Construction Management Plan

Table of Contents
  Amendments ................................................................................................................................................... 2
  Distribution ...................................................................................................................................................... 2
1.0          Introduction .................................................................................................................................... 4
  1.1             Purpose ............................................................................................................................................ 4
  1.2             Scope ............................................................................................................................................... 4
  1.3             Proposed Works .............................................................................................................................. 4
  1.4             Site location ..................................................................................................................................... 4
  1.5             Precedence ...................................................................................................................................... 5
  1.6             Interface with other project plans and processes ........................................................................... 5
2.0                Construction Management ............................................................................................................. 6
  2.1             Approach ......................................................................................................................................... 6
  2.2             Approvals ......................................................................................................................................... 6
  2.3             Site security ..................................................................................................................................... 7
  2.4             Public / Worker safety ..................................................................................................................... 7
  2.5             Hoarding and Temporary Fencing ................................................................................................... 7
3.0               Construction Methodology ............................................................................................................. 8
  3.1       Demolition and excavation .............................................................................................................. 8
  3.2       Substructure works.......................................................................................................................... 8
  3.3 Structure ................................................................................................................................................... 8
  3.4       Services and finishes ........................................................................................................................ 9
  3.5       External works ................................................................................................................................ 9
  3.6 Construction sequence and planning ........................................................................................................ 9
  3.7 Material handling .................................................................................................................................... 10
  Material handling will be complete manually around the site, using mechanical aids as required. ............ 10
  3.7.1 Mobile cranes ....................................................................................................................................... 10
  3.7.2 Concrete handling ................................................................................................................................ 10
  3.7.3 Rubbish removal ................................................................................................................................... 10
4.0         Environmental ............................................................................................................................... 11
  4.1             General .......................................................................................................................................... 11
  4.2             Noise and vibration management ................................................................................................. 11
  4.3             Dust management ......................................................................................................................... 11
  4.4             Stormwater and sediment control ................................................................................................ 11
5.0               Appendices ...................................................................................................................................... 1
   5.1            Appendix 1 – Site Layout 1
   5.2            Appendix 2 - Erosion and Sediment Control Plan
   5.3            Appendix 3 - Construction Program




Authorised Managing Director                                     UNCONTROLLED WHEN PRINTED                                                            Page 1 of 14
Commencement Date: 27 August 2020                                     IMS-4-T3 Version 3                                                Review Date: 27 August 2022
Log in to download the original file

Construction Management Plan V2.pdf · 1.3 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.