Traffic Engineering Report

of 26

Page text shows just the words. Original shows the document exactly as it was published.

3           Site Access Arrangements
3.1         Proposed Access Arrangements
Table 3.1 details the site access design and location standards, proposed provisions and compliance.

Table 3.1: Noosa Eumundi Road Access Requirements, Proposed Provisions and Compliance
            Design Aspect                      Council Requirement                Proposed Provision             Compliance
 Minimum Intersection Separation           6m from tangent point of kerb   16m west                            Compliant
                                                                           22m east (to pedestrian crossing)   Compliant
 Pedestrian Visibility Splays              2m x 2.5m on exit side          2m x 2.5m on exit side              Compliant
 Sight Distance - 60kph                    Desirable – 83m                 108m to south                       Compliant
                                           Minimum - 65m                   >90m to north                       Compliant
 Design Type                               Type B2 (IPWEAQ)                Type B2 (IPWEAQ)                    Compliant
 Width/ Entry and Exit Widths              6-9m                            6.2m                                Compliant
 Minimum Queuing Provisions                -                               1 car (8.4m)                        See note below
 Gradient of first 6m                      1:20 (5%)                       Generally Flat                      Compliant

The proposed access arrangements generally comply with Council requirements, however the following item
is resolved with a performance solution.

Queuing

The development proposal provides 8.4m queuing (1 car) to the proposed first conflict point.

As detailed further in Section 6, it is expected that the peak vehicle movements into/out of the site will be
17vph during the peak-hour periods. The probability (using the Poisson distribution method) of more than 1
vehicle entering the site at the same time (or say within a 30 second period whilst a car is manoeuvring
in/out of initial parking spaces) and all requiring to queue in advance of the first internal car parking space,
extending back onto Eumundi Noosa Road, is less than 1%. As such, the proposed internal queuing capacity
of 1 vehicle is sufficient to cater for the 99th percentile entry queue of the site and is therefore considered
acceptable.

With respect to entry queue capacity, it is noted that the car parking areas accessed from this driveway will
comprise of low-turnover residential and visitor parking spaces. It is also proposed that the first parking
spaces within the site will be residential and PWD parking, which are expected to only turn over 1-2 times a
day. Therefore, the probability of a car manoeuvring from these spaces at the same time as another car
trying to enter/exit will be low.

Overall, the proposed access arrangements are considered suitable for the proposed development and ‘fit
for purpose’.




Site: 99, 101 & 105 Eumundi Noosa Road, Noosaville                                                                              10
Reference: 20BRT0474
Log in to download the original file

Traffic Engineering Report.pdf · 6.7 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.