Construction Management Plan


[OCR of page images]
Construction Management Plan deluca

 

CERTIFIED

~ ASANZ

   

CERTIFICATION...

deluca

CONSTRUCTION
MANAGEMENT PLAN
Log in to download the original file

Construction Management Plan V2.pdf · 1.3 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

Full text of the other 14 pages

Page 2

Construction Management Plan

Table of Contents
  Amendments ................................................................................................................................................... 2
  Distribution ...................................................................................................................................................... 2
1.0          Introduction .................................................................................................................................... 4
  1.1             Purpose ............................................................................................................................................ 4
  1.2             Scope ............................................................................................................................................... 4
  1.3             Proposed Works .............................................................................................................................. 4
  1.4             Site location ..................................................................................................................................... 4
  1.5             Precedence ...................................................................................................................................... 5
  1.6             Interface with other project plans and processes ........................................................................... 5
2.0                Construction Management ............................................................................................................. 6
  2.1             Approach ......................................................................................................................................... 6
  2.2             Approvals ......................................................................................................................................... 6
  2.3             Site security ..................................................................................................................................... 7
  2.4             Public / Worker safety ..................................................................................................................... 7
  2.5             Hoarding and Temporary Fencing ................................................................................................... 7
3.0               Construction Methodology ............................................................................................................. 8
  3.1       Demolition and excavation .............................................................................................................. 8
  3.2       Substructure works.......................................................................................................................... 8
  3.3 Structure ................................................................................................................................................... 8
  3.4       Services and finishes ........................................................................................................................ 9
  3.5       External works ................................................................................................................................ 9
  3.6 Construction sequence and planning ........................................................................................................ 9
  3.7 Material handling .................................................................................................................................... 10
  Material handling will be complete manually around the site, using mechanical aids as required. ............ 10
  3.7.1 Mobile cranes ....................................................................................................................................... 10
  3.7.2 Concrete handling ................................................................................................................................ 10
  3.7.3 Rubbish removal ................................................................................................................................... 10
4.0         Environmental ............................................................................................................................... 11
  4.1             General .......................................................................................................................................... 11
  4.2             Noise and vibration management ................................................................................................. 11
  4.3             Dust management ......................................................................................................................... 11
  4.4             Stormwater and sediment control ................................................................................................ 11
5.0               Appendices ...................................................................................................................................... 1
   5.1            Appendix 1 – Site Layout 1
   5.2            Appendix 2 - Erosion and Sediment Control Plan
   5.3            Appendix 3 - Construction Program




Authorised Managing Director                                     UNCONTROLLED WHEN PRINTED                                                            Page 1 of 14
Commencement Date: 27 August 2020                                     IMS-4-T3 Version 3                                                Review Date: 27 August 2022

Page 3

Construction Management Plan
AMENDMENTS & DISTRIBUTION

Amendments

   (a) All controlled copies of this plan are version numbered and are subject to amendment as required and the
       relevant pages within the plan are replaced. The revision system is administered by the administrator.
   (b) Amendments are identified by the next consecutive issue indicator and the date of issue.
   (c) The project manager is required to give consideration to a re-issue of the whole plan if it is considered that
       the number of changes to the plan have a significant impact on the readability and cross referencing of
       the document. All new issues supersede all previous issues.
   (d) The document history table indicates all amendments. Recipients of new issues are responsible for the
       approved disposition of superseded pages and the updating of their copy of the Plan.
   (e) Amendments to this template may be made where specified by blue text with less than / greater than
       symbols < > either side. Amendments are formatted to black prior to issue and the < > symbols removed.
       Click on update table tab at contents page to incorporate changes.
   (f) Amendments are to be approved by the project manager and the document history table amended and
       signed.


Distribution

   Construction management plan re-issues and page revisions are distributed to the selected controlled plan
   holders as listed. Amendment control is as specified as above.
   The plan is retained on site by the project manager who ensures that it is available to subcontractors, workers,
   and others as necessary.
   Where contractually specified, the client is issued with an uncontrolled copy, unless specified otherwise.
   An electronic copy of the plan including amendments and updates are legal records and must be kept in the
   electronic folder for the project and archived according to company recordkeeping requirements.




