PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 20 MAY 2014
Page 76 of 143
Document No; "[Click to insert document #]"
Revision No: 001
Effective date: 6 March 2014 _————
Next Review Date; 30 May 2014
Unitywater ; ; ' ; i
ae Interim Connections Policy — Schedule 2: Applications
Table 5 - Staged Connections and Other Connections Application and Approval Information
Step Connections Policy Provision
Application for: How do! apply for a Staged Connection or Other Connection?
Other Connection or ¢ The Applicant must do all of the following:
Staged Connection (each o Complete the Unitywater approved application form (available on Unitywater’s website at www.unitywater.com),
stage) including supplying the plans and other information specified in the form;
Note: The steps, requirements oc Pay the fee stated in Unitywater's Fees and Charges Schedule;
and timeframes outlined in this
table apply for each stage in a oc If the applicant is not the owner of the land related to the Connection, provide the land owner's written consent to the
Staged Connection application.
Note: This also includes the written consent of land owners related to the Connection e.g, the nearest suitable sewerage main may be located on an
adjoining private property and work will need to be carried out to this main to provide the Connection. The written consent of this land owner is also
required to accompany the application.
Assessment What will the application be assessed against?
Criteria and timeframes e The application must be assessed against: (Act, s.99BRAG(3))
© The Connection Criteria listed in Schedule 1, Table 2 — Connection Criteria for Other Connections or Table
3 - Connection Criteria for Staged Connections of this Policy as applicable to the category of Connection;
o The SEQ WS & S Design and Construction Code;
o Any other matter Unitywater considers relevant to the Connection or supply of its water or sewerage services.
What is the timeframe for deciding the application?
e Decision timeframe - if no extra information required:
Copyright © Unitywater Page 23 of 28
Printed copies are uncontrolled.
Page 76 of 143See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.