Construction Management Plan V2

of 15

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
Construction Management Plan
AMENDMENTS & DISTRIBUTION

Amendments

   (a) All controlled copies of this plan are version numbered and are subject to amendment as required and the
       relevant pages within the plan are replaced. The revision system is administered by the administrator.
   (b) Amendments are identified by the next consecutive issue indicator and the date of issue.
   (c) The project manager is required to give consideration to a re-issue of the whole plan if it is considered that
       the number of changes to the plan have a significant impact on the readability and cross referencing of
       the document. All new issues supersede all previous issues.
   (d) The document history table indicates all amendments. Recipients of new issues are responsible for the
       approved disposition of superseded pages and the updating of their copy of the Plan.
   (e) Amendments to this template may be made where specified by blue text with less than / greater than
       symbols < > either side. Amendments are formatted to black prior to issue and the < > symbols removed.
       Click on update table tab at contents page to incorporate changes.
   (f) Amendments are to be approved by the project manager and the document history table amended and
       signed.


Distribution

   Construction management plan re-issues and page revisions are distributed to the selected controlled plan
   holders as listed. Amendment control is as specified as above.
   The plan is retained on site by the project manager who ensures that it is available to subcontractors, workers,
   and others as necessary.
   Where contractually specified, the client is issued with an uncontrolled copy, unless specified otherwise.
   An electronic copy of the plan including amendments and updates are legal records and must be kept in the
   electronic folder for the project and archived according to company recordkeeping requirements.




Authorised Managing Director                 UNCONTROLLED WHEN PRINTED                                      Page 2 of 14
Commencement Date: 27 August 2020                 IMS-4-T3 Version 3                          Review Date: 27 August 2022
Log in to download the original file

Construction Management Plan V2.pdf · 1.3 MB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.