Authorised Managing Director                 UNCONTROLLED WHEN PRINTED                                      Page 2 of 14
Commencement Date: 27 August 2020                 IMS-4-T3 Version 3                          Review Date: 27 August 2022

Page 4

Construction Management Plan
 Project Details
  Project Name:                        Noosa Youngcare - Residential Care Facility
  Project No:                          7203
  Client:                              Deluca Charitable Foundation Limited
  Location:                            32 Viewland Dr Noosa Heads
  Scope of works:                      Construction of Residential Care Facility
  Duration of Works:                   30 Weeks
  BSA 62822                            ABN 80 055 193 514                      ACN 055 193 514


 Document Approval and Control
  Approval                             Name and Role                           Signature                 Date
  Prepared by:                        Jade Randall HSEQ Advisor                Jade Randall
  Project Manager Approval:           Glenn Ricketts


 Document Control & Related Documents
 This Construction Management Plan is to be read in conjunction with the following documents:
  1. Work Health and Safety Management Plan
  2. Environmental Management Plan
  3. Emergency Management Plan
  4. Traffic Management Plan
  5. Project Risk Assessment and Register

 Construction Management Plan – Document History
 Status           Version Details of Changes                                   Date Issued    Approved by:
 Issued              1        Site Establishment & Commencement                18/11/21

 For Review          2

 For Review          3

 Competency
  A person holding a certificate IV OHS or higher qualification or the repealed WHSO qualification or builders license
  under the QBCC scheme and/or underpinning supervisors license or previous S1 S2 S3 now known as G1, 8, 9 can
  conduct or oversee construction management strategies conducted on site including training personal in this
  Construction Management Plan and the associated risk management strategies contained herein.

Persons nominated below have been trained in this Construction Management Plan and its related documents.
 Name of persons trained in this Construction MP & responsible for HSE administration
  Name                              Position                             Date of Training        Signature
 Glenn Ricketts                     Project Manager
 Warren Kane                        Site Manager
 Oscar Hole                         Contracts/Cadet Administrator

                                    Site Foreman
 Jade Randall                       External HSE Resource




Authorised Managing Director                       UNCONTROLLED WHEN PRINTED                                    Page 3 of 14
Commencement Date: 27 August 2020                       IMS-4-T3 Version 3                        Review Date: 27 August 2022

Page 5

Construction Management Plan
1.0 Introduction

1.1    Purpose
This construction management plan has been developed to describe how the project management team shall
implement and conduct its allocated site management responsibilities during the construction phase of the
Noosa Youngcare – Residential. A fundamental aim of this plan is to ensure all construction is properly
facilitated, integrated, and coordinated to deliver certainty to the objectives of the project.

This plan forms part of the DLC Integrated Management System which is accredited to IS0 9001 – Quality
Management, ISO 14001 – Environmental Management, and ISO 45001 Occupational Health and Safety
Management Systems.

1.2 Scope
This plan provides a holistic approach that:
        advises how the project management team will comply with the requirements of the contract
          relating to construction
        defines the project objectives and targets of particular relevance to the construction phase
        describes constraints specific to the construction phase and the project in general
        describes the process for the identification and control of risks specific to the construction phase
        details the proposed strategy for the construction phase, with particular regard to establishment
          resourcing, site organisation and construction controls.

1.3    Proposed Works
The proposed works require the construction of:

This type of construction will have several distinct phases that will require different material handling
strategies to optimise the construction works and minimise impact to surrounding streets, other stakeholders
(such as Noosa Council) and neighbours. Our material handling strategies and construction planning will
require consultation with stakeholders and authorities before implementation.

1.4    Site location
The proposed development site (refer Figure 1) is bounded by Viewland Dr Noosa Heads. The site area for the
works is approximately 3,105m² and is in a Community Facilities Zoning according to the Noosa Council Plan.




