Original source · versioned page text
Attachment 2 - Negotiated Decision Notice MCU16-0130
Attached to the e-mail Change to DA - MCU16/0130.01.msg.
Noosa Council documents
MCU16/0130
Stormwater Drainage
31. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with an Operational
Works approval and be generally in accordance with drawing number 16789-SK001
Revision A dated 1 February 2017 prepared by TOD Engineers and Project Managers
Electricity and Telecommunication Services
32. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits and
pipes to accommodate the future connection of optic fibre technology
telecommunications.
33. Certification must be submitted to Council from all relevant service providers which
certifies that the development has met the requirements of this Decision Notice and all
applicable legislation at the time of construction.
Easements
34. Unless otherwise agreed in writing by the relevant service provider, any public or third
party infrastructure located on the subject site must be placed within an easement
registered against the title of the property.
35. All easements must be designed in accordance with the planning scheme and granted
at no cost to the Grantee. Where the Grantee is Council or a service authority, the
easement documentation must be in accordance with the Grantee’s standard easement
terms. Draft easement documentation must be submitted to Council for endorsement.
36. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
37. All fill and associated batters must be undertaken in accordance with an Operational
Works approval, and contained entirely within the subject site unless written permission
from the respective landowner(s) is provided to Council.
38. All retaining walls must be designed and constructed in accordance with the planning
scheme and must be certified by an RPEQ where exceeding 1.0m in height. All retaining
walls that are publicly accessible and exceed 1.0m in height must be fitted with a
commercial grade safety fence.
Damage to Services and Assets
39. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
5. REFERRAL AGENCIES
Not applicable.
Page 6 of 11
Document Set ID: 20586157
Version: 6, Version Date: 24/05/2018 Print Date: 24 May 2018, 11:22 AM
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.