PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 20 MAY 2014
Car Parking
45. A minimum of 85 car parking spaces must be provided and marked on the site and
made available and accessible at all times while the use is open for business. The
works must be undertaken in accordance with an Operational Works approval and
must include in particular:
(a) 13 staff parking spaces within the total, which are clearly marked for that
purpose
(b) provision of vandal resistant public lighting with intensities to satisfy the
requirements of Australian Standard AS1158: Public Lighting Code
(c) dimensions, crossfalls and gradients in accordance with Australian Standard
AS/NZS 2890.1:2004 and AS/NZS2890.6:2009 for the relevant user class
46. All car parking areas and access driveways must be maintained exclusively for
vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
47. Directional signage must be provided to direct customers to the car parking spaces
provided on site.
Service Vehicles
48. Service vehicle parking, manoeuvring and standing spaces must be provided on the
site. The works must be undertaken in accordance with an Operational Works
approval and must include in particular:
(a) regular access for a SRV
(b) regular access for a LRV
(c) regular for a waste collection vehicle
Pedestrian and Bicycle Facilities
49. Pedestrian and bicycle facilities must be provided for the development. The works
must be undertaken in accordance with an Operational Works approval and must
include in particular:
(a) a 2.5 metre wide concrete shared pathway within the road verge for the entire
length of the site’s frontage to David Low Way
(b) a 2 metre wide concrete pathway within the road verge for the length of the
site’s frontage to the unnamed road (Road 151) extending from the intersection
with David Low Way to the entrance to the site
(c) reinstatement of road cycle lanes (minimum of 1.5m in width) and green
pavement treatments to delineate bike land and neatly integrate with existing
bike land treatments.
Stormwater Drainage
50. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval and must include in particular a detailed Stormwater Management
Plan (including MUSIC modeling and reporting) for the construction and operational
phases of the development that:
(a) demonstrates that there is no net increase in stormwater runoff (volume and
frequency) from the site
(b) includes stormwater quality improvement devices that achieve the current “best
practice” water quality objectives
(c) Sediment and Erosion Control Plan during the construction phases
(d) Provision to cater for the stormwater runoff from the adjoining properties and
roads that drain through the site, including registration of drainage easements
Page 14 of 143
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.