Authorised Managing Director              UNCONTROLLED WHEN PRINTED                                  Page 4 of 14
Commencement Date: 27 August 2020              IMS-4-T3 Version 3                      Review Date: 27 August 2022

Page 6

Construction Management Plan




Figure 1 – Site Location


1.5    Precedence
Where ambiguity is detected between the processes and requirements in this plan and the DLC management
system, then the processes nominated in this plan will take precedence.

1.6    Interface with other project plans and processes
The construction management plan forms part of an integrated set of management plans and should be read
in conjunction with these other plans.




Authorised Managing Director            UNCONTROLLED WHEN PRINTED                                Page 5 of 14
Commencement Date: 27 August 2020            IMS-4-T3 Version 3                    Review Date: 27 August 2022

Page 7

Construction Management Plan
2.0 Construction Management

2.1    Approach
The major external constraints on the project are:
     • Maintaining smooth traffic and pedestrians flow with minimal disruptions to the surrounding streets
     • Undertaking works with minimal impact on neighbours
     • Ensuring existing roads maintain in clean state, all erosion and sediment controls in place to protect
        existing council storm water system
     • Main access and parking on viewland Drive. Entry and exit must be set up taking into account existing
        road visibility in order to avoid potential collisions or danger to pedestrians.
           o Traffic control will be used as needed to assist the flow of external traffic
      • Upon commencement, our project team’s immediate tasks will be to:
           o Locate a project office, site accommodation and facilities
           o Undertake a survey of the site and complete a dilapidation report of surrounding properties
               and assets
           o Confirm the locations of existing services and obtain all necessary permits and licences and
               approvals
           o Arrange for the installation of temporary services – power, water and sewer to service the site
               works and the amenities.


2.2    Approvals
The works will be completed in one go without any staging of the works and this will be reflected in the Building
Approval and Development Application. A development approval is available for the works, which includes
clearing and bulk excavation works. Operational works pre-start meeting with Noosa Council is required, prior
to commencement of the building works on site. Development approval contains conditions that certain
reports will need to be completed, submitted and approved before works can commence. Some of these
reports needing approval are:
      • Construction management plan (CMP)
      • Erosion and sediment control (completed by separate contractor as part of the bulk earthworks)

Prior to commencing temporary modification or arrangements, further approvals may be required from Noosa
Council including but not limited to:
      • Application / Notification to Work on Council Property
      • Temporary Footpath Closure Application
      • Crossover application

It is proposed that a single Building Approvals (BA) will be obtained from a qualified private certifying authority
(PCA) prior to commencement on site. It is proposed that the BA will be approved in the following sequence:
       • Structural and foundation works
       • Base Build Certification
       • Services and Internal Fit Out

The staging of the BA’s will allow works to commence, whilst affording time for those works requiring intense
design time such as structural and finishes works. The net effect is an overall reduction in total development
construction time.




Authorised Managing Director                UNCONTROLLED WHEN PRINTED                                     Page 6 of 14
Commencement Date: 27 August 2020                IMS-4-T3 Version 3                         Review Date: 27 August 2022

Page 8

Construction Management Plan


2.3    Site security
The site is to be secured with the use of the temporary construction fences and hoardings around the
perimeter of the construction site which will be established prior to the commencement of the bulk
earthworks. This fencing is securely locked after hours, to prevent un-authorised access to the construction
site. All visitors to the site will be required to report to the site office, and will be appropriately inducted and
registered in a site attendance log book.

It is proposed that the site will be accessed by vehicles via designated entry and exit points (refer Appendix 1
Site Layout Plan). Construction vehicles will be monitored and appropriately cleaned as required when leaving
the site. It is anticipated the development will have approximately 10-15 movements entering/exiting the site
per day, in peak construction periods with approximately 60 movements during the importation of filling
material. All materials handling and unloading will be contained within the site, at designated locations. These
construction handling processes will be managed on site and will not impact the surrounding or neighbouring
traffic movements.

