PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 20 MAY 2014
Page 57 of 143
PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 20 MAY 2014
Document No: 001
Effective date: 6 March 2014
Next Review Date: 30 May 2014
Unitywater Interim Connections Policy
The Staged Connection category is primarily intended for network Connections for multi-
stage subdivision estates and master-planned communities. This category is also for
any Connection that will be staged over two or more approvals, whether or not Network
Infrastructure works are also involved,
Schedule 1, Table 3 - Connection Criteria for Staged Connections sets out the
Connection Criteria that Unitywater will assess applications in this category against.
3.3. Applications and Approvals
a. Requirements for all categories of Connections
Schedule 2 sets out the following:
« the way to apply for a Water Approval; and
* the timeframes for decisions for Connections.
Schedule 3, Table 6 - Amendments of conditions of Water Approvals sets out the way to
amend conditions of Water Approvals.
3.4. Construction Maintenance and Defects Liability
Unitywater's construction maintenance and defects liability requirements are those as
specified in Unitywater’s Connections Administration Manual.
Unitywater's Connections Development Manual establishes the requirements and processes
for the construction and acceptance of all water and sewerage infrastructure that will be
constructed by a developer and handed to Unitywater as a ‘Donated Asset’ to operate and
maintain.
3.5. Miscellaneous
a. Conditions for when water approval for a Connection lapses
A Water Approval for a Connection has effect until it lapses under a condition of the
approval.
Unitywater’s conditions for when a Water Approval lapses are that all categories of
Water Approvals (including Standard Connections, Other Connections and staged
Connections) lapse 4 years after the date the Water Approval takes effect’.
Note: Application to extend or otherwise aller the lapsing period of a Water Approval may be made to Unitywater
in the way described in Schedule 3, Table 6 - Amendments of conditions of Water Approvals Step.
b. Agreements
The Act provides for water infrastructure agreements to be entered into as provided
under s.99BRDA of the Act, and for water approval condition agreements to be entered
into as provided under s.99BRAL of the Act.
The period for executing any agreement referred to in s S9BRDA and s.99BRAL of the
Act is 6 months starting from the day after:
* Water approval takes effect in accordance with s.99BRAO of the Act.
Copyright © Unitywater Page 4 of 26
Printed copies are uncontrolled
Page 57 of 143See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.