Appendix D - Erosion and Sediment Control Plan

Attached to the e-mail Operational Works Application - DA Form 1 - Town Planning Report - Global Stability Assessment Report - Earthworks Compaction Report - Erosion and Sediment Control Plan - 36 Tunba Court Cooroy Mountain.

of 8

Page text shows just the words. Original shows the document exactly as it was published.

Page text read automatically using OCR, there may be inaccuracies

Plans and drawings

This document appears to be plans or drawings. Its page text below holds only the words printed on the drawings, without the drawings themselves, so it may be jumbled or hard to follow. To see the plans as drawn, choose Original above or download the file (both need you to log in).

Log in to see the plans as drawn
EROSION AND SEDIMENT CONTROL PLAN (36 Tunba Court, Cooroy Mountain)
EARTHWORKS PHASE                                                                                                   SITE FEATURES


                                                                                                                           Overland Flow


                                                                                                                          Construction Area



                                                                                                             EROSION AND SEDIMENT CONTROLS


                                                                                                                            Diversion Channel (refer Standard Drawing DC-01,
                                                                                                                            Appendix A)


                                                                                                                            Sediment barrier use Coir logs or Silt fence (refer
                                                                                                                            Appendix A for Standard Drawings)



                                                                                                            ORDER OF WORK
                                                                                                            1. Survey and mark boundaries, access, no-go zones, construction
                                                                                                            pads, diversion drains, stockpiles and laydown areas,.
                                                                                                            2. Install preliminary erosion and sediment controls and clean-water diversions.
                                                                                                            3. Strip topsoil, removal of woody vegetation and stockpile
                                                                                                            4. Surface levels shall be graded and filled to ensure all stormwater runoff is
                                                                                                            directed through erosion and sediment controls and towards the Sediment
                                                                                                            Controls
                                                                                                            3. Temporary and permanent erosion and drainage controls shall be installed
                                                                                                            systematically as works progress.
                                                                                                            4. For cut and fill batters , temporary toe drainage will be maintained as works
                                                                                                            progress.
                                                                                                            5. Batters will be protected as works progress.
                                                                                                            6. Cover any disturbed areas within 5 days or if rainfall predicted (70% chance
                                                                                                            of rainfall >5mm within 24 Hours or 80% chance of rainfall >10mm within 48
                                                                                                            Hours).




                                                     Client                                                         PROJECT TITLE                       DRAWING TITLE
                                                                                                                    36 Tunba Court, Cooroy Moun-        Erosion and Sediment Control Plan
                                                     Geoff & Tamara Hussin                                          tain (new shed)                     Earthworks Phase
                                                                             19 Central Park Drive, Yandina 4561
                                                                             www.aussieenvironmental.com.au                                                                       Drawing No.
                                                                                                                                                                                  ESCP03
Log in to download the original file

Appendix D - Erosion and Sediment Control Plan.pdf · 7.9 MB (large file)

Large file: the download may take up to a minute.

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.