PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 20 MAY 2014
ENGINEERING
External Works
41. The David Low Way frontage to the subject site and the intersection of David Low
Way with the unnamed road (Road 151) at the south eastern corner of the subject
site must be upgraded. The works must be generally in accordance with drawing No.
13512-1 dated 21 March 2014 prepared by Holland Traffic Consulting and
undertaken in accordance with an Operational Works approval. The works must
include in particular:
(a) construction of the required intersection islands and linemarking
(b) construction of any necessary widening on the eastern side of David Low Way
opposite the intersection, with any works restricted to a maximum incursion
width of 0.5m
(c) construction of new kerb and channeling and bus stop in the David Low Way
frontage of the site
(d) any associated underground stormwater drainage
(e) any associated realignment or relocation of existing services and lighting
(f) widening and sealing of the existing road pavement
(g) construction of any associated retaining structures
(h) construction of a shared pathway in accordance with the conditions of this
Decision Notice
(i) provision of landscaping in accordance with Council requirements
42. The existing formation of the unnamed road (Road 151) must be upgraded as
required to cater for the proposed development. The works must be undertaken in
accordance with an Operational Works approval and must include in particular:
(a) repair and/or replacement of any damaged sections of kerb and channel
(b) repair and/or replacement of any substandard sections of pavement
(c) repair and/or replace green bike land pavement treatments in accordance with
Council requirements
(d) any extension to the formation to facilitate access to the subject site
(e) relocation or extension to the existing stormwater system, services and property
accesses
(f) a 30mm asphalt overlay at the completion of the construction works
Road Widening
43. The property boundary along David Low Way must be realigned to be a minimum of
2.5m from the new kerb line of the bus stop. The affected parts of the site must be
dedicated as “Road”.
Site Access and Driveways
44. A sealed access driveway must be provided from the unnamed road (Road 151) to all
parking and manoeuvring areas of the development. The works must be undertaken
in accordance with an Operational Works approval and must include in particular:
(a) a driveway crossover in accordance with IPWEAQ standard drawing SEQ –
R052
(b) suitable safety measures, including warning signage, to improve driver
awareness of pedestrians and enhance pedestrian safety. Warning signage
must be provided near the exit to warn motorists of pedestrian movement along
the frontage street
(c) fencing or vegetation near the driveway must comply with the sight line
requirements as defined in AS/NZS2890.1:2004. The sight lines must be shown
on nay plans submitted for Operational Works approval.
Page 13 of 143
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.