2018-07-10 Planning & Environment Committee Agenda

of 86

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Very large file: it may take a few minutes

The original of this document is very large (15.6 MB). Opening the original or downloading it may take a few minutes. Please be patient and don't click again. The page text is quick to read. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.

PLANNING & ENVIRONMENT COMMITTEE MEETING AGENDA                                        10 JULY 2018


RECOMMENDATION
That Council note the report by the Coordinator Planning to the Planning & Environment
Committee Meeting dated 10 July 2018 regarding Application No. 132003.221152.6 for a request
to change a Development Permit for Material Change of Use for a dwelling house to include a lift
accessed by a subterranean tunnel situated at 12 Park Road, Noosa Heads and:
A.   Agree to the change for a lift and subterranean access tunnel subject to the following
     additional conditions:
     Additional Conditions July 2018 (Subterranean pedestrian access and lift)
     62.   Development undertaken in accordance with this approval must comply with the
           approved plans of development. The approved plans are listed in the following table
           unless otherwise amended by these conditions.
      Plan No.     Rev.     Plan/Document Name                                         Date
      CD 5.01      P1       Axonometric Site Plan, prepared by Tim Ditchfield          31.01.2018
                            Architects
      CD 2.01      P3       Ground Floor Plan, prepared by Tim Ditchfield Architects   15.01.2018
      CD 2.02      P3       Upper Floor Plan, prepared by Tim Ditchfield Architects    15.01.2018
      CD 3.01      P3       West Elevation, prepared by Tim Ditchfield Architects      14.01.2018
      CD 4.01      P2       Section A-A, prepared by Tim Ditchfield Architects         15.01.2018
                            Amended ’Construction Management Plan’                     26.09.2017
                   D        Tree Protection Plan, prepared by Myles Baldwin Design     06/04/2018

           Retention of Existing Trees
     63.   All works must be carried out in accordance with Miles Baldwin Design report listed
           within this Decision Notice and the following requirements:
           a.    No further works, machinery or storage of materials are to be located within the
                 undeveloped portion of the Tree Protection Zone of Tree 28, the Endiandra
                 sieberi (Corkwood), located immediately north of the proposed lift access
                 walkway entrance
           b.    Adherence to the recommendations laid out in AS4970-2009 Protection of trees
                 on development sites throughout the remaining build.
           c.    Establish a Tree Protection Zone as per AS4970 requirements
           d.    Tree 28, the Endiandra sieberi (Corkwood), must be monitored and protected
                 from construction activities in accordance with an operational works approval
                 which details the following information:
                 i.       an advanced arboriculture inspection of the root plate and collar in
                          accordance with the ISA Tree Risk Assessment procedure. The
                          arboriculture inspection must be in the company of Council’s delegate.
                          The permit applicant shall meet the reasonable cost of Council’s delegate
                          attending the inspection.
                 ii.      landscaping works within the tree protection zone must be undertaken
                          under the direction of the Project Arborist.
           Landscaping Works
     64.   The development site must be landscaped. The works must be undertaken generally
           in accordance with the Miles Baldwin Design report listed within this Decision Notice
           and a further Operational Works approval. The Operational Works must include the
           following at a minimum:

                                                                                       Page 31 of 86
Log in to download the original file

2018-07-10 Planning & Environment Committee Agenda(PDF, 15MB).pdf · 15.6 MB (very large file)

Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.