Amended Noosa Project Restoration Plan V12_5
Attached to the e-mail OPW22/0029 - SRA application correspondence - Referral agency response – with conditions.
This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).
Log in to see the plans as drawninvertebrates recruit Recruitment > once every year for oyster recruitment, as
to the restoration mortality (count/m2) the following years. per specifications. See
substrates10 per restoration site Annex 7: Engineering
Specifications –
Within 6-8years: Rectifications Table
Density of rock oysters Seeded oyster cultch
at restoration site and live oysters added
average of > 200 to rock substrate to
individuals/m2 augment recruitment
as per specifications.
4+ age classes of rock Substrate height
oysters present at adjusted to optimise
restoration site (= oyster recruitment, as
approx. 2 cohorts of per specifications. See
oysters reproductive) Annex 7: Engineering
Specifications
> 5% of rock oyster
population at the site
is 3+ years old
Increased density of
oyster recruits with 3-
4 reproductive cycles
5 times more epifauna
on oyster habitat than
on surrounding
sediment
3. Community use and enjoyment of oyster restoration sites
Oyster beds do not Visually monitor Ongoing - report Maintain complaints
significantly impact community use of the significant complaints mechanism as per
community safety, restoration sites or incidents to Section 8.5 Complaints
access and/or use of authorities management
the Noosa River If a site needs closer
estuary including Fish monitoring, as Annually - report Modify oyster reef
Habitat Areas. directed by a public feedback received and patch/es or signage,
authority, then the responses in project aids to navigation as
project will establish a report per Section 8.6
specific action for that Contingency plan
purpose.
Report feedback and
Maintain records of adaptive management
partner or community responses in the
feedback and reported project annual report.
evidence of substrate
or signage vandalism
or vessel strike.
Records will include:
69
See the original
The page text is free to read. Viewing or downloading an original file needs an account.