2.4    Public / Worker safety
All site staff and subcontractors will be required to complete a site-specific induction before commencing work
on site. The induction will cover aspects relating to safety and amenity, including access, emergency
evacuation procedures, location of first aid facilities, location of amenities, site hours, material handling, noise
and dust management and environmental management. Prior to commencing works on site, all
subcontractors will be required to submit a project specific work health safety and environmental
management plan. This plan will be reviewed by DLC for compliance with the overall project WHSE
management plans.
As per 2.3 above, the site is currently secured with the use of the existing temporary construction fences and
hoardings around the perimeter of the construction site and is locked after hours to prevent un-authorised
access to the construction site.


2.5    Hoarding and Temporary Fencing
The hoarding construction will consist of temporary wire mesh fence panels to 2.1m high with branded banner
mesh. Gates will be used on all access points onto the site. The branded banner mesh is also utilised to help
control dust and assits by keeping the site safe from the public.




Authorised Managing Director                 UNCONTROLLED WHEN PRINTED                                     Page 7 of 14
Commencement Date: 27 August 2020                 IMS-4-T3 Version 3                         Review Date: 27 August 2022

Page 9

Construction Management Plan
3.0 Construction Methodology
3.1    Demolition and excavation
The bulk earthworks phase will consist of removal of the existing vegetation into a stockpile for processing
onsite and then removed in chip form from site. The topsoil and organic matter will be stripped into stockpiles
for removal during the works. The civil design has been completed to utilise fill material from the site to
minimise the import and export of fill from the site. This will limit the truck movements required to undertake
the works for this project.

Existing services within the site will be located and either capped if redundant or modified if they are to be
used as temporary services for the works according to the approved design. If this is unachievable than all
services will be held temporarily and pumped out or supplied as required. The retaining wall systems will
commence during the bulk earthworks phase and completed to allow the final level to be completed. The
overall Design drawings and specifications can be provided as a standalone document (if required) and is not
included in this CMP.


3.2    Substructure works
From the Geotechnical report we envisage that the substructure works will be a combination of Strip and high
level pad footing arrangements and some minor bored piers. As the detailed excavation is complete,
foundations will be cast, in ground services installed, and the ground will be prepared for the structure and
the slabs will be cast on ground.
3.3 Structure

The structure trades and works will be supported by mobile cranes for lifting of materials, propriety perimeter
edge protection will be used to provide fall protection. Where required perimeter scaffolding will be installed
within our property to allow the external cladding trades to complete their works including painting etc.
Loading and unloading of these materials and equipment will be completed outside of peak traffic times and
the working hours stipulated in the Development Approval.




Authorised Managing Director               UNCONTROLLED WHEN PRINTED                                   Page 8 of 14
Commencement Date: 27 August 2020               IMS-4-T3 Version 3                       Review Date: 27 August 2022

Page 10

Construction Management Plan

3.4    Services and finishes
Prior to slabs being placed in the buildings the services are to be installed in ground as per the approved
design. These works will commence within the building but will not be completed until the fitout of
appliances is complete.

After the structure is complete, the services will commence to be installed. These works will commence within
the building but will not be completed till the façade to that level is complete. The façade provides edge
protection for the men working near the edge and provides weatherproofing for equipment that is water
sensitive. The works will be organised in several passes, with what we term “rough in of services” being the
first pass which is all services that can be installed before the façade is completed. Finishes are normally
commenced in earnest when the façade is installed to that floor. The services will be scheduled to be
completed enough to allow finishes to commence in our programming. Plant, equipment and materials will
be lifted to the floors via several means depending on what stage the building is at.

3.5     External works
The completion of external wall cladding will allow the external works to be commenced and completed in a
timely manner. The works will also include making good any areas that have been affected by the construction
of the project. Once these areas are rectified, casting of external hardstands, footpaths and crossovers will
commence. Landscaping works will commence concurrently in order to stabilise the ground and place soil in
garden beds prior to closing area with new cast concrete slabs.

