial
  Park, Trail 3




  Hitching rail and trough at
  McKanes Memorial Park, Trail 3




                                                                Page 3 of 5

Page 4

SERVICES & ORGANISATION COMMITTEE MEETING REPORT 12th August 2025



  Smaller Crossing at Ringtail
  Creek Road, Trail 4




Parks & Playgrounds

  Ed Webb Park Upgrade,
  Sunshine Beach
  Works are predominantly
  complete to the timber deck and
  shelter structures. Softscape
  nearing completion with planting
  complete and open space areas
  prepared for turf. Work is now
  focussed on the interface with
  Webb Road to complete the
  kerb and channel replacement,
  footpath extension and bio
  retention pod.




                                                                Page 4 of 5

Page 5

SERVICES & ORGANISATION COMMITTEE MEETING REPORT 12th August 2025



Public Amenities

  Visitor Information Centre
  N38 Amenities, Noosa Heads


  Refurbishment of one of
  Council’s highest use facilities.




                                                                Page 5 of 5

Used in these records

About this file

File size
14.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 1 - Capital Program Delivery Status.pdf · 14.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.