Log in to see the plans as drawnConstruction Management Plan
4.0 Environmental
4.1 General
The objective of this section is to identify the proposed methods that will be employed to minimise the impact
of noise, vibration and air quality in the vicinity of the development.
4.2 Noise and Vibration Management
The normal hours of work will typically be 7:00am to 6:00pm, Monday to Saturday and 9:00am to 5:00pm
Sunday and public holidays according to the development approval conditions. Noise management will
generally be in accordance with the QLD DEHP environmental noise management criteria. It is anticipated
that all contractor plant is regularly maintained and log books are supplied, ensuring that there are no excess
noise emissions. Where it is practical, electric machinery will be used in lieu of mechanical devices. All
subcontractors will be responsible for managing noise and vibration in accordance with their project specific
management plans.
All after hour’s works will be subject to consultation with the Noosa Council, which will occur at all times, prior
to any works being scheduled. All businesses and surrounding residents will be given notification of all the
proposed after hours works prior to the works commencing, which will include details of the works and the
time to undertake each activity.
4.3 Dust Management
Dust control measures will be implemented as required throughout construction, and will be in accordance
with QLD workplace health and safety regulations and Environmental Protection Act. Dust management will
be most critical during the footing and in-ground services installation, with the subcontractors for these trades
specifically dealing with dust management within their project specific management plans. Measures that will
be employed include:
• Site Perimeter – A 1.8m high sheeted/shade cloth hoarding will be provided in all areas where
external works are occurring.
• Excavation – water down working surfaces as required. Minimise stock piling of material.
Maintaining stabilised access roads and driveway.
• Construction – maintain a high level of housekeeping to minimise likelihood of windblown dust.
4.4 Stormwater and Sediment Control
A sediment and erosion control plan has been developed by Neil Mckenzie and Associates (Appendices - 2)
and will be implemented as part of the bulk excavation works. This will be maintained during the construction
phase to ensure that stormwater does not enter adjoining properties, and that all water that enters the council
stormwater system does not contain silt or other contaminants. The following are possible solutions during
each phase of construction which will be developed further and consolidated into the overall management
plan:
• Excavation – at the commencement of these works, screens and bunding at the perimeter of the site
where stormwater may run off, will be installed. The existing bunding will be reviewed and maintained
around the existing stormwater drains
• Diligent housekeeping will be implemented to minimise risk of dust/debris being washed into pits
• Construction – Installed drainage pits will be bunded or have filter cloth applied to ensure debris and
silt does not enter the council’s drains during construction, according to the civil designs.
Authorised Managing Director UNCONTROLLED WHEN PRINTED Page 11 of 14
Commencement Date: 27 August 2020 IMS-4-T3 Version 3 Review Date: 27 August 2022