response to information request - 9 Bottlebrush
Attached to the e-mail Response to RFI - 9 Bottlebrush Avenue Noosa Heads - MCU21/0133.
6. Provide an amended earthworks plans that is consistent with and includes the
recommendations of the submitted geotechnical investigation
Please find attached response to the detailed items 1-6 from Recor Consulting Engineers.
In regard to the use of parking bay 1 adjacent to the lift core, the bay has been changed
from a visitor bay to an owner’s bay. The owner will have access to the panel lift garage
door to allow for existing.
An additional visitor parking bay has also been provided for within Bottlebrush Ave.
Detailed engineering design has been included to allow for the parking bay, while allowing
for landscaping, appropriate sightlines and stormwater. It is considered the number of
parking provided onsite and in front of the development meets the Performance Outcomes
for the number and type of vehicles to use the site and the streetscape context.
7. Calculation of gross floor area taken from the external walls and to include the
common walls.
8. Plot ratio not to exceed 0.7:1, or 0.75:1 where small dwelling units are provided
at a ratio of 3:4.
9. Amended pans with compliant plot ratio.
10. Clarification of which part of each level has been included in the site coverage
calculation.
11. The site cover calculation to include all buildings and structures, including
podium areas around the building.
A service void is provided through the building to comply with the required Gross Floor
Area requirements. Updated plans are provided with measurements taken from external
walls and site cover for all buildings.
Page 2 of 4
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.