Ernest St, Goodchap St, Hilton Tce, $50,000 This intersection has been identified as the
Noosaville intersection Priority 1 intersection recommended for
upgrading from the Draft Traffic Study. (Detailed
analysis of the intersection upgrade
requirements will be presented at the traffic
workshop in early September 2015)
Poinciana Ave, Moorindil St, $50,000 This intersection has been identified as the
Tewantin intersection Priority 2 intersection recommended for
upgrading from the Draft Traffic Study. (Detailed
analysis of the intersection upgrade
requirements will be presented at the traffic
workshop in early September 2015)
Main Beach Boardwalk, Noosa $40,000 $500,000 was allocated in the 2014/2015 capital
Heads works programme for construction of the
“missing link” section of boardwalk between the
Noosa Heads Surf Club and Park Road (90
metres). These funds have since been
reallocated to the 2016/2017 forward
programme and adjusted to $700,000.
The current design is a timber boardwalk at
ground surface level. Based on feedback and
lessons learnt from previous stages it is being
asked whether this is the most appropriate
design considering the whole of life costs.
It is proposed to review the current design and
look at modifying it to concrete surfacing with
feature and build out sections constructed of
timber boardwalk. This may involve engaging
structural consultants to revise design drawings,
cost estimates and structural details in
collaboration with Council’s Design Team.
Lake Weyba Dr Noosaville $20,000 Planning & preliminary design for proposed bus
turnaround facilities. (A letter has been sent to
TransLink from CEO seeking joint funding)
Pomona Precinct $20,000 Pedestrian linkages planning for town centre
required to match future program.
Cooroy Town Centre $10,000 Pedestrian linkages planning for town centre
required to match future program.
Tewantin Bypass, Beckmans Rd $10,000 Concept, planning and preliminary design for
Noosaville duplication and intersection upgrade to reinforce
Council’s technical position with DTMR and to
drive successful outcome.
Myall St/Elm St Cooroy intersection $10,000 Concept, planning and preliminary design for
duplication and intersection upgrade to reinforce
Council’s technical position with DTMR and to
drive successful outcome.
Page 22 of 40
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.