Attachment C- REC14.0005 Negotiated Decision Notice

of 10

Page text shows just the words. Original shows the document exactly as it was published.

                                                                                  REC14/0005

28.   Stormwater retention systems and gross pollutant traps must maintain a minimum
      clearance of 1.5 meters from Unitywater water supply and sewerage infrastructure

29.   Tree plantings must maintain a minimum horizontal clearance of 1.0 metre from
      Unitywater water mains and 1.5 metres from Unitywater sewerage mains. Landscaping
      plants within these clearances must be low growing when mature and suitable
      Unitywater approved varieties.

30.   Construction works undertaken in the vicinity of Unitywater water supply or sewerage
      infrastructure must not adversely affect the integrity of the infrastructure. All costs
      associated with repair, replacement or alteration of infrastructure must be met by the
      applicant.

5     REFERRAL AGENCY CONDITIONS

Not Applicable

6     ADVISORY NOTES

The following notes are included for guidance and information purposes only and do not form
part of the assessment manager conditions:

      Building and Construction Industry (Portable Long Service Leave) Levy
1.    The QLeave levy must be paid prior to the issue of a development permit where it is
      required. Council will not be able to issue a Decision Notice without receipt of details
      that the Levy has been paid. QLeave contact: 1800 803 481 (free call) or (07) 3212
      6855.

      Co-ordination of Operational Works Assessment
2.    Additional application fees apply to Operational Work applications where the different
      aspects of the works are lodged separately. Significant savings in application fees will
      result if all works are lodged in a single application.

      Preparation of a Preliminary Construction Management Plan
3.    A preliminary Construction Management Plan must be submitted with the Operational
      Works application and must address the following:
      (a) traffic management during all aspects of the construction phase including:
           (i)   a Traffic Management Control Plan in accordance with the Manual of
                 Uniform Traffic Control Devices (MUTCD) detailing all temporary signage
                 and traffic control measures prior to construction
           (ii) maintenance of safe pedestrian access for the areas affected by the works
                 during and after daily construction has ceased
           (iii) proposed fencing to the site during the construction phase of the
                 development
           (iv) approval of the Traffic Management Control Plan by the Department of
                 Transport and Main Roads (DTMR) for any works on State controlled roads
           (v) provision for worker car parking
      (b) maintenance and protection of water quality and existing drainage lines through
           the construction site, through the implementation of appropriate erosion and
           sediment control measures


                                                                               Page 6 of 10
Log in to download the original file

Attachment C- REC14.0005 Negotiated Decision Notice.pdf · 113 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.