RFI traffic updated 2016
Attached to the e-mail MCU15/0111 Information Request Response to Concurrence Agency - 2-4 Lamonts Rd & 19 Trading post Rd, Cooroy - email 1 of 2.
Total 55vph total two-way development traffic at Elm Street (Cooroy Connection Road) / Lamont Road. During
the morning peak hour, 17vph travel towards the site, and 38vph travel away from the site. The reverse is true
during the evening peak hour.
At Elm Street (Cooroy Connection Road), it is anticipated that 90% of the 134vph total two-way development
traffic travels south towards the town centre of Cooroy, and the remaining 10% travels north.
The existing properties along Lamonts Road include several (less than 5) rural residential properties and the
heli-aviation company. It is anticipated that the existing traffic volumes along Lamonts Road is approximately
20vph in both the AM and PM peaks. Therefore during the current morning peak hour, it is anticipated that
around 4vph travel towards Lamonts Road, and 16vph travel away from Lamonts Road. The reverse is
anticipated to be true during the evening peak hour.
At the Elm Street (Cooroy Connection Road) / Diamond Street intersection the existing directional split of traffic
as per TMR intersection count (2013) has been adopted for the following assessment. That is, from the northern
approach 30% of the outgoing development traffic is anticipated to travel east along Diamond Street towards
Noosa and Tewantin, and 70% of the outgoing development traffic is anticipated to travel south towards the
Cooroy town centre and destinations accessed via the Bruce Highway such as Nambour and Brisbane, 15% of
the incoming development traffic is anticipated to originate from the east from Diamond Street and 85% of the
traffic is anticipated to originate from the south at Elm Street.
Please do note that it is anticipated that up to 10% of all trips may occur by PT or active mode shares however the
following assessment is conservative in allowing for 100% car mode share.
3.2 INTERSECTION ASSESSMENT
The future year (2028) traffic volumes for the intersections within the vicinity of the site have been adjusted to include the
anticipated peak hour development traffic volumes. Each intersection is discussed below.
3.2.1 ELM STREET (COOROY CONNECTION ROAD) / PEARSONS ROAD
INTERSECTION
The anticipated future year traffic volumes, including the development traffic, are presented below in Figure 3-1.
AM Peak PM Peak
Hour
Figure 3-1: Elm Street (Cooroy Connection Road) / Pearsons Road intersection, 2028 AM and PM Peak Hour, total
volumes including Development Traffic
B14158.ER02-B | TRAFFIC IMPACT ASSESSMENT | PALM LAKES RESORTS COOROY RETIREMENT COMMUNITY | 12
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.