All environmental controls installed as part of the earthworks, will be monitored and maintained during the
construction of the warehouses. On commencement of external works according the operation works
approvals, existing services like street lights, fire hydrants and the like, will be protected as required during
the construction of the approved works.


3.6 Construction sequence and planning
The locations and types of plant may vary depending on the results of more detailed planning as the design
solidifies and the availability of plant is firmed up. There will be 3 distinct phases requiring different material
handling logic, to construct the building efficiently and minimise impact on surrounding streets and
neighbours.

The phases are:
Phase 1. Site establishment; bulk excavation, detailed excavation and footings installation
Phase 2. Structure
Phase 3. Finishes and external works

Each phase will not happen in isolation. Phase 2 and 3 will happen simultaneously once the structure is
sufficiently complete, to allow the finishes trades to commence on lower levels.




Authorised Managing Director                UNCONTROLLED WHEN PRINTED                                     Page 9 of 14
Commencement Date: 27 August 2020                IMS-4-T3 Version 3                         Review Date: 27 August 2022

Page 11

Construction Management Plan
3.7 Material handling
Material handling will be complete manually around the site, using mechanical aids as required.
3.7.1 Mobile cranes
Mobile cranes will be used throughout the construction sequence and brought to site as required by the
relevant contractor.
3.7.2 Concrete handling
A concrete washout bay will be established on site, for cleaning purposes and dumping small leftovers.
Solidified concrete waste will be regularly removed to local concrete recycling facility for processing.
3.7.3 Rubbish removal
Construction waste will be removed from site by a licenced waste contractor and taken to a transfer facility
for separation. Recycling bins will be used on site for materials separation and returned to suppliers for
processing and recovery.

3.8     Pedestrian Traffic flow around the site
Pedestrian traffic will be a focal point for the Se Luca Site Team as construction works are being carried out in
and around the Project Site. There will be limited footpath access to Viewland Drive during certain times to
complete crossovers, associated works and major deliveries. Chainwire fencing will be used in these areas with
dust/shade cloth installed to the road frontage. The relevant statutory signage will be installed to direct the
local pedestrian traffic around these areas and temporary works will be completed to maintain pedestrian
access outside of working hours.

3.8.1 Workers movements
All staff, subcontractors, suppliers, consultants and the like will be advised that they are to be mindful of the
local residents. All parking is to be located on the site in designated subcontractor and office parking sections.

3.8.2 Material Deliveries/Waste Removal
Deliveries and waste removal will be scheduled during low traffic and off peak times to limit unnecessary
congestion to the neighbourhood.

3.9     Vehicular traffic flow around the site
Vehicular traffic around the construction zone should not be overly affected during the construction of the
new residential care facility. During these times, any necessary traffic control will be provided to limit and
manage the impact on the neighbourhood. Works to these areas will be scheduled and planned in short
durations to limit the affect of congestion to the area.

3.10 Traffic controllers required to coordinate traffic flow
De Luca Corporation will rely on licensed traffic controllers that will be utilized when required. Not all
deliveries will require traffic controllers to be onsite and will be managed accordingly by De Luca’s site staff.
Site and activity specific traffic management plans will be completed when required. The aim of the traffic
controllers is to ensure disruption to the local traffic is kept to minimum.




Authorised Managing Director                UNCONTROLLED WHEN PRINTED                                   Page 10 of 14
Commencement Date: 27 August 2020                IMS-4-T3 Version 3                        Review Date: 27 August 2022

Page 12

Construction Management Plan
4.0 Environmental
4.1 General
The objective of this section is to identify the proposed methods that will be employed to minimise the impact
of noise, vibration and air quality in the vicinity of the development.

