2014-05-20 Planning & Organisation Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
PLANNING & ORGANISATION COMMITTEE MEETING AGENDA 20 MAY 2014
Page 77 of 143
Document No: "[Click to insert document #]"
Revision No: 001 ——————
Effective date: 6 March 2014
Next Review Date: 30 May 2014
Unitywater : . : ‘ wos
ae Interim Connections Policy — Schedule 2: Applications
o Total decision timeframe - up to 25 business days (or longer period agreed by the Applicant) as follows:
= Up to 20 business days to assess the application starting on the day after Unitywater receives the complete
application;
* Upto 5 business days after the decision is made to give the Applicant notice of the decision.
e Extended decision timeframe - if extra information is required from Applicant:
o Upto an extra 25 business days (or longer period agreed to by the Applicant) as follows:
* Up to 20 business days to assess the application starting on the day after Unitywater receives the Applicant's
compete response to the request of extra information and the application will be held in abeyance until the
Applicant's complete response is received:
= Up to 5 business days after the decision is made to give the Applicant notice of the decision.
Note: The application is taken to have been refused if the Applicant is not given a decision notice within the applicable timeframes specified above
(s.99BRAI(4)).
e Lapsing — the application lapses if the Applicant has not responded to the request for extra information within 6 months
after the request was made and an application for internal review (failure to decide) has not been applied for in
accordance with Part 4, Division 2 of the Act.
What happens when request is granted?
Unitywater gives the Applicant a decision notice within 5 business days after the Staged Connection or Other Connection is
decided.
The decision notice will include: (Act, s. 99BRAU, s.99BRAV, s.99BRCJ)
© any Water Approval conditions imposed;
o the following charges levied (to the extent applicable):
= Charges stated in Unitywater’s Fees and Charges Schedule to the extent applicable for the Connection;
* The Connection Charge/Act, s.99BRAV(1)(a) ;
= The Property Service Works Charge (Act, s.99BRAV(1)(b));
Copyright © Unitywater Page 24 of 28
Printed copies are uncontrolled.
Page /7 of 143See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.