4.2 Noise and Vibration Management
The normal hours of work will typically be 7:00am to 6:00pm, Monday to Saturday and 9:00am to 5:00pm
Sunday and public holidays according to the development approval conditions. Noise management will
generally be in accordance with the QLD DEHP environmental noise management criteria. It is anticipated
that all contractor plant is regularly maintained and log books are supplied, ensuring that there are no excess
noise emissions. Where it is practical, electric machinery will be used in lieu of mechanical devices. All
subcontractors will be responsible for managing noise and vibration in accordance with their project specific
management plans.

All after hour’s works will be subject to consultation with the Noosa Council, which will occur at all times, prior
to any works being scheduled. All businesses and surrounding residents will be given notification of all the
proposed after hours works prior to the works commencing, which will include details of the works and the
time to undertake each activity.

4.3 Dust Management
Dust control measures will be implemented as required throughout construction, and will be in accordance
with QLD workplace health and safety regulations and Environmental Protection Act. Dust management will
be most critical during the footing and in-ground services installation, with the subcontractors for these trades
specifically dealing with dust management within their project specific management plans. Measures that will
be employed include:
      • Site Perimeter – A 1.8m high sheeted/shade cloth hoarding will be provided in all areas where
           external works are occurring.
      • Excavation – water down working surfaces as required. Minimise stock piling of material.
           Maintaining stabilised access roads and driveway.
      • Construction – maintain a high level of housekeeping to minimise likelihood of windblown dust.

4.4 Stormwater and Sediment Control
A sediment and erosion control plan has been developed by Neil Mckenzie and Associates (Appendices - 2)
and will be implemented as part of the bulk excavation works. This will be maintained during the construction
phase to ensure that stormwater does not enter adjoining properties, and that all water that enters the council
stormwater system does not contain silt or other contaminants. The following are possible solutions during
each phase of construction which will be developed further and consolidated into the overall management
plan:
    • Excavation – at the commencement of these works, screens and bunding at the perimeter of the site
         where stormwater may run off, will be installed. The existing bunding will be reviewed and maintained
         around the existing stormwater drains
    • Diligent housekeeping will be implemented to minimise risk of dust/debris being washed into pits
    • Construction – Installed drainage pits will be bunded or have filter cloth applied to ensure debris and
         silt does not enter the council’s drains during construction, according to the civil designs.




Authorised Managing Director                UNCONTROLLED WHEN PRINTED                                    Page 11 of 14
Commencement Date: 27 August 2020                IMS-4-T3 Version 3                         Review Date: 27 August 2022

Page 13

                   Construction Management Plan



5.0 Appendices
  5.1   Appendix                 1                –   Site   Layout


[OCR of page images]
Construction Management Plan deluca

5.0 Appendices

5.1 Appendix 1 - Site Layout

Legend
—o—_o— Temporary Fencing
[5 “CC sic ottice

= on

| TT | Pedestrian Walkway
+ _ Vehicle Entry / Exit

 

     
  

\
oa aaa
v

is eee gene

N

Z

‘SITE PARKING
=| ano vay cow |

M/F Amenities

Designated Parking

 

 

—>
i Emergency Evac.
' Point
i
: access Vehicle Access Gate
i
I PEDESTRIAN Pedestrian Access
i “= Gate
:
i 4 Temporary Power
|
a Water Point

Fire Extinguishers

First Aid

u
a
Zw Bin

 

 

 

 

Site Layout Plan

Noosa Youngcare, Noosa Heads

 

Page 14

                                       Construction Management Plan
5.0         Appendices
      5.2    Appendix 2 – Erosion & Sediment Plan




                                       Authorised Managing Director        UNCONTROLLED WHEN PRINTED                 Page 2 of 14
                                       Commencement Date: 27 August 2020        IMS-4-T3 Version 3     Review Date: 27 August 2022

Page 15

                                Construction Management Plan

5.3   Appendix 3 – Construction Program




                                Authorised Managing Director        UNCONTROLLED WHEN PRINTED                 Page 3 of 14
                                Commencement Date: 27 August 2020        IMS-4-T3 Version 3     Review Date: 27 August 